Summary of July 15, 2019, Public Teleconference with Florida Power & Light Company Regarding the NRC Review Status of License Amendment Request 258
ML19198A041
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/23/2019
From: Perry Buckberg
Plant Licensing Branch II
To: Stall J
Florida Power & Light Co
Buckberg P, NRR/DORL. 301-415-1383
References
EPID L-2018-LLA-0120
Download: ML19198A041 (4)


Text

July 23, 2019 LICENSEE: Florida Power & Light Company FACILITY: Turkey Point Nuclear Generating Unit Nos. 3 and 4

SUBJECT:

SUMMARY

OF JULY 15, 2019, PUBLIC TELECONFERENCE WITH FLORIDA POWER & LIGHT COMPANY REGARDING THE NRC REVIEW STATUS OF LICENSE AMENDMENT REQUEST 258 FOR TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 (EPID L-2018-LLA-0120)

On July 15, 2019, a Category 1 public teleconference was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Florida Power & Light Company (the licensee). The purpose of the teleconference was to discuss the status of the staff review of license amendment request (LAR) 258 for Turkey Point Nuclear Generating Unit Nos. 3 and 4.

This LAR would revise the Technical Specification Safety Limit 2.1.1.b to reflect the peak fuel centerline melt temperature specified in Westinghouse Topical Report WCAP-17642-NP-A, Revision 1, Westinghouse Performance Analysis and Design Model (PAD5) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17338A396). The meeting notice and agenda, dated July 9, 2019, are available at ADAMS Accession No. ML18099A160. A list of attendees is provided as an enclosure to this summary. No regulatory decisions were made at this meeting.

The NRC staff began the discussion by informing the licensee that the safety evaluation for LAR 258 would continue toward issuance with no additional documentation needed from the licensee. The NRC staff also offered that LAR 258 had been evaluated independent of Topical Report WCAP-17642-NP-A. In response to licensee questions, the NRC staff offered that LAR 258 approval would require no license conditions, and the issue date for the associated license amendments was estimated to be mid-August 2019.

Members of the public were in attendance. No comments or Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-1383 or e-mail to Perry.Buckberg@nrc.gov.

/RA/

Perry H. Buckberg, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250 and 50-251

Enclosure:

List of Attendees cc: Listserv

ML19198A041 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LAiT NRR/DORL/LPL2-2/LA NAME PBuckberg KEntz LRonewicz DATE 7/18/2019 7/18/2019 7/18/2019 OFFICE NRR/DORL/LPL2-2/BC NRR/DORL/LPL2-2/PM NAME UShoop PBuckberg DATE 7/18/2019 7/23/2019 LIST OF ATTENDEES JULY 15, 2019, PUBLIC TELECONFERENCE WITH FLORIDA POWER & LIGHT COMPANY TO DISCUSS THE NRC REVIEW STATUS OF LICENSE AMENDMENT REQUEST 258 TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 Name Organization Perry Buckberg U.S. Nuclear Regulatory Commission (NRC)

Undine Shoop NRC Benjamin Parks NRC Josh Borromeo NRC Diana Woodyatt NRC Robert Lukes NRC Lundy Pressley NRC Steve Catron Florida Power & Light Company (FPL)

Patrick Hahn FPL Olga Hanek FPL Jarrett Mack FPL Emilio Fuentes FPL Phil Tiemann FPL Jay Kabadi FPL Several members of the public Enclosure