Category:Inspection Plan
MONTHYEARML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 IR 05000333/20220062023-03-0101 March 2023 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2022006) ML22321A0102022-11-17017 November 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20220052022-08-31031 August 2022 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2022005) IR 05000333/20210062022-03-0202 March 2022 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021006) ML22005A0232022-01-0505 January 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000333/2022010 IR 05000333/20210052021-09-0101 September 2021 Updated Inspection Plan for the James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021005) IR 05000333/20200062021-03-0303 March 2021 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2020006) ML21041A1932021-02-10010 February 2021 Request for Information for a Triennial Baseline Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Inspection; Inspection Report (05000333/2021011) IR 05000333/20200052020-08-31031 August 2020 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2020005) IR 05000333/20190062020-03-0303 March 2020 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2019006) ML19326A9262019-11-22022 November 2019 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000333/2019005) IR 05000333/20180062019-03-0404 March 2019 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2018006) IR 05000333/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000333/2018005) IR 05000333/20170062018-02-28028 February 2018 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Reports 05000333/2017006, 05000333/2017402, and 05000333/2017501) IR 05000333/20170052017-08-28028 August 2017 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2017005) IR 05000333/20160062017-03-0101 March 2017 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2016006) IR 05000333/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2016005) IR 05000333/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015006) IR 05000333/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015005) IR 05000333/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014001)(w/Inspection Plan) ML14247A4532014-09-0404 September 2014 Fitzp Notification of Conduct of a Triennial Fire Protection Baseline Inspection - 90 Day Letter Rev 1 IR 05000333/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014006) ML14177A7752014-06-24024 June 2014 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000333/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013001)(w/Inspection Plan) IR 05000333/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013006) IR 05000333/20120012013-03-0404 March 2013 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333-12-001) ML12244A3412012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 James A. FitzPatrick Nuclear Power Plant IR 05000333/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000333/2011001) ML1124208192011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - James A. Fitzpatrick Nuclear Power Plant IR 05000333/20100012011-03-0404 March 2011 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2010001) ML1024402772010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - James A. Fitzpatrick Nuclear Power Plant ML1006214222010-03-0303 March 2010 Annual Assessment Letter - James A. Fitzpatrick, (IR 05000333-10-001) ML0924401472009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20090012009-03-0404 March 2009 Annual Assessment Letter, James A. FitzPatrick Nuclear Power Plant (Report 05000333/2009001) ML0824703132008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, James A. Fitzpatrick IR 05000333/20080012008-03-0303 March 2008 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2008001) ML0734709442007-12-13013 December 2007 ROP 8 - Fitzpatrick - Change to Inspection Plan, 12/13/07 ML0724309402007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20070012007-03-0202 March 2007 Annual Assessment Letter - James A. Fitzpatrick Nuclear Power Plant (Report 05000333-07-001) ML0606202432006-03-0202 March 2006 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Station (Report 05-333/2006001) ML0506105112005-03-0202 March 2005 Annual Assessment Letter 2005001-Fitzpatrick ML0424402522004-08-30030 August 2004 FitzPatrick Station ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323902312003-08-27027 August 2003 2003 - Mid-Cycle Performance Review and Inspection Plan for FitzPatrick Nuclear Power Plant ML0305807282003-03-0303 March 2003 2003 - Annual Assessment Letter - Fitzpatrick Nuclear Power Plant (50-333/2003-001) IR 05000333/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Fitzpatrick Nuclear Plant (Report No. 50-333/02-001) 2024-01-18
[Table view] Category:Letter
MONTHYEARIR 05000333/20230042024-02-0707 February 2024 Integrated Inspection Report 05000333/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200012/2023001 ML24037A0102024-02-0606 February 2024 Requalification Program Inspection ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML24004A2302024-01-0808 January 2024 Project Manager Reassignment ML23356A0832024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0058 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines JAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20234012023-12-0808 December 2023 Cybersecurity Inspection Report 05000333/2023401 (Cover Letter Only) RS-23-126, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use IR 05000333/20230032023-11-13013 November 2023 Integrated Inspection Report 05000333/2023003 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000333/20230102023-10-26026 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000333/2023010 JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use IR 05000333/20233012023-10-19019 October 2023 Initial Operator Licensing Examination Report 05000333/2023301 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20230022023-08-0707 August 2023 Integrated Inspection Report 05000333/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance ML23208A1622023-07-27027 July 2023 Operator Licensing Examination Approval IR 05000333/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000333/2023402 IR 05000333/20230112023-07-25025 July 2023 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000333/2023011 IR 05000333/20235012023-07-20020 July 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000333/2023501 JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation IR 05000333/20234202023-06-26026 June 2023 Security Baseline Inspection Report 05000333 2023420 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report IR 05000333/20230012023-05-0303 May 2023 Integrated Inspection Report 05000333/2023001 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report IR 05000333/20230122023-04-13013 April 2023 Quadrennial Fire Protection Inspection Report 05000333/2023012 ML23095A3722023-04-0505 April 2023 2023 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000333/20220042023-03-20020 March 2023 Integrated Inspection Report 05000333/2022004 JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 2024-02-07
[Table view] |
Text
[Type here]
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 November 22, 2019 Mr. Bryan C. Hanson Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - NOTIFICATION OF CONDUCT OF A FIRE PROTECTION TEAM INSPECTION
Dear Mr. Hanson:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct a fire protection team inspection at your James A. FitzPatrick Nuclear Power Plant starting in March 2020. The inspection will be conducted in accordance with Inspection Procedure 71111, Attachment 21N.05, Fire Protection Team Inspection (FPTI), dated June 12, 2019. The inspection team will be led by Ms. Carey Bickett, a Senior Reactor Inspector from the NRC Region I Office.
