|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] Category:STATE/LOCAL GOVERNMENT TO NRC
MONTHYEARML20011E5981990-02-0505 February 1990 Requests That Listed Individuals Be Deleted from Svc List for Facilities.Documents Already Sent to Dept of Environ Protection of State of Nj ML19332E6461989-11-0808 November 1989 Discusses PA Dept of Environ Resources Insp Rept 50-334/PA-89-01 on 891016.No Violations or Deviations Noted. Major Areas Inspected:Low Level Radwaste Shipment to Burial Site,Vehicle Insp & Radiation & Contamination Surveys ML20247D3811989-09-0707 September 1989 Informs That RM Smith Appointed Commissioner of Labor,State of Wv ML18094A6231989-08-11011 August 1989 Requests Addition of Ofc of Peoples Counsel to NRC Svc Lists for Insps,Events & Mgt of Facilities.Ofc of Peoples Counsel Represents Residential Customers of Utils Regulated by State of MD PSC ML20206C5901988-11-0909 November 1988 Forwards Withdrawal of Request of State of Tn to Participate as Interested Party,Per 10CFR2.715(c).Requests That Mh Mobley Remain on Svc List for Purpose of Receiving All Pertinent Correspondence,Filings & Notices ML20207M0691988-09-29029 September 1988 Comments on Environ Assessments & Finding of No Significant Impact Documents Re Alchemie Facilities.Blind Approach of Addressing Stable Isotope Enrichment Appalling ML20154A0931988-08-30030 August 1988 Forwards Comments on from Alchemie,Inc Re Radiological Hazards.Clarification Desired ML20151G6531988-07-18018 July 1988 Advises That State of Tn Will Forgo Appearance at 880721 Prehearing Conference in Knoxville,Tn Based on Concerns Already or in Process of Being Addressed ML20236Y2041987-11-17017 November 1987 Requests to Remain on Svc List for Plant.Mailing Address Listed ML20236Y2911987-11-11011 November 1987 Requests to Remain on Svc List for Plant,Per Tam ML20236Y2501987-11-0909 November 1987 Requests to Remain on Svc List for Unit 1 & Added to Svc List for Unit 2,per Recent Ps Tam Inquiry.Documents Should Be Addressed to Author ML20236Y2211987-11-0909 November 1987 Requests to Continue Receiving Publications for Plants,Per P Tam Request for Confirmation of Desire to Remain on Mailing List ML20236Y2711987-11-0202 November 1987 Requests Continuance of Mailings Currently Received,Per Ps Tam 871029 Request ML20195G6951987-09-0202 September 1987 Opposes Plant Restart Pending Revs to Radiological Emergency Response Plan.Current Plan,Dtd May 1985,inadequate W/Respect to Response Time,Evacuation Procedures & Reception Ctrs ML17347A5661987-06-0505 June 1987 Advises That Verbal Notification of Release of Amends to NRC Licenses in State of Fl Not Necessary.Written Notification of Proposed Amends Soliciting Comments & Written Rept of Release Adequate ML20235G2131987-05-28028 May 1987 Requests Info Re NRC Insp of Detroit Edison Safeteam Files, Including Insp Results,Corections to Problems,Adequacy of Util Investigations & Manner NRC Selected Files to Examine ML20204F2681987-03-19019 March 1987 Requests Removal from Distribution List for Listed Dockets ML20213G5481987-03-12012 March 1987 Requests Timely Review of Encl Draft Legislation Creating Onsite Monitoring Presence for State of Me at Facility & MOU Between NRC & State of or ML20211G5061987-02-13013 February 1987 Advises of Change of Address for State of Oh Dept of Health. Functions of Power Siting Commission Transferred to Board Operating Under Auspices of Puc of State of Oh ML20211G5301987-01-14014 January 1987 Forwards Rept of Emergency Evacuation Review Team on Emergency Response Plans for Perry & Davis-Besse Nuclear Power Plants. Rept Concluded That Current Emergency Response Plan Inadequate.Served on 870128 ML20237C8811986-12-22022 December 1986 Forwards Rept to Governor on