Responds to Re Safety Concerns at Facility. Insp Conducted at Facility During 861113-14 to Investigate Concerns Received from Employee Legal Project.No New Safety Issues Raised as Result of Insp
ML20212M213
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 01/13/1987
From: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lima K
AFFILIATION NOT ASSIGNED
Shared Package
ML20212M217 List:
References
NUDOCS 8701300039
Download: ML20212M213 (2)


Text

.a

. L Q - WWh; Y Kristine Rodrigues Lima 105 Brooks Street Medford, Massachusetts 02155

Dear Ms. Lima:

This refers to your letter of December 10, 1986 regarding safety concerns at Sea-brook Station. Your letter has been referred to me for response.

In July of this year, the NRC Region I Office learned of the establishment of the Employee's Legal Project of Amesbury, Massachusetts, which was designed to help current and former nuclear power plant employees to report safety problems at their work place. The Region I Office has been in frequent communication with the pro-ject's director, Ms. Sharon Tracy, since early August,1986. NRC Region I received several pieces of correspondence from the Employee's Legal Project in September and October, 1986, which provided a number of safety concerns pertaining to the Seabrook Station.

These safety concerns, as they became available, were given to the NRC Resident Inspectors as well as Public Service of New Hampshire for preliminary investigation.

In the final analysis, some 61 potential safety concerns were formulated from the various docements received from the Employee's Legal Project. In order to thoroughly investigate these concerns collectively, a special team inspection was conducted by seven NRC Region I inspectors at Seabrook during the period November 3-14, 1986. In addition to their inspection activities at the site, these inspec-tors also interviewed those former workers who had given their concerns to the Employee's Legal Project and who were willing to talk to the NRC.

The NRC Region I inspection team issued its final report on December 19, 1986.

The report concludes that the concerns raised by the Employee's Legal Project do not raise any specific new safety issues which adversely impact on safety at Sea-brook Station. At the conclusion of our inspection, we again told Ms. Tracy to contact NRC Region I immediately if she received additional concerns or more spect-fic information regarding existing concerns. NRC Region I is prepared to act promptly on'any additional information provided by the Employee's Legal Project or others.

Sincerely,

' Original signed by

? ~ ,r,tinrley Thomas E. Murley Regional Administrator 8701300039 870113 PDR ADOCKOSOOg3 H

4

. 4 Kristine Rodrigues Lima 2 ,

bec:

T. Murley W. Kane E. Wenzinger -

T. Elsasser POR (w/ original incoming letterV

/

/V RI:CRP RI:DRP f P R f.I RP asser W zi er fygj A 1l V Muf!e 1/9/87 il%

OFFICIAL RECORD COPY