UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 August 31, 2007 Mr. Peter T. Dietrich Site Vice President Entergy Nuclear Northeast James A. FitzPatrick Nuclear Power Plant Post Office Box 110 Lycoming, NY 13093

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

JAMES A. FITZPATRICK NUCLEAR POWER PLANT

Dear Mr. Dietrich:

On August 15, 2007, the NRC staff completed its performance review of the James A. FitzPatrick Nuclear Power Plant for the first half of the calendar year 2007 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as, Official Use Only--Security Information, will include the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter of 2007 at the James A. FitzPatrick Nuclear Power Plant was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's

P. Dietrich 2 document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

The NRC is currently evaluating the scope and frequency of all baseline inspection procedures.

If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5171 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Eugene W. Cobey, Chief Projects Branch 2 Division of Reactor Projects Docket No. 50-333 License No. DPR-59

Enclosure:

FitzPatrick Nuclear Power Plant Inspection/Activity Plan cc w/encl:

G. J. Taylor, Chief Executive Officer, Entergy Operations J. Wayne Leonard, Chairman & CEO, Entergy Operations M. R. Kansler, President & CEO / CNO, Entergy Nuclear Operations, Inc.

J. T. Herron, Senior Vice President, Entergy Operations M. Balduzzi, Senior Vice President, Northeastern Regional Operations Senior Vice President of Engineering and Technical Services J. DeRoy, Vice President, Operations Support K. Mulligan, General Manager, Plant Operations O. Limpias, Vice President, Engineering (ENO)

J. Ventosa, General Manager, Engineering (ENO)

J. McCann, Director, Nuclear Safety and Licensing (ENO)

Manager, Licensing (ENO)

E. Harkness, Director of Oversight (ENO)

Director, Nuclear Safety Assurance J. Costedio, Manager, Licensing W. Dennis, Assistant General Counsel (ENO)

M. Balboni, Deputy Secretary for Public Safety, New York State P. Eddy, New York State Department of Public Service P. Smith, President, New York State, Energy, Research, and Development Authority S. Lyman, Oswego County Administrator Supervisor, Town of Scriba C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law J. Sniezek, PWR SRC Consultant M. Lyster, PWR SRC Consultant cc w/encl:

P. Dietrich 3 J. Doering, PWR SRC Consultant S. Lousteau, Treasury Department, Entergy Services J. Spath, Program Director, New York State Energy Research and Development Authority Institute of Nuclear Power Operations (INPO)

P. Dietrich 3 document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5171 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Eugene W. Cobey, Chief Projects Branch 2 Division of Reactor Projects Docket No. 50-333 License No. DPR-59

Enclosure:

FitzPatrick Nuclear Power Plant Inspection/Activity Plan cc w/encl:

G. J. Taylor, Chief Executive Officer, Entergy Operations J. Wayne Leonard, Chairman & CEO, Entergy Operations M. R. Kansler, President & CEO / CNO, Entergy Nuclear Operations, Inc.

J. T. Herron, Senior Vice President, Entergy Operations M. Balduzzi, Senior Vice President, Northeastern Regional Operations Senior Vice President of Engineering and Technical Services J. DeRoy, Vice President, Operations Support K. Mulligan, General Manager, Plant Operations O. Limpias, Vice President, Engineering (ENO)

J. Ventosa, General Manager, Engineering (ENO)

J. McCann, Director, Nuclear Safety and Licensing (ENO)

Manager, Licensing (ENO)

E. Harkness, Director of Oversight (ENO)

Director, Nuclear Safety Assurance J. Costedio, Manager, Licensing W. Dennis, Assistant General Counsel (ENO)

M. Balboni, Deputy Secretary for Public Safety, New York State Energy Research and Development Authority P. Eddy, New York State Department of Public Service P. Smith, President, New York State, Energy, Research, and Development Authority S. Lyman, Oswego County Administrator Supervisor, Town of Scriba C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law J. Sniezek, PWR SRC Consultant M. Lyster, PWR SRC Consultant SUNSI Review Complete: BEW (Reviewers Initials)

DOCUMENT NAME: S:\ROP 8 Mid Cycle Review\Letters for Mid Cycle\Branch 2 Mid-cycle letters\Fitz 2007 Mid-Cycle Letter.wpd After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME BWelling/BEW ECobey/EWC DATE 08/30/07 08/31/07 OFFICIAL RECORD COPY

