MONTHYEARML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 IR 05000333/20220062023-03-0101 March 2023 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2022006) ML22321A0102022-11-17017 November 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20220052022-08-31031 August 2022 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2022005) IR 05000333/20210062022-03-0202 March 2022 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021006) ML22005A0232022-01-0505 January 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000333/2022010 IR 05000333/20210052021-09-0101 September 2021 Updated Inspection Plan for the James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021005) IR 05000333/20200062021-03-0303 March 2021 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2020006) ML21041A1932021-02-10010 February 2021 Request for Information for a Triennial Baseline Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Inspection; Inspection Report (05000333/2021011) IR 05000333/20200052020-08-31031 August 2020 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2020005) IR 05000333/20190062020-03-0303 March 2020 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2019006) ML19326A9262019-11-22022 November 2019 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000333/2019005) IR 05000333/20180062019-03-0404 March 2019 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2018006) IR 05000333/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000333/2018005) IR 05000333/20170062018-02-28028 February 2018 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Reports 05000333/2017006, 05000333/2017402, and 05000333/2017501) IR 05000333/20170052017-08-28028 August 2017 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2017005) IR 05000333/20160062017-03-0101 March 2017 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2016006) IR 05000333/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2016005) IR 05000333/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015006) IR 05000333/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015005) IR 05000333/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014001)(w/Inspection Plan) ML14247A4532014-09-0404 September 2014 Fitzp Notification of Conduct of a Triennial Fire Protection Baseline Inspection - 90 Day Letter Rev 1 IR 05000333/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014006) ML14177A7752014-06-24024 June 2014 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000333/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013001)(w/Inspection Plan) IR 05000333/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013006) IR 05000333/20120012013-03-0404 March 2013 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333-12-001) ML12244A3412012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 James A. FitzPatrick Nuclear Power Plant IR 05000333/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000333/2011001) ML1124208192011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - James A. Fitzpatrick Nuclear Power Plant IR 05000333/20100012011-03-0404 March 2011 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2010001) ML1024402772010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - James A. Fitzpatrick Nuclear Power Plant ML1006214222010-03-0303 March 2010 Annual Assessment Letter - James A. Fitzpatrick, (IR 05000333-10-001) ML0924401472009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20090012009-03-0404 March 2009 Annual Assessment Letter, James A. FitzPatrick Nuclear Power Plant (Report 05000333/2009001) ML0824703132008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, James A. Fitzpatrick IR 05000333/20080012008-03-0303 March 2008 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2008001) ML0734709442007-12-13013 December 2007 ROP 8 - Fitzpatrick - Change to Inspection Plan, 12/13/07 ML0724309402007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20070012007-03-0202 March 2007 Annual Assessment Letter - James A. Fitzpatrick Nuclear Power Plant (Report 05000333-07-001) ML0606202432006-03-0202 March 2006 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Station (Report 05-333/2006001) ML0506105112005-03-0202 March 2005 Annual Assessment Letter 2005001-Fitzpatrick ML0424402522004-08-30030 August 2004 FitzPatrick Station ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323902312003-08-27027 August 2003 2003 - Mid-Cycle Performance Review and Inspection Plan for FitzPatrick Nuclear Power Plant ML0305807282003-03-0303 March 2003 2003 - Annual Assessment Letter - Fitzpatrick Nuclear Power Plant (50-333/2003-001) IR 05000333/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Fitzpatrick Nuclear Plant (Report No. 50-333/02-001) 2024-01-18
[Table view] Category:Letter
MONTHYEARIR 05000333/20230042024-02-0707 February 2024 Integrated Inspection Report 05000333/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200012/2023001 ML24037A0102024-02-0606 February 2024 Requalification Program Inspection ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML24004A2302024-01-0808 January 2024 Project Manager Reassignment ML23356A0832024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0058 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines JAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20234012023-12-0808 December 2023 Cybersecurity Inspection Report 05000333/2023401 (Cover Letter Only) RS-23-126, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use IR 05000333/20230032023-11-13013 November 2023 Integrated Inspection Report 05000333/2023003 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000333/20230102023-10-26026 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000333/2023010 JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use IR 05000333/20233012023-10-19019 October 2023 Initial Operator Licensing Examination Report 05000333/2023301 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20230022023-08-0707 August 2023 Integrated Inspection Report 05000333/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance ML23208A1622023-07-27027 July 2023 Operator Licensing Examination Approval IR 05000333/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000333/2023402 IR 05000333/20230112023-07-25025 July 2023 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000333/2023011 IR 05000333/20235012023-07-20020 July 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000333/2023501 JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation IR 05000333/20234202023-06-26026 June 2023 Security Baseline Inspection Report 05000333 2023420 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report IR 05000333/20230012023-05-0303 May 2023 Integrated Inspection Report 05000333/2023001 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report IR 05000333/20230122023-04-13013 April 2023 Quadrennial Fire Protection Inspection Report 05000333/2023012 ML23095A3722023-04-0505 April 2023 2023 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000333/20220042023-03-20020 March 2023 Integrated Inspection Report 05000333/2022004 JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 2024-02-07
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION rch 4, 2013
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR JAMES A. FITZPATRICK NUCLEAR POWER PLANT (REPORT 05000333/2012001)
Dear Mr. Colomb:
On February 13, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of James A. FitzPatrick Nuclear Power Plant (FitzPatrick). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2012 through December 31, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, FitzPatrick operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at FitzPatrick during the most recent quarter was within the Regulatory Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (Green) and one performance indicator was of low to moderate safety significance (White) in the Initiating Events cornerstone. Specifically, the Unplanned Power Changes per 7,000 Critical Hours performance indicator exceeded the Green/White threshold value in the fourth quarter of the assessment period.
