MONTHYEARPMNS20201328, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2020-12-0909 December 2020 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML20338A0472020-12-0909 December 2020 December 9, 2020 FPL Slides Rps/Esfas Nuclear Instrumentation Project stage: Request PMNS20201397, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2020-12-16016 December 2020 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21011A2382021-01-11011 January 2021 Slides for January 13, 2021 Presubmittal Meeting with NextEra Concerning Digital I&C Closed Non-Proprietary Project stage: Request ML21011A2232021-01-22022 January 2021 Requests for Withholding Information from Public Disclosure Project stage: Other PMNS20210136, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-02-0404 February 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21047A2102021-02-16016 February 2021 NRC Presubmittal Meeting Telecon February 18, 2021 Open Meeting - FPL Safety System Replacement Project LAR - Nonproprietary Project stage: Meeting PMNS20210305, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade at Turkey Point Nuclear Generating, Unit Nos. 3 and 42021-03-29029 March 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade at Turkey Point Nuclear Generating, Unit Nos. 3 and 4 Project stage: Request ML21054A0012021-03-29029 March 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade Project stage: Meeting ML21096A0772021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification Project stage: Request ML21096A0612021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification - Open Project stage: Request ML21099A1052021-04-23023 April 2021 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance PMNS20210737, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-05-28028 May 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21159A1652021-06-0404 June 2021 Affidavit for Nextera Tricon Presentation for Turkey Point 5th Presubmittal Meeting Project stage: Meeting ML21159A1892021-06-0909 June 2021 Non-Proprietary - FPL NRC Presubmittal Meeting June 9th Closed Slides Project stage: Meeting ML21159A1712021-06-0909 June 2021 FPL NRC Presubmittal Meeting June 10th Week Open Session Project stage: Meeting ML21176A0102021-06-29029 June 2021 Summary of Drop-in Meeting with NextEra-Florida Power and Light to Discuss Pending Submittals Related to Digital Instrumentation and Controls and Improved Standard Technical Specifications for Turkey Point Nuclear Plant, Units 3 & 4 (EPID L Project stage: Meeting ML21172A2712021-06-29029 June 2021 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Withholding Request Acceptance PMNS20210933, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-07-12012 July 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21200A1472021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Closed Public Project stage: Request ML21200A1562021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Open Project stage: Request ML21190A1862021-08-0202 August 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 Project stage: Meeting ML21232A0172021-08-20020 August 2021 Licensee'S Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting Project stage: Meeting ML21279A0962021-08-20020 August 2021, 23 August 2021, 15 October 2021 Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 Project stage: Request ML21235A0932021-08-23023 August 2021 Licensee'S Non-Proprietary Presentation (1 of 2) for August 23 and 25, 2021 Public Meeting Project stage: Meeting PMNS20211047, Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control License Amendment Request for Turkey Point Nuclear Generating Unit Nos. 3 and 42021-08-23023 August 2021 Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control License Amendment Request for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Meeting ML21279A0432021-10-15015 October 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 Project stage: Meeting ML21214A1192021-11-23023 November 2021 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Withholding Request Acceptance ML21246A0212021-11-23023 November 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 Project stage: Meeting ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request Project stage: Other PMNS20220162, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Units 3 and 42022-02-25025 February 2022 Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Units 3 and 4 Project stage: Meeting ML22063A4482022-03-0202 March 2022 Nextera/Fpl Affidavit for Proprietary Presentation for March 7, 2022, Public Meeting Project stage: Meeting ML22101A2042022-04-0606 April 2022 Nextera/Fpl Affidavit for Proprietary Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request Project stage: Meeting ML22101A2262022-04-11011 April 2022 NRC Staff Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request Project stage: Meeting ML22098A0902022-04-13013 April 2022 Nextera/Fpl Non-Proprietary Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (EPID L-2021-LRM-0007) (Slides) Project stage: Meeting ML22098A0932022-04-13013 April 2022 Nextera/Fpl Redacted Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (Public Version) Project stage: Meeting ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 Project stage: Meeting ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 Project stage: Meeting 2021-06-29