Emergency Preparedness for Accident at Pilgrim Nuclear Power Plant, Presented on 861216.Governor Accepted Finding That Current Offsite Radiological Emergency Response Plans for Plant Inadequate ML20211A9381986-10-0909 October 1986 Requests to Be Placed on Mailing Lists for Publications Re Perry,Davis-Besse & Beaver Valley Nuclear Plants.Puc of Oh Directed to Conduct Investigations. Comprehensive Assessment of Perry First Study to Be Conducted ML20205F3051986-08-15015 August 1986 Withdraws State of Oh Support for Evacuation Plans & Expects NRC to Withhold Full Power Ols,Pending State Review of 860131 Earthquake Near Perry & 850609 Event at Davis-Besse. Full Exercise of State Rights Anticipated.Served on 860818 ML20204F2571986-07-29029 July 1986 Requests Notification Before Issuance of License Amends for State of Il Nuclear Power Plants,Per 10CFR50.91(b) ML20204F1911986-07-29029 July 1986 Requests Notification Prior to Issuance of Amends to OLs Per 10CFR50.91(b).NRC Adherence to State Notification Practice Generally Acceptable,W/Some Exceptions ML20199L5831986-05-0707 May 1986 Raises Concerns Re NRC Poor Record of Enforcing High Safety Stds in State of Oh.Reconsideration of Earthquakes as Safety Issue Requested ML20206U8211986-02-25025 February 1986 Responds to Acceptance Appraisal on 851017-18.One Technician Added to Div of Labs & Split Sampling Program for Cooper Nuclear Station Initiated in Jan 1986 ML20154L4851986-02-25025 February 1986 Ack Receipt of Re Acceptance Appraisal Rept 99990004/85-10 on 851017-18 for Proposed Nrc/State of Ne Environ Monitoring Agreement Around Fort Calhoun & Cooper Plants.Response to Rept Concerns Listed ML20205J0911986-01-27027 January 1986 Requests Removal of Author Name from Svc List in Proceeding ML20137A3631986-01-0707 January 1986 Advises of No Adverse Findings as Result of Review of Proposed Tech Spec Amend to License NPF-37 Re Closure of Valves SI 8809A & B During Check Valve Surveillance Testing ML20136F6741986-01-0303 January 1986 Requests That NRC Continue to Send Copies of Correspondence W/Util to State & Delete as Cauger & EA Eisen from Svc List.Ltr to Wl Clements & NRC 841211 Memo Encl ML20136A5621985-12-11011 December 1985 Lists New Address for Cd Jones,Director,State of Il Emergency Svcs & Disaster Agency ML20137Q9741985-11-25025 November 1985 Advises That Review of Fes Completed.No Comments Offered at Present ML20213F3831985-07-15015 July 1985 Requests Suspension of Low Power Testing at Facility Until Investigation of Accident Causing Hot Shutdown of Plant & Review of Training of Personnel & Condition of Equipment Complete ML20137E9721985-07-11011 July 1985 Discusses Interim Environ Surveillance Program Under Cooperative Agreement NRC-31-83-671.Proposed State Program Will Be Implemented by End of 1985 ML20213F3871985-07-11011 July 1985 Requests Immediate Halt of Low Power Testing at Facility Until Investigation of 850710 Accident in Which Valve Sys in Primary Containment Bldg Improperly Left Open Releasing Gas Into Atmosphere Complete ML20127N5501985-06-27027 June 1985 Discusses Proposed Exemption from 10CFR50.71 to Submit Updated FSAR for Both Plants 12 Months After Issuance of Braidwood Unit 2 Ol.Updated FSAR for Byron Should Be Issued by 880214,per 850627 Discussion W/L Olshan ML20215L2171985-05-23023 May 1985 Notifies That Agreement Between Valley Stream Union Free School District Thirteen,American Red Cross & Util Re Use of Congregate Care Ctrs in Event of Nuclear Plant Emergency Nonexistent.Served on 850603 ML20215L2201985-05-20020 May 1985 Notifies That Roslyn Board of Education Agreement W/Util Re Use of Congregate Care Ctrs in Event of Plant Emergency Nonexistent.Served on 850603 ML20215L2271985-05-17017 May 1985 Notifies