Consistent with the graded approach in the NRCs ROP, this change in performance from the Licensee Response Column to the Regulatory Response Column results in a corresponding increase in the NRCs inspection and assessment oversight. Therefore, in addition to ROP baseline inspections, the NRC plans to schedule and conduct a supplemental inspection in accordance with Inspection Procedure 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area," after your staff has notified us of your readiness for this inspection. This inspection procedure is conducted to provide assurance that the root causes and contributing causes of risk significant performance issues are understood, the extent of condition and cause were identified, and the corrective actions are sufficient to prevent recurrence.
The enclosed inspection plan lists the inspections scheduled through June 30, 2014. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to the baseline inspections, the NRC will perform Inspection Procedure (IP) 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, and TI-182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan, should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
On January 25, 2012, the NRC issued a Confirmatory Order which included a severity level III traditional enforcement violation associated with willfulness. Therefore, the NRC also plans to conduct IP 92702, Follow-up on Traditional Enforcement Actions including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders and Alternate Dispute Resolution Confirmatory Orders" to follow-up on actions as documented in the Confirmatory Order.
In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Art Burritt at 610-337-5069 with any questions you have regarding this letter.
Sincerely,
/RA/
Darrell J. Roberts, Director Division of Reactor Projects Docket Nos. 50-333 License Nos. DPR-59 Enclosure: James A. FitzPatrick Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML13060A336 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP RI/DRP NAME BBickett EKnutson via email ABurritt DRoberts DATE 02/25/13 02/25/13 02/26/13 03/04/13 Distribution w/encl: (via email)
W. Dean, RA D. Lew, DRA D. Roberts, DRP M. Layton, DRP C. Miller, DRS J. Clifford, DRS A. Burritt, DRP B. Bickett, DRP S. McCarver, DRP E. Knutson, DRP, SRI B. Sienel, DRP, RI M. Rose, DRP, AA J. Cassidy, RI OEDO DRS Branch Chiefs (6)
D. Screnci, PAO, N. Sheehan, PAO N. McNamara, SLO D. Tifft, SLO D RidsNrrPMFitzPatrick Resource RidsNrrDorlLpl1-1 Resource ROPassessment Resource RidsNrrDirslpabResource
Page 1 of 2 FitzPatrick 02/25/2013 09:04:03 Inspection / Activity Plan Report 22 01/01/2013 - 06/30/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 92702 - CONF. ORDER FOLLOWUP FITZ ADR ACTION E-F 1 1 01/01/2013 03/31/2013 IP 92702 Followup On Corrective Actions For Violations And Deviations 71124 - RADIATION SAFETY INSPECTION 1 1 04/08/2013 04/12/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/08/2013 04/12/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 04/08/2013 04/12/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/08/2013 04/12/2013 IP 71124.04 Occupational Dose Assessment 7111121 - CDBI 6 1 06/10/2013 06/14/2013 IP 7111121 Component Design Bases Inspection 1 06/24/2013 06/28/2013 IP 7111121 Component Design Bases Inspection 1 07/08/2013 07/12/2013 IP 7111121 Component Design Bases Inspection 71124 - RADIATION SAFETY INSPECTION 1 1 06/03/2013 06/07/2013 IP 71124.07 Radiological Environmental Monitoring Program 1 06/03/2013 06/07/2013 IP 71151 Performance Indicator Verification 60855 - ISFSI LOADING INSPECTION 2 1 06/01/2013 08/31/2013 IP 60855 Operation Of An ISFSI 1 06/01/2013 08/31/2013 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants EX INSP - EP EXERCISE INSPECTION 2 1 08/12/2013 08/16/2013 IP 7111401 Exercise Evaluation 71124 - RADIATION SAFETY INSPECTION 1 1 08/12/2013 08/16/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 08/12/2013 08/16/2013 IP 71124.04 Occupational Dose Assessment TI 182 - DEGRAD UNDERGROUND PIPING - PHASE 2 1 1 09/09/2013 09/13/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 71124 - RADIATION SAFETY INSPECTION 1 1 10/21/2013 10/25/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/21/2013 10/25/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 10/21/2013 10/25/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 10/21/2013 10/25/2013 IP 71124.04 Occupational Dose Assessment 1 10/21/2013 10/25/2013 IP 71151 Performance Indicator Verification 4/14EXAM - FITZPATRICK INITIAL EXAM 3 1 03/10/2014 03/14/2014 U01887 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM 1 04/07/2014 04/11/2014 U01887 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 FitzPatrick 02/25/2013 09:04:03 Inspection / Activity Plan Report 22 01/01/2013 - 06/30/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71152B - PI&R BIENNIAL 4 1 04/14/2014 04/19/2014 IP 71152B Problem Identification and Resolution 1 04/28/2014 05/03/2014 IP 71152B Problem Identification and Resolution 71124 - RADIATION SAFETY INSPECTION 1 1 04/07/2014 04/11/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 04/07/2014 04/11/2014 IP 71124.02 Occupational ALARA Planning and Controls 1 04/07/2014 04/11/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 04/07/2014 04/11/2014 IP 71124.04 Occupational Dose Assessment 71124.08 - RADWASTE 1 1 05/05/2014 05/09/2014 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124 - RADIATION SAFETY INSPECTION 1 1 05/19/2014 05/23/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 05/19/2014 05/23/2014 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.