Provides Required Response 2 to NRC Bulletin 96-003, Potential Plugging of ECC Suction Strainers in Bwrs. During Recently Completed 17R Refueling Outage,New Strainers Were Installed
ML20196B447
Person / Time
Site: Oyster Creek
Issue date: 11/23/1998
From: Roche M
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
1940-98-20687, IEB-96-003, IEB-96-3, NUDOCS 9812010101
Download: ML20196B447 (3)


Text

.

  • 6 s

{

GPU Nuclear, Inc.

(

U.S. Route #9 South NUCLEAR Post Office Box 388 Forked River, NJ 087310388 Tel 609-971-4000 i

November 23,1998 1940-98-20687 U. S. Nuclear Regulatory Commission Atta: Document Control Desk Washington DC 20555

Dear Sir:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 1

NRC Bulletin %-03; Required Response No.2 On May 6,1996, the NRC issued Bulletin 96-03, " Potential Plugging of Emergency Core Cooling Suction Strainers in Boiling Water Reactors". By letter dated November 4,1996, GPU Nuclear, Inc. provided information to address Required Response No.1. In that letter, GPU Nuclear, Inc. described a new suction strainer design and committed to installing the new j

strainers during the next refueling outage.

On page nine of the referenced bulletin, a second reporting requirement was detailed requiring b

notification of the NRC within 30 days of completion of the installation of the selected

/p modification. During the recently completed 17R refueling outage the new strainers were

'J installed.

j Attachment I to this cover provides the requisite response.

9812010101 981123 F PDR ADOCK 05000219 G

PDR;

.o

1940-98-2 % 87 Page 2 If any additional information or assistance is required, please contact Mr. John Rogers of my staff at 609.971.4893.

Very tmly yours, Michael B. Roche Vice President and Director Oyster Creek Attachment MBR/JJR cc:

Administrator, Region I NRC Project Manager Resident Inspector Sworn to and subscribed before me this M3 Nb day of November,1998.

'20inio>h1. b h &

A Notary Public My commission expires (na /3. cpooi l} o w a u. ose u m o sp ermbdue " W_ _ hoot

i Attachment I NRC Bulletin 96-03 Required Response No. 2 NRC Required Response No. 2:

"Within 30 days of the completion of all required actions, (submit) a report confirming completion and summarizing any actions taken.

GPU Nuclear Response:

During the recently completed 17R refueling outage, the original Emergency Core Cooling (ECCS) Suction Strainers were replaced with new, large capacity strainers. These new strainers are of a segmented, stacked disk design, which allowed them to be assembled inside the wetwell with no required welding. After assembly, they were bolted onto the existing flanges. This design was consistent with criteria set forth in the Boiling Water Reactor Owners Group Utility Resolutimt Guidance document, which has recently been approved by the NRC.

Evaluation of the Mark I Loss of Coolant Accident induced hydrodynamic loads allowed for installation of the selected modification without any new structural supports. However, relocation of some existing catwalk supports was required. Post maintenance testing of the new strainers validated the clean strainer pressure drop used in the analysis.