That Island Park School District Agreement W/Red Cross & Util Re Relocation in Event of Radiological Emergency Nonexistent.Served on 850603 ML20215L2381985-05-13013 May 1985 Notifies That Westbury Union Free School District Agreement W/American Red Cross or Util Re Svc as Relocation Ctr in Event of Plant Emergency Nonexistent.Served on 850603 ML20215L2491985-05-10010 May 1985 Protests That Willingness to Participate W/American Red Cross in Event of Natural Emergency Extended by Red Cross to Include Any Emergency Occurring from Plant Atomic Energy Generators.Served on 850603 ML20215L2581985-05-0909 May 1985 Notifies That Freeport Public Schools Not Consulted by Util Re Emergency Evacuation Plan & Unaware of Inclusion in Plan Until After Publication.Served on 850603 ML20215L2661985-05-0808 May 1985 Notifies That Permission to Include School in Evacuation Plan,Consistent W/Plan Evacuation Schedule,Granted to No One.Served on 850603 ML20215L2621985-04-0808 April 1985 Informs That No Legal Agreement Exists Between Nassau County & Util Re Use of Plant.Served on 850603.W/service List & Certificate of Svc ML20099L5581985-03-11011 March 1985 Advises That No National Register Eligible or Listed Historic or Archeological Properties in Area of Proposed Project,Per Issuance of Des ML20102C2881985-02-27027 February 1985 Offers No Comments on Facility Des ML20136F6811985-02-14014 February 1985 Forwards Info to Update Svc Lists Per NRC 841211 Memo ML20213F1201984-12-20020 December 1984 Supports Resolution, Sense of Legislature Resolution Requesting That NRC Permit Suffolk County to Present Oral Arguments Opposing Util Request for Low Power License for Shoreham Nuclear Power Plant. Resolution Encl ML20213F1081984-12-19019 December 1984 Decries Licensee Refusal to Provide Info to Public Re Status of Fuel Loading.Immediate NRC Order Directing Util to Provide Regular,Full & Accurate Disclosure of Fuel Loading & Low Power Testing Requested 1990-02-05
[Table view] |
Text
~
5 .
^ Pennsylvania Public Utility Commission North Office Building P. O. Box 3265 Harrisburg, PA 17120 May 5, 1980 Mr. William T. Russell Office of Noclear Reactor Regulation Nuclear Regulatory Commission Washington, D. C. 20555
Dear Bill:
Subject:
NRC Staff Testimony The following is a summary of the issues and matters I think we should y
cover at the Pennsylvania depositions iri May, note that this letter includes only the Beaver Valley dynamic stress analysis and turbine spindle issues.
My following letter will cover the low-head injection pump and chronology -
history of inspection issues.
First, each witness should probably pr'epare a qualifications summary in written form. I will have the reporter insert each summary into the record at the outset, to save time. I have enclosed an example of expert qualification testimony submitted in another proceeding. Each witness should include a complete summary, with dates, of educational qualifications after high school or preparatory school, nature of educational concentration, any educational or professional scholarships or awards, work experience, and nature of duties to the present (emphasizing and describing in detail NRC employment), professional papers and articles authored or co-authored, membership in professional organ-izations, major work projects completed or in progress, testimony (and in what areas) given before courts, legislative bodies or administrative agencies and any other relevant factors or experience which would cause the Public Utility Commission to regard the witness as an expert in the specific areas to be addressed. Finally, if any witness holds a security clearance or is otherwise restricted from testifying on some aspect of work experience, so indicate.