Letter to Peter T. Dietrich from David C. Lew dated August 31, 2007 Distribution w/encl: (via E-mail)

S. Collins, RA P. Frechette, DRS M. Dapas, DRA D. Silk, DRS D. Lew, DRP D. Screnci, PAO J. Clifford, DRP N. Sheehan, PAO M. Cox, RI OEDO R. Barkley, ORA J. Thompson, NRR D. Holody, ORA E. Cobey, DRP M. Cox, RI OEDO D. Jackson, DRP M. Kowal, NRR B. Welling, DRP J. Boska, PM NRR M. Gamberoni, DRS J. Hughey, NRR D. Roberts, DRS G. Hunegs, DRP, Senior Resident Inspector J. Trapp, DRS L. Casey, DRP, Acting Resident Inspector J. Rogge, DRS K. Kolek, Resident OA M. Sykes, DRS Region I Docket Room J. White, DRS RidsNrrDirslpab@nrc.gov L. Doerflein, DRS ROPreports@nrc.gov R. Conte, DRS L. Scholl, DRS

Page 1 of 2 FitzPatrick 08/27/2007 13:37:09 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7111121 - CDBI 6 1 IP 7111121 Component Design Bases Inspection 07/09/2007 07/13/2007 Baseline Inspections 1 IP 7111121 Component Design Bases Inspection 07/16/2007 07/20/2007 Baseline Inspections 71121 - OCC RADIATION SAFETY 1 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 11/05/2007 11/09/2007 Baseline Inspections 3/31 EXM - INITIAL OPERATOR LICENSING EXAM 6 1 U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM 03/03/2008 03/07/2008 Not Applicable 1 U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM 03/31/2008 04/04/2008 Not Applicable 1 U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM 04/07/2008 04/11/2008 Not Applicable 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 12/03/2007 12/21/2007 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 12/03/2007 12/21/2007 Baseline Inspections EP - EP PROGRAM INSPECTION 2 1 IP 7111402 Alert and Notification System Testing 02/04/2008 02/08/2008 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 02/04/2008 02/08/2008 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 02/04/2008 02/08/2008 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/04/2008 02/08/2008 Baseline Inspections 1 IP 71151-EP01 Drill/Exercise Performance 02/04/2008 02/08/2008 Baseline Inspections 1 IP 71151-EP02 ERO Drill Participation 02/04/2008 02/08/2008 Baseline Inspections 1 IP 71151-EP03 Alert & Notification System 02/04/2008 02/08/2008 Baseline Inspections 7111111B - REQUAL INSPECTION +P/F REVIEW 5 1 IP 7111111B Licensed Operator Requalification Program 05/05/2008 05/09/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 03/17/2008 03/21/2008 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 03/17/2008 03/21/2008 Baseline Inspections TRI FIRE - TRIENNIAL FIRE PROTECTION INSPECTION 3 1 IP 7111105T Fire Protection [Triennial] 04/21/2008 04/25/2008 Baseline Inspections 1 IP 7111105T Fire Protection [Triennial] 05/12/2008 05/16/2008 Baseline Inspections 71152B - PI&R 4 1 IP 71152B Identification and Resolution of Problems 07/14/2008 07/18/2008 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 07/28/2008 08/01/2008 Baseline Inspections 7111108G - INSERVICE INSPECTION 1 1 IP 7111108G Inservice Inspection Activities - BWR 09/22/2008 09/26/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1 IP 7112101 Access Control to Radiologically Significant Areas 09/22/2008 09/26/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 FitzPatrick 08/27/2007 13:37:09 Inspection / Activity Plan Report 22 07/01/2007 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 1 IP 7112102 ALARA Planning and Controls 09/22/2008 09/26/2008 Baseline Inspections MODS - MODS AND 50.59 3 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 10/20/2008 10/24/2008 Baseline Inspections 1 IP 7111117B Permanent Plant Modifications 10/20/2008 10/24/2008 Baseline Inspections MR - MAINTENANCE RULE 1 1 IP 7111112B Maintenance Effectiveness 11/03/2008 11/07/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.