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24128A2102024-05-0707 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Regarding Saint Lucie ML22132A0032024-04-23023 April 2024 Summary of Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML23276A1852023-09-25025 September 2023 Subsequent License Renewal Draft EIS Public Meetings: Meeting Summary ML23221A3782023-08-16016 August 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23087A0692023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23058A4262023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML23108A2752023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23068A0712023-04-28028 April 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 (EPID L-2022-LLA-0105) - Nonproprietary ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23081A5022023-03-28028 March 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23048A0492023-03-0303 March 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22349A0012023-01-0505 January 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22276A2302022-10-0606 October 2022 Summary of September 13, 2022, Public Meeting with FPL Concerning Supplemental Information Needed for Acceptance of License Amendment Request to Replace Instrumentation with Digital Systems on Turkey Point, Units 3 and 4 ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22238A2762022-08-29029 August 2022 Summary of August 17, 2022, Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Extend the Completion Time for an Inoperable Reactor Trip Breaker ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22228A2352022-08-23023 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22228A2032022-08-22022 August 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22195A1752022-07-27027 July 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22186A0812022-07-15015 July 2022 Summary of June 22, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Fire Protection Program Changes ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22160A3792022-06-30030 June 2022 Summary of May 24, 2022, Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22054A0082022-03-0303 March 2022 Summary of February 17, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Intake Cooling Water Discharge Piping Proposed Alternative ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21327A1802021-12-0707 December 2021 Summary of August 25, 2021 Observation Public Meeting with FPL to Discuss Proposed Alternative Report for the Intake Cooling Water System ML21246A0212021-11-23023 November 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 ML21279A0432021-10-15015 October 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 ML21285A0412021-10-13013 October 2021 Summary of September 29, 2021 Meeting with the U.S. Fish and Wildlife Service Regarding Crocodile Monitoring at Turkey Point ML21190A1862021-08-0202 August 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 ML21176A0102021-06-29029 June 2021 Summary of Drop-in Meeting with NextEra-Florida Power and Light to Discuss Pending Submittals Related to Digital Instrumentation and Controls and Improved Standard Technical Specifications for Turkey Point Nuclear Plant, Units 3 & 4 (EPID L ML21159A1352021-06-0808 June 2021 Public Meeting Summary Regarding the Saint Lucie Nuclear Plant, Units 1 and 2, Docket No. 50-335 and 389, and the Turkey Point Nuclear Generating Station Units 3 and 4, Docket No. 50-250 and 50-251; Meeting Number 20210505 ML21158A0572021-06-0707 June 2021 Summary of May 3, 2021, Teleconference with the U.S. Fish and Wildlife Service and Florida Power & Light Company Regarding Injured American Crocodile at Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML21158A0582021-06-0707 June 2021 Summary of May 20, 2021, Teleconference with the Florida Power & Light Company Regarding Endangered and Threatened Species Reporting at Turkey Point Nuclear Generating Unit Nos. 3 and 4 2024-05-07
[Table view] |
Text
August 2, 2021 LICENSEE: Florida Power & Light Company FACILITY: Turkey Point Nuclear Generating Unit Nos. 3 and 4
SUBJECT:
SUMMARY
OF PRE-APPLICATION MEETINGS WITH FLORIDA POWER AND LIGHT CONCERNING A PROPOSED DIGITAL INSTRUMENTATION AND CONTROL UPGRADE ON TURKEY POINT UNIT NOS. 3 AND 4 (EPID L-2021-LRM-0007)
On February 18 and April 8, 2021, partially closed observation public meetings were held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Florida Power & Light Company (the licensee) via teleconference. The purpose of the partially closed meetings was to discuss the licensing process proposed for the Turkey Point Nuclear Generating Unit Nos. 3 and 4 digital instrumentation and control (DI&C) license amendment request. The meeting notices and agendas, dated February 4 and March 25, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession Nos. ML21035A141 and ML21088A014. A list of attendees is provided as .
The licensee presented information for both meetings which are available in ADAMS. The slides for the public portion of the meetings can be found under ADAMS Accession Nos. ML21047A210, ML21096A061, and ML21096A077).
FEBRUARY 18, 2021 The licensee provided an update regarding the intent to submit a licensing amendment request for a digital upgrade on two vertical panels in the control room for Turkey Point Units 3 and 4, using the Tricon Platform approved by the NRC in a safety evaluation dated April 12, 2012 (ADAMS Accession No. ML120900890). The focus for this meeting was in the areas proposed architecture for the system (including the diversity and defense-in-depth (D3) analyses), details regarding the Vendor Oversight Plan (VOP), and the various follow-up items from the December 9, 2020 meeting.
The licensee provided an update on ongoing design lifecycle activities and discussed the proposed quality assurance (QA) program elements related to the DI&C upgrade. The staff questioned the pedigree of the QA program that the licensee intended to use given that one being applied was not approved as part of the Triconex topical report approval. The licensee indicated that a gap was identified and an audit would be performed to evaluate any differences.
The licensee affirmed that QA related activities would be conducted consistent with Framatomes QA program.
Lessons-learned from the NRCs DI&C Workshop were discussed. The NRC clarified that Inspection Procedure 35017, Quality Assurance Implementation Inspection (ADAMS Accession No. ML20259A220) will be better integrated into the Reactor Oversight Program under Inspection Manual Chapter 2515, Light Water Reactor Inspection Program Operations Phase, but would not be part of baseline inspection activities.