Definitions - Dynamic Stress Analysis It is desireable.to define, at the outset all of the numerous technical .
terms and abbreviations to be used in testimony. Ordinarily, we would prepare a glossary in written form, but that is impractical in this proceeding. I have culled a few of the more difficult and important terms from the literature which could stand definition.
- dynamic stress analysis
- static stress analysis
- intermodal combination
- intramodal combination
- shock spectrum 8508130174 850703 PDR- FOIA HERRMAN85-301 PDR
Mr. William T. Russell Page 2 May 5, 1980
- two directional and three directional analysis
- single and multiple pulse quakes
- RMS
- algebraic, square root sum of the squares (SRSS) and absolute summations
- response spectrum analysis
- ASME codes
- Regulatory Guides, and 91.92
- FSAR
- SER
- linear combination among nodes
- absolute combination among nodes
- SHOCK I code >
- SHOCK II code
- NUPIPE code
- dynamic; static analysis .
- phasing and earthquake phase relationships Questions - Dynamic Stress Analysis
- 1. Name, address, present occupation, prior education and experience.
- 2. Present NRC position - role of NRC staff in nuclear safety review.
3.- Scope of expertise and testimony in this case.
.4. . Definitions of terminology to be used.
- 5. What events led up to the March 13th shutdown?
- 6. What did Beaver Valley's SER say with respect to stress analysis?
The FSAR? -
- 7. What NRC regulations, regulatory quidea or understandings with respect
- to stress analysis and when?
- 8. Who performed initial stress analysis computations? When?
- 9. ~What methodology was used? What methodology should have been used, in your opinion? Why?
- 10. Should S & W have known, or its mechanical engineers have known that .
its computer codes were wrong? Why?
- 11. Were there any subsequent events after B-V was planned which could have alerted S & W to a need for reanalysis? Was such reanalysis performed? l
- 12. What was NRC staff's first reaction upon learning of the stress analysis methodology-used? (What problems - regulatory and engineering - did it present?)
- 13. What actions did the NRC's show cause order require of Duquesne, the operating licensee?
- 14. How long did the shutdown last?
- 15. What specific reanalysis was required of the licensee? Who did it?
- 16. 14 tat analysis did S & W actually perform? (Did they do more than I required? Did this delay start-up?)
16a. In your opinion, did S & W delay the reanalysis?
- 17. What deficiencies were uncovered as a result of the analysis? (DBE -
OBE requirements and problems?)
- 18. Were those deficiencies corrected? How?
- 19. Describe the difference between SRSS, algebraic summation, and absolute summation stress analysis methods?
- 20. Which method predicts actual stress conditions best? Why?
F Mr. William T. Russell Page 3 May 5,1980
- 21. What trade-offs must an engineer make in stress analysis and reinforce-ment? (harmonic coupling problems, overdesign problems, etc.)
- 22. What design features of B-V already contributed to stress resistance?
- 23. Why was a dynamic rather than a static analysis required?
- 24. Do all licensees now calculate stress by the SRSS method? Are other and older plants other than S & W plants being reanalized?
Definitions - Turbine Spindle Cracking
- parts of turbine spindle
- low pressure turbine vs. pressure turbine ,
- spindle
- shaft
- keyway
- rotors or blades ,
- necessary metallurgical terms
- stress corrosion cracking
- turbine missiles
- turbine discs Questions - Turbine Spindle Cracking Qualifications
- 1. What event alerted the NRC to a problem with turbine disc cracking?
- 2. Describe the current problems with disc cracking.
- 3. Is the problem peculiar to a specific turbine design or manufacturer?
- 4. What theories have been advanced to '.xplain the cracking?
- 5. "hnt ctcpc have been taken to cure the cracking? (Duquesne? Other licencees?)
