Forwards Application for Amend to License DPR-16,consisting of Tech Spec Change Request 148,revising Sections 3.6 & 4.6 Re RCS Iodine Activity Limits & Surveillance Requirements. Certificate of Svc Encl.Fee Paid
ML20215M443
Person / Time
Site: Oyster Creek
Issue date: 10/23/1986
From: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
To: Zwolinski J
Office of Nuclear Reactor Regulation
Shared Package
ML20215M444 List:
References
NUDOCS 8610300250
Download: ML20215M443 (3)


Text

__

GPU Nuclear gI f 100 Interpace Parkway Parsippany New Jersey 07054 201 263-6500 TELEX 136-482 Writer's Direct Dial Number:

October 23, 1986 Mr. John A. Zwolinski, Director BWR Project Directorate No.1 Division of BWR Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Zwolinski:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Technical Specification Change Request (TSCR) No.148 In accordance with 10 CFR 50.59,10 CFR 50.90 and 10 CFR 50.91, GPU Nuclear Corporation, operator of the Oyster Creek Nuclear Generating Station, Provisional Operating License No. DPR-16, requests changes to Appendix A of that license.

Technical Specification Change Request No. 69, Revision 1, " Radiological Effluent Environmental Technical Specifications" dated October 22, 1984 proposer: changes to sections 3.6 and 4.6 concerning reactor coolant system (RCS) iodine activity limits and surveillance requirements. These changes were proposed following discussions with the NRC staff during the integrated assessment of the Systematic Evaluation Program for Topic XV-16, " Radiological Consequences of Failure of Small Lines Carrying Primary Coolant Outside Containment".

The staff recently requested re-submittal of the proposed changes regarding the reactor coolant radioactivity limits with the following additional information:

1. provide definition for DOSE EQUIVALENT Iodine-131,
2. provide limits for non-iodine radioactivity in the reactor coolant as

(

shown in Standard Technical Specifications for General Electric Boiling Water Reactors (NUREG-0123),

3. modify Limiting Condition for Operation as shown in NUREG-0123 and
4. provide annual reporting requirement for radiciodine spiking as shown in i NRC Generic Letter a5-19, " Reporting Requirement on Primary Coolant Iodine Spikes". He la e 5 l

8610300250 861023 00[ Add:dAR MM TIAMd M AVN 3 I l

PDR P

ADOCK 05000219 PDR g

l GPU Nuclear is a part of the General Pubhc Utiliaes System

Q As we have discussed with Mr. J. Donohew, NRC Project Manager for Oyster Creek, additional time is required to evaluate the need for incorporating certain infomation requested, namely, non-iodine RCS activity limit and sampling requirement following changes in themal power or off-gas level. In these areas jpplicability of the non-iodine limit given in NUREG-0123 and the existing mon 16 ring capability must be evaluated. It is estimated that approximately five months is required for the evaluation. The results of the evaluation will be forwarded and a separate TSCR will be submitted if it is detemined that such changes are needed.

Currently, a release rate of gross activity is monitored continuously at plant stack to assure that radioactive material is not released to the environment in an uncontrolled manner and that the radioactive material released is kept as low as is reasonably achievable. Section 3.6A(1) of Oyster Creek Technical Specifications limits the release rate of gross activity, except fodines and particulates with half lives longer than eight days, to 0.21/E (C1/sec) at the plant stack where E is the average gamma energy (MeV) per disintegration of the released materials.

All specifications proposed in the TCSR No.148 can be implemented at Oyster Creek within two months of issuance by NRC. This time is necessary in order for new procedures to be put in place and to allow for personnel training on these changes to be effected.

This Technical Specification Change Request has been reviewed in accordance with Section 6.5 of the Oyster Creek Technical Specifications.

Pursuant to 10 CFR 50.91 (b) (1), a copy of this Technical Specification Change Request has been sent to the State of New Jersey Department of Environmental Protection.

l A check for $150.00 pursuant to 10CFR170.12 will be provided by separate l letter.

l l

Very truly yours, ,

D Vice President and Director

! Oyster Creek l

PBF/pa Attachments cc: Dr. Thomas E. Murley, Administrator Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 NRC Resident Inspector Oyster Creek Nuclear Generating Station Forked River, N.J. 08731 wrw

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION IN THE MATTER OF )

) DOCKET No. 50-219 GPU NUCLEAR CORPORATION )

CERTIFICATE OF SERVICE This is to certify that a copy of Technical Specification Change Request No.

148 for the Oyster Creek Nuclear Generating Station Technical Specifications filed with the United States Nuclear Regulatory Commission on October 23, 1986, has this day of October 23 ,1986, been served on the Mayor of Lacey Township, Ocean County, New Jersey by deposit in the United States mail, addressed as follows:

Mayor of Lacey Township 818 West Lacey Road Forked River, NJ 08731 o

A ,

By. _ _-

w Peter 5.'Fiedler Vice President and Director Oyster Creek DATED: October 23, 1986 PBF:pa 3202f t