MONTHYEARIR 05000387/20240022024-08-12012 August 2024 Integrated Inspection Report 05000387/2024002 and 05000388/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification PLA-8117, 23rd Refueling Outage Owners Activity Report (PLA-8117)2024-07-23023 July 2024 23rd Refueling Outage Owners Activity Report (PLA-8117) ML24197A0982024-07-15015 July 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000387/2024010 and 05000388/2024010 PLA-8126, Response to Request for Confirmation of Information Regarding Relief Request 1RR062024-05-29029 May 2024 Response to Request for Confirmation of Information Regarding Relief Request 1RR06 ML24127A2262024-05-29029 May 2024 Issuance of Amendment Nos. 288 and 272 Adoption of TSTF-563 PLA-8122, Annual Radiological Environmental Operating Report (PLA-8122)2024-05-28028 May 2024 Annual Radiological Environmental Operating Report (PLA-8122) PLA-8115, Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115)2024-05-23023 May 2024 Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115) IR 05000387/20240012024-05-13013 May 2024 Integrated Inspection Report 05000387/2024001 and 05000388/2024001 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 PLA-8101, Re 2023 Annual Report of Radiation Exposure2024-04-22022 April 2024 Re 2023 Annual Report of Radiation Exposure ML24082A1372024-04-22022 April 2024 Issuance of Amendment Nos. 287 and 271 Adoption of TSTF-568, Revision 2 and Associated Technical Specification Changes PLA-8094, Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-80942024-04-22022 April 2024 Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-8094 PLA-8095, 2023 Annual Radiological Environmental Operating Report (PLA-8095)2024-04-22022 April 2024 2023 Annual Radiological Environmental Operating Report (PLA-8095) PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8102, Annual Environmental Operating Report (Nonradiological) PLA-81022024-04-11011 April 2024 Annual Environmental Operating Report (Nonradiological) PLA-8102 PLA-8112, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-81122024-04-0909 April 2024 Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 PLA-8110, Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110)2024-04-0404 April 2024 Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110) ML24092A4022024-04-0101 April 2024 Annual Financial Report (PLA-8098) PLA-8100, Property Insurance Program (PLA-8100)2024-04-0101 April 2024 Property Insurance Program (PLA-8100) PLA-8109, Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109)2024-03-21021 March 2024 Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109) ML24067A2512024-03-19019 March 2024 Authorized Alternative to Requirements of the ASME Code PLA-8107, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance2024-03-19019 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance ML24044A2532024-03-14014 March 2024 Associated Independent Spent Fuel Storage Installation – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0077 (Security Notifications, Reports, and Recordkeeping & Suspicious Activity Reporting)) IR 05000387/20240112024-02-29029 February 2024 Commercial Grade Dedication Inspection Report 05000387/2024011 and 05000388/2024011 IR 05000387/20230062024-02-28028 February 2024 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2023006 and 05000388/2023006) ML24039A1882024-02-27027 February 2024 Issuance of Amendment Nos. 286 and 270 Changes to Technical Specifications for Control Rods ML24037A3072024-02-22022 February 2024 Summary of Regulatory Audit in Support of Relief Request 5RR-02 PLA-8099, Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099)2024-02-13013 February 2024 Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099) IR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23345A0682023-11-28028 November 2023 Technical Specification Bases, Manual PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) IR 05000387/20230032023-11-0303 November 2023 Integrated Inspection Report 05000387/2023003 and 05000388/2023003 PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML23291A1132023-10-12012 October 2023 Submittal of Revision 71 to Updated Final Safety Analysis Report and Revision 25 to Fire Protection Review Report ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000387/20233012023-09-20020 September 2023 Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000387/20230052023-08-31031 August 2023 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2023005 and 05000388/2023005) ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval IR 05000387/20230022023-08-0101 August 2023 Integrated Inspection Report 05000387/2023002 and 05000388/2023002 ML23195A1852023-07-27027 July 2023 Correction to Technical Specifications Page 3.3-73 in Amendment No. 265 2024-08-12