- 6. Ar e the replacement spindles of Duquesne of the same design as the original (cracked) spindles?
- 7. Could cracking prob.' ems occur with the replacement spindles?
- 8. Have the cracks appeared in Westinghouse spindles earlier than expected by the nature of the design?
- 9. Has spindle cracking contributed or is it likely to contribute to any B-V shutdown?
Please feel free to telephone comments or suggestions for additional defi-nitions or questions to me. I will be at out-of-town hearings until May 9,1980, but my secretary will relay messages.
I hope this provides a good starting point for preparation.
N$rytrulyyours, J hn A. Levin sistant Counsel rrr Enclosure
F' I.
> QUALIFICATIONS AND
SUMMARY
OF FINDINGS J. Please state your name and business address.
2 A, My name is John K. Stutz.
My business address is Energy Systems Research Group, Inc., 120 Milk Street, Boston, Massachusetts 02109.
Q.
Dr. Stutz, please describe your background and qualifications .
A.
I am currently a senior research scientist at Energy System'.
Research Group, Inc. (ESRG),
a non-profit firm specializing in research on energy-related matters.
At ESRG I have had extensive experience in the area of mathematical modelling and its application to energy-related problems, particularly long-range load forecasting for electric utilities.
I have testified in electric utility cases in New York Massachusetts, Rhode Island, g
Connecticut, Pennsylvania, and Michigan. I have prepared long-l range electric load forecasts for utilities in New York, Connecti- >
cut, Pennsylvania and Ohio.
Before joining ESRG, and after i receiving my Ph.D.
at Princeton University, I taught :nd did j resacrch in mathematics and economics at M.I.T., the State University of New York at Albany, and most recently at Fordham University, where I held the position of Associate Professor and co-director of the program in Mathematics and Economics. My .
g background is described more fully in the Vita attached as 4 Exhibit (JS-1) below.
What is the subject of your testimony today?
My testimony concerns the long-range load grow:h forecast by the member utilities of CAPCO. -I am sponsoring independent
.^
e i
1 O #
.meeen m # -
7 Shsot 1 T(^~'"Mug-.,,7,, y ,
'F. W y.)
iT, he,E .*- -
, 9t .%. s i
JOHN K. STUTz ? :n
- lly. 4, i
Research Scs. .e ntist i+dge,k ' '
, Secretary of the Corporation .
h.p,q[t
'# l .
Energy Systems Research Group '
"$*f?P
. .,..; M64 e, s N D q..q;N iId*
Education-Mathematics, Princeton University,1969. -%j Ph.D.: Mathematics, State University of New York 3 l B.S.: at Stony Brook, 1965 ,
Ercerience Inc.
Energy Systems Research Group, 1977 - Present:
Responsibility for mathematical modellin .
electrical demand forecasting and input-output analysis of the labor impacts ofen electric service and rate design issues; analysis of energy price impacts on consumers.
. Associate Professor, Mathematics Department,Co-d 1976 - 1977:
~
Fordham University.B.S. program in economics and m -
/
Assistant Professor to Associate Professor, 1971 - 1976: State University of New York at Albany,then Allen Center.
Mathematics Department, Instructor, Mathemacies Depart = enc, 1969 - 1971: Massachusetts Institute of Technology.
ESRG Research r
Long Range Forecast of.Ohic Electric Demand, ESRG -
Study No. 79-24. Principal Investigator.
Forthcoming:
Testimony, Pennsylvania Public Utility Long Commissio:
range March 1980: (Duquesne Light Co. and CAPCO) .
forecast of electric energy and demand.
Testi:nony, Case 20055, Massachusetts Department January 1930: (New Bedford Gas and Edison of Public UtilitiesElectricity conservation strategies Light Co.).
and alternative generation options; critiqu forecast.
4 i
6
.w w. .a
- ~ 2 r .. . :. :;.