Additional discussions during the meeting covered assumptions related to the D3 analyses, describing the engineered safety features actuation system (ESFAS) architecture, the safety/non-safety system interface, the scope of the Triconex approval, ongoing review activities concerning operator manual actions, and aspects related to environmental qualification testing and summary activities.
It was discussed that the scope of the proposed technical specification surveillance reduction change and the use of diagnostics be discussed at a future pre-submittal meeting.
APRIL 8, 2021 The April 8, 2021, pre-submittal meeting focused on architecture for the system, the human factors engineering (HFE) design elements, cyber-security, and an on ongoing design lifecycle activities. During the open session the licensee addressed the proposed intent and content of the VOP and the associated procedures involved. The NRC staff commented regarding the need for a discussion of the criteria for NextEras acceptance of procedures associated with the digital modification and demonstration of a clear tie of that acceptance to the procedure and whether an audit was/will be conducted of that procedure. Additionally, the NRC staff provided administrative lessons-learned from other recent reviews. This included a discussion of editorial format issues (i.e., numbering, subsections, common terminology etc) associated with the VOP that would facilitate an easier review and documentation of the NRC staffs findings. The NRC staff also suggested that clear attribution of the responsible company/organization performing each development activity would support a more efficient review.
In the closed session, the scope of the NRCs approval of the Tricon topical report was discussed. The NRC staff commented on various components and programs that were not approved and recommended the submittal of detailed information to support more effective NRC review activities. During the HFE discussion, the licensee outlined the implementation plans regarding validation and verification activities. The NRC staff had questions regarding the schedule of the implementation activities and the multidisciplinary team assigned. The discussion also included current cybersecurity design requirements applicable to Turkey Point and the licensees proposed cybersecurity elements for the proposed modification.
The licensee addressed the proposed technical specification (TS) changes that will likely be included with the proposed request. There was a discussion about the expected involvement with various automated indications proposed. Additional discussion was held regarding the applicability of precedent reviews that the licensee intended to credit in support of the human-system interface activities.
The licensee discussed changes to the lifecycle design schedule from the last meeting. The NRC staff indicated concern with the ability to support the revised schedule in part due to the change in schedule for certain lifecycle design activities. The NRC staff discussed that the unavailability of some design information along with the change in the NRC staffs access to
various design activities combined with the expanded scope of the proposed change may provide a challenge to the ability of the NRC staff to meet the requested date.
It was discussed that an overview of the proposed submittal, a discussion of those items considered beyond the scope of the Tricon topical report approval, a discussion of the simulator training plan and schedule, as well as additional discussions regarding the scope of the VOP and VOP summary document be included at the next pre-submittal meeting.
One member of the public was in attendance during the open session. No Public Meeting Feedback forms or comments were received.
Please direct any inquiries to me at 301-415-2315, or Eva.Brown@nrc.gov.
/RA/
Eva A. Brown, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-250 and 50-251
Enclosure:
List of Attendees cc w/enclosure: Listserv
ML21190A186
- via e-mail OFFICE LPL2-2/PM LPL2-2/LA LPL2-2/BC NAME EBrown RButler DWrona DATE 7/9/2021 7/14/2021 8/2/2021 PARTICIPANT LIST FOR PRE-APPLICATION MEETING WITH NEXTERA-FLORIDA POWER AND LIGHT TO DISCUSS PENDING SUBMITTALS RELATED TO DIGITAL INSTRUMENTATION AND CONTROLS AND FEBRUARY 18 AND APRIL 8, 2021 Nuclear Regulatory Commission Eric Benner Joseph Ashcraft Brian Green Samir Darbali Caroline Carusone Kim Lawson-Jenkins**
Michael Marshall Deanna Zhang Kerri Kavanagh* Jack Zhao Michael Waters Dan Warner Tarico Sweat William Roggenbrodt Mary-Jane Ross Lee* Joseph Donoghue*
Richard Stattel Aaron Armstrong*
Gregory Suber Greg Galletti Vic Cusamano Dabin Ki David Desaulniers Ed Miller Natreon Jordan* Phil McKenna Justin Vazquez NextEra-FPL Sargeant & Lundy Steve Catron Pareez Golub Brian Dunn William Maher Warren Busch Michael Matchinis Dave Stoia*
Jarrett Mack Ron LeGrand Brian Hayes Phil Barnes Fajth Banks Richard Baird*
Wesley Frewin Framatome Ron Legrand Ted Quinn Jerry Mauck Ron Jarrett Rick Turk Bill Hannaman Brian Haynes Michael Howard*
John Hefler*