UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 March 2, 2006 Mr. Theodore Sullivan Site Vice President Entergy Nuclear Northeast James A. FitzPatrick Nuclear Power Plant Post Office Box 110 Lycoming, NY 13093
SUBJECT:
ANNUAL ASSESSMENT LETTER - JAMES A. FITZPATRICK NUCLEAR POWER PLANT (REPORT 05000333/2006001)
Dear Mr. Sullivan:
On February 6, 2006, the NRC staff completed its performance review of James A. FitzPatrick Nuclear Power Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2005.
The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Official Use Only - Security-Related Information will include the physical protection review and resultant inspection plan.
Overall, FitzPatrick operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct the reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through September 30, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
T. Sullivan 2
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (610)337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Brian J. McDermott, Chief Projects Branch 2 Division of Reactor Projects Docket No.
50-333 License No.
Enclosure:
FitzPatrick Nuclear Power Plant Inspection/ Activity Plan cc w/encl:
G. Taylor, CEO, Entergy Operations, Inc.
M. Kansler, President, Entergy Nuclear Operations, Inc (ENO)
J. Herron, Sr, VP and Chief Operating Officer, (ENO)
C. Schwarz, VP, Operations Support (ENO)
K. Mulligan, General Manager, Plant Operations (ENO)
O. Limpias, VP, Engineering (ENO)
J. McCann, Director, Licensing (ENO)
C. Faison, Manager, Licensing (ENO)
M. Colomb, Director of Oversight (ENO)
D. Wallace, Director, Nuclear Safety Assurance (ENO)
R. Plasse, Acting Manager, Regulatory Compliance (ENO)
T. McCullough, Assistant General Counsel (ENO)
P. Smith, President, New York State Energy Research and Development Authority P. Eddy, New York State Department of Public Service S. Lyman, Oswego County Administrator Supervisor, Town of Scriba C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law J. Sniezek, PWR SRC Consultant M. Lyster, PWR SRC Consultant S. Lousteau, Treasury Department, Entergy Services
T. Sullivan 3
Distribution w/encl: (VIA E-MAIL)
S. Collins, RA M. Dapas, DRA B. Holian, DRP Director D. Lew, DRP Deputy Director B. McDermott, DRP E. Cobey, DRP D. Jackson, DRP B. Sosa, OEDO J. Boska, NRR R. Laufer, NRR R. Clark, NRR P. Tam, NRR G. Hunegs, DRP - NRC Senior Resident Inspector D. Dempsey, DRP, Resident Inspector K. Kolek, Resident OA N. Sheehan, PAO R. Blough, DRS Director M. Gamberoni, DRS Deputy Director R. Lorson, DRS J. Rogge, DRS L. Doerflein, DRS R. Conte, DRS D. White, DRS J. White, DRS RidsNrrDirsIpab Institute of Nuclear Power Operations (INPO)
Region I Docket Room (with concurrences)
DOCUMENT NAME: S:\\ROP-6 EOC Review\\ROP-6 Annual Assessment Letters\\FITZ EOC.wpd SISP Review Complete: _DEJ1______ (Reviewers Initials)
After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME GHunegs/DEJ DJackson/DEJ BMcDermott/BJM DATE 03/02/06 03/02/06 03/0206 OFFICIAL RECORD COPY
FitzPatrick Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2006 14:59:33 Report 22 2
4/15EXM
- SRO ONLY INITIAL EXAM RETAKE Not Applicable 04/15/2006 04/15/2006 1
U01699 FY06 - FITZPATRICK RETAKE OPERATOR EXAM 3
7111111B
- L.O..REQUAL. PROG. + P/F REVIEW Baseline Inspections 05/22/2006 05/26/2006 1
7111111B IP Licensed Operator Requalification Program Baseline Inspections 05/29/2006 06/02/2006 1
7111111B IP Licensed Operator Requalification Program 4
- PI&R Baseline Inspections 07/10/2006 07/14/2006 1
71152B IP Identification and Resolution of Problems Baseline Inspections 07/24/2006 07/28/2006 1
71152B IP Identification and Resolution of Problems 1
71151
- EP PI VERIFICATION Baseline Inspections 08/20/2006 08/21/2006 1
71151 IP Performance Indicator Verification 1
71121
- OCC RAD SAFETY Baseline Inspections 09/18/2006 09/22/2006 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/18/2006 09/22/2006 1
7112102 IP ALARA Planning and Controls 1
71121
- OCC RAD SAFETY Baseline Inspections 10/16/2006 10/20/2006 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 10/16/2006 10/20/2006 1
7112102 IP ALARA Planning and Controls Baseline Inspections 10/16/2006 10/20/2006 1
71151 IP Performance Indicator Verification 1
7111108G
- INSERVICE INSPECTION Baseline Inspections 10/16/2006 10/20/2006 1
7111108G IP Inservice Inspection Activities - BWR 3
7111117B
- MODS AND 50.59 Baseline Inspections 11/27/2006 12/01/2006 1
7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 11/27/2006 12/01/2006 1
7111117B IP Permanent Plant Modifications 1
71121
- OCC RAD SAFETY Baseline Inspections 02/05/2007 02/09/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 02/05/2007 02/09/2007 1
7112102 IP ALARA Planning and Controls 4
7111401
- EP EXERCISE & PI VERIFICATION Baseline Inspections 03/05/2007 03/09/2007 1
7111401 IP Exercise Evaluation Baseline Inspections 03/05/2007 03/09/2007 1
71151-EP01 IP Drill/Exercise Performance Baseline Inspections 03/05/2007 03/09/2007 1
71151-EP02 IP ERO Drill Participation Baseline Inspections 03/05/2007 03/09/2007 1
71151-EP03 IP Alert & Notification System 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 04/09/2007 04/13/2007 1
7112202 IP Radioactive Material Processing and Transportation 1
711107
- HEAT SINK INSP Baseline Inspections 05/07/2007 05/11/2007 1
7111107B IP Heat Sink Performance This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
FitzPatrick Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2006 14:59:33 Report 22 1
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 06/11/2007 06/15/2007 1
7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 7
7111121
- CDBI Baseline Inspections 06/11/2007 06/15/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 06/25/2007 06/29/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 07/09/2007 07/13/2007 1
7111121 IP Component Design Bases Inspection Baseline Inspections 07/16/2007 07/20/2007 1
7111121 IP Component Design Bases Inspection 1
7112203
- PUB RAD SAFETY - REMP Baseline Inspections 06/25/2007 06/29/2007 1
7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 3
10/15EXM
- OPERATOR LICENSING INITIAL EXAM Not Applicable 09/17/2007 09/21/2007 1
U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM 1
71121
- OCC RAD SAFETY Baseline Inspections 09/10/2007 09/14/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/10/2007 09/14/2007 1
7112102 IP ALARA Planning and Controls This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.