,.__~__.__,.,_-.__
/ Exhibit (JS-1)
- ' Shsst 2 of 6 f ,
/
/ December 1979: Testimony, Case 1232, Rhode Island Public
- Utility Commission (Blackstone Valley Electric Co.). Critique of cost of service study and analysis of alternative rate designs. i November 1979: Testimony, Docket R-79060865, Pennsylvania i P.U.C. (Philadelphia Electric Co. ) Long-range i demand forecast (base case and conservation policy case).
October 1979: Testimony, Case U-6217, Michigan Public Service Commission (Detroit Edison Co.) . Forecast critique.
September 1979: Energv and Jobs: Analyzing the Economic Impacts of State Policies to Promote Energy Conservation, ESRG Study No. 79-01. Develop-ment of input-output model and application to a region in Massachusetts. Principal Investigator.
September 1979: Testimony, The.New York State Energy Master Planning and Long Ran,ge Ele,ctric and, Gas ' .
System Proceeding. Leng-range electric ,
demand and the employment implications of energy conservation.
July 19 79 : Base Case Forecast and Emplevment Impacts of the Conservation Poliev Case Alternative, volumes I and III of ESRG Study No. 79-12, Electricity Requirements in New York State.
Principal Investigator for Volume III.
June 1979: Long-Range Forecast of Electric Energy and Demand in the Service Territory of tne Ducuesne Lignt Company, ESRG S:udy No. 7 9 - 1 7 .-* -Principal Investigator.
May 1979: Testimony, Case 19494,' Massachusetts DPU l (Boston Edison Co.). Growth in electric demand.
May 1979: Assessment of the New England Pcwer Pcol - I Sattelle Long Range Electric Demand Forecasting Mcdel, ESRG Study No. 7 9-06, A Repcrt to cae New England Conference of Public Utility Ccmmissicners. Co-auther.
May 1979: Testimony, Case U-6006, Michigan P.S.C. (Detroit
- sdison Co.). Forecast critique.
i l .
- 1. --. . , . - _ _
v- .c._.-_.==. .__.
y . .,
. . c, ,
n Dit J3-1)
./.
March 1979: Testimony, Cases 27461 and 27462, New York 7,f Public Service Commission (Central Hudson Gas and Electric Co.). Critique of revenue 1 g/v and demand forecasts.
l l
/ February 1979: Analvzine the Impacts of Energy Prices on i New England Residents, ISRG Study No. 79-01. l Principal Investigator. )
1 Deca =ber 1973: Energv Demand Study: Power Authority of the State of New York, ESRG Study No. 78-15.
Principal Investigator.
December 1978: Economic Impact of an Electricity Rate Increase in New York City, ESRG Study No.
78-14. Principal Investigator.
Deca-her 1978: Gas Production from Nuclear Power Plant waste Heat: An Econcmic Analysis, ESRG Study No. 78-12. Co-author.,'
' Octcber 1978: Testimony, D'ocket 780701, Connecticut Puelic Utilities Control Authority (United Illuminating Co.). Forecast critique and long-range demand ferecast.
October 1978: The Employment Creation' Potential of Energy conservation and Solar Tecnnologies : The Implications of the Long Island Jobs Study for New England, 1978-1993. Principal inves tigator.
September 1978: Long Range Forecast of Electric Energy and Demand in New York State, ESRG S:udy No.
78-07. Co-autner.
September 1979: Testimony, Case 27319, N.Y. Public Service Commission (Pewer Pool Long Range Plan) .
Forecast critique and demand forecast.
May 1978: A Methodology for Estidating Tetal Icenemic and Employmen: Im= acts of Energy Related Construction, ESRG Study No. 73-03. Principal Investigator.
March ~ 1978 : Testimeny, Docket 433, Pennsylvania Public C llity Commission (Philadelphia Electric Co.).
Forecast critique and demand ferecast.
.' cau4wAw w a 11 l Sheot 4 oT~6 l J
. ..a september 1977: Testimony, cockets 770319 and 770320,
,p' Connecticut Public Utilities Control J Authority (Ncrtheast Utility System) .