The inspection will verify that plant structures, systems, and components, and/or administrative controls credited in the approved fire protection program can perform their licensing basis function.
The schedule for the inspection is as follows:
Information Gathering Visit: March 3-5, 2020 Onsite Inspection: Weeks of March 16, 2020 and March 30, 2020 The purpose of the information gathering visit is to obtain information and documentation needed to support the inspection and to become familiar with the stations fire protection program, fire protection features, post-fire safe shutdown capabilities, and plant layout. During the information gathering visit, the team leader will select the specific samples to be reviewed during the onsite inspection weeks.
The enclosure lists the types of documents that will be needed prior to the information gathering visit. Please provide the referenced information to the Region I office by February 12, 2020.
Following sample selection, additional documents will be requested specific to those samples.
Your cooperation and support during this inspection will be appreciated.
If you have questions concerning this inspection, or the inspection team's information request or logistical needs, please contact Ms. Carey Bickett, Team Leader at (610) 337-5317, or via e-mail at carey.bickett@nrc.gov.
B. Hanson 2 This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, under Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-333 License No. DPR-59
Enclosure:
Fire Protection Team Inspection Supporting Documentation cc: Distribution via ListServ
ML19326A926 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRS RI/DRS NAME CBickett GDentel DATE 11/21/19 11/22/19 Fire Protection Team Inspection Supporting Documentation If you have any questions regarding this information request, please contact Ms. Carey Bickett at (610) 337-5317 or via e-mail at carey.bickett@nrc.gov.
Electronic format is preferred. If electronic media is made available via an internet-based document management system, then document access must allow inspectors to download, save, and print the documents in the NRC's Regional office. Paper records (hard copy) are acceptable. At the end of the inspection, the documents in the teams possession will not be retained.
This document request is based on typical documents that a generic plant might have. As such, this generic document request is not meant to imply that any specific plant is required to have all of the listed documents. It is recognized that some documents listed below may not be available for your plant. In addition, the document titles listed below are based on typical industry document names; your plant specific document titles may vary.
Note that following sample selection, additional documents will be requested specific to those samples.
Please provide these documents to the inspection team leader in the Region I Office by February 12, 2020:
- 1. Post-Fire Safe Shutdown or Alternative Shutdown Analysis
- 2. List of post-fire safe shutdown components (i.e., safe shutdown equipment list), if not already included in item (1) above
- 3. Fire Hazards Analysis Report
- 4. Fire Probabilistic Risk Assessment (Fire PRA) Summary Document. If a Fire PRA is not available, please provide the Individual Plant Examination for External Events (Fire Chapter Only)
- 5. Fire Protection Program and/or Fire Protection Plan Document(s)
- 6. Fire Protection Program implementing procedures, if not already included in item (5) above
- 7. Fire Protection Design Basis Document(s), if available
- 8. List of all safety evaluations performed to support any plant modifications since May 2017.
Include a short description and/or title of each evaluation.
- 9. List of all 10 CFR 50.59 applicability determinations and screens (date, number, title) performed since May 2017. Include a short description and/or title of each document.
- 10. List of all fire protection system impact screening reviews for any design changes, modifications, or temporary modifications completed since May 2017 (e.g., a Generic Letter 86-10 review, LS-AA-128 review, etc.). Include a short description and/or title of each review.
Enclosure
- 11. List of fire protection system, post-fire safe shutdown, or alternative shutdown design changes completed since May 2017. Include a short description and/or title of each change.
- 12. List of the top 25 highest fire CDF scenarios, if available
- 13. List of the top 25 highest fire LERF scenarios, if available
- 14. From your most recent site-specific PRA, including external events and fires (if available):
Two risk rankings of components: one sorted by Risk Achievement Worth (RAW) and the other sorted by Birnbaum Importance A list of the top 200 cut sets
- 15. Risk ranking of operator actions and/or recovery actions from your site-specific PRA sorted by Risk Achievement Worth
- 16. List of current fire protection system impairments, including description
- 17. One-line diagram of the electrical distribution system
- 18. Copy of the Updated Final Safety Analysis Report
- 19. Copy of the Technical Requirements Manual
- 20. Copy of the Quality Assurance Program Manual (including specific fire protection Quality Assurance Manual, if applicable)
- 21. Copy of the Corrective Action Program Procedure(s)
- 22. List of station procedures used to respond to fire (i.e., Emergency Operating Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures). Include the procedure number, title, and current revision
- 23. List of open and closed issue reports for post-fire safe shutdown or alternative shutdown issues since May 2017 (e.g., issues affecting safe shutdown analysis, fire hazards analysis, safe shutdown operating procedures and/or training, timeline evaluations for operator actions, etc.). Include the issue report number and a brief description.
- 24. List of open and closed issue reports for fire protection system issues (e.g., fire pumps, detection, suppression, etc.) since May 2017. Include the issue report number and a brief description.
- 25. List of open and closed issue reports related to the fire brigade or fire drills since May 2017.
Include the issue report number and a brief description.
- 26. Copies of the following issue reports:
3999668 3999670 3999671 3999673 4000149 4000151 4006010 4006553 4006563 4006592 4006662 4011547 4011710 4012033 4012160 4012322
- 27. Copies of any self-assessments performed, and corrective action documents generated, in preparation for this fire protection team inspection.