/
Forecast critique, conservaation options; l
./- comparative costs of generatien alternatives.
/ i April 1977: Assessing cemand, Alternative Generating '
Strategies, and Utility Economics in tne Service Territory of orance and Rockland Utili tie s , ES RG S tudy No . 77-01. Co-author.
April 1977: Testimony, Cases 27094 and 27095, N.Y.
Public Service Commission (Orange and Rockland Utilities) .
Other Publications April 1979: . Production of Synthetic Gas from Nuclear Energy Sources, Los Alamos Scientific Laboratory Report LA-7592-MS. Co- autho r .
February 1979: " Energy Policy and Employment," Peoole Energy Primer, Syracuse Peace Council.
1976: "Equisingularity and Local Analytic
. Proceedings of the American Geometry,"
Mathematica l~ Society, Summer Institute on Severai Complex Variables.
April 1976: " Residual Equisingularity," with Jos'aph Becker. Proceedings of the American Mathematical soc 1ety, vol. 56.
1974: " Primitive Elements for Mcdules ever O(?) ,"
Duke Mathematics Journal, vol. 4.
1 1973: "The.C Embedding Dimension of Certain Analytic Sets," with J. Beckar. Ouke Mathematics Journal, vol. 40.
1973: " Resolving Singularities via Lccal Quadratic Transformations," with J. Secker. Proceedings of the conf erence en Singularities , Rice University Studies, vol. 59.
1973: " Wings in Analytic Sets," Indiana University Mathematics Jcurnal, vol. 22.
1972: "Equisingularity and Equisaturation in Cedimen-sien I," American Journal of Mathematics, vol.
94.
~ ww Exhibit (JS-1)
. ,/ ShOct 5 of 6 g* \
I I
1972:
" Analytic Sets as Branched Coverings,"
,/- Transactions of the American Mathematical s y Society, vol. 166. l
/
1970:
"The Representation P cblem fod Differential Operators on Analytic Sets ," Math. Ann. ,
vol. 189.
Selected Pacers and Professional Activities Consultant to National Consumer Law Center.
1979 - present: Electric utility load research methodology.
1978 - 1979 Consultant to Council on Economic Priorities.
Energy and employment.
1979:
" Assessing Local Employment Impacts of Conservation and Solar-Related Activities,"
Conf erence sponsored by the International Solar Energy Society, Georgia Office of Energy Resources, and Solar Energy Research -
Institute.
October 1978: Panelist on electric utility rate structures and load forecasting, national meeting of the Critical Mass Energy Project. .
August 1978: Participant, Boston workshop on electricity supply and demand planning sponsored by the National Governors' Association, National
. Association of Regulatory Utility Commissioners, and Department of Energy.
Fall 1977: "The Role of Public Agencies in Utility Load Forecasting Proceedings ," Lawyers ' Guild meeting , Hartford.
November 1977: " Utility Electrical Cemand Projections,"
Northeastern Political' Science Association meeting, Mt. Pocono, Pennsylvania.
S c=ser 19 7 5 :
Invited speaker- American Mathematical Society's Summer Institute on Analytic Functions of Several Complex variables.
1973:
Invited Participant, Rice University Ccnference on Singularities of Analytic Sets.
1972 - Present:
Referee, Proceedings of the American Mathematical Society and Duke Mathematics Jcurnal.
h
j! hbbbt 6 of 5 l
',[ ' 1969 - 1975: R0 viewer for Methematical RnviGws cnd
/ Zentralblat fGd Mathematik.
/
/ Awards and Honors State University of New York Faculty Fellowship, St=mer 19 72 and Summer 19 73.
National Science Foundation Cooperative Fellcwship, 1965 - 1967.
Professional Sccieties American Mathematics Society.
G 1
l l
1 l
.m
-s - e ..
o