[Table view] Category:Meeting Summary
MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21035A1842021-02-11011 February 2021 Summary of the January 26, 2021, Meeting with Susquehanna Nuclear Regarding a Future License Amendment Request Related to Adopting Technical Specifications Task Force Traveler TSTF-505, Revision 2 ML20065F5522020-03-19019 March 2020 Summary of February 27, 2020, Meeting with Talen Energy Regarding Future License Amendment Request Related to Creating New Condition for Inoperable Manual Synchronization Circuit at Susquehanna Steam Electric Station, Units 1 and 2 ML19308A1082019-11-18018 November 2019 Summary of Meeting with Talen Energy Regarding a Future License Amendment Request Related to Revising the Dose Consequence Analysis for a Loss-Of-Coolant Accident at Susquehanna Steam Electric Station, Units 1 and 2 ML19259A2222019-10-16016 October 2019 Summary of September 16, 2019, Closed Meeting with Susquehanna Nuclear, LLC Regarding the Transition to Allow the Use of Atrium 11 Fuel for the Susquehanna Steam Electric Station, Units 1 and 2 ML19176A0502019-07-16016 July 2019 Summary of June 18, 2019, Meeting with Talen Energy Regarding Submittal of a Potential License Amendment Request Related to Changes to the Emergency Response Organization Staffing and Augmentation ML19191A1882019-07-0909 July 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - Meeting Summary ML19134A0292019-05-21021 May 2019 Summary of Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Use of Atrium 11 Fuel ML18311A2622018-11-26026 November 2018 Summary of Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Emergency Service Water Piping Replacement for Susquehanna Steam Electric Station, Units 1 and 2 ML18156A2632018-06-15015 June 2018 May 15, 2018, Summary of Closed Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request the Use of Atrium 11 Fuel for Susquehanna Steam Electric Station, Units 1 and 2 ML18141A2032018-05-22022 May 2018 2018 Susquehanna Annual Assessment Meeting Summary and Attendance List ML17250A3902017-09-14014 September 2017 Susquehanna Station, Units 1 and 2 - Summary of August 10, 2017, Pre-Submittal Teleconference with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Re: Technical Specifications Task Force Traveler-542 (CAC Nos. MG0059 and MG0060) ML17153A1012017-06-0202 June 2017 May 4, 2017, Summary of Annual Assessment Meeting for Susquehanna Steam Electric Station Held ML16131A1942016-05-10010 May 2016 April 27, 2016, Summary of Public Meeting on Susquehanna Steam Electric Station ML15295A2022015-10-29029 October 2015 Summary of Meeting with Susquehanna Nuclear, LLC on the TSTF-425 License Amendment Request for Susquehanna Steam Electric Station, Units 1 and 2 ML15278A4922015-10-0909 October 2015 Summary of Meeting with Susquehanna Nuclear, LLC on the Emergency Action Level Scheme Change Submittal for a License Amendment for Susquehanna Steam Electric Station, Units 1 and 2 ML15174A0262015-06-23023 June 2015 Annual Assessment Meeting Summary 2014 ML14247A6082014-09-0404 September 2014 2014 Susquehanna Regulatory Performance Meeting - Summary of Public Meeting ML14191A6992014-07-31031 July 2014 July 2, 2014 Summary of Meeting with PPL Susquehanna, LLC, Pre-Submittal Meeting Regarding Future Submittal for a License Transfer Amendment for Susquehanna Steam Electric Station, Units 1 and 2 ML14133A0592014-07-0101 July 2014 Summary of Closed Meeting Between Representatives of the Army Corps of Engineers, Nuclear Regulatory Commission, Federal Energy Regulatory Commission, Exelon Generation Co, LLC, and PPL Susquehanna, LLC, to Discuss Dam Failure Analysis.. ML14104B1302014-04-14014 April 2014 Summary of Public Meeting on April 9, 2014 ML13121A0812013-05-0101 May 2013 Summary of Public Meeting, Susquehanna Steam Electric Station ML13107B1372013-04-17017 April 2013 Annual Assessment Meeting Sign in Sheets for April 10, 2013 Public Meeting ML12297A2252012-10-23023 October 2012 Summary of Substantive Cross-Cutting Issues Progress Meeting with PPL Susquehanna, LLC, and Acknowledgement of Readiness for NRC 95002 Supplemental Follow-Up Inspection ML12093A3152012-04-0202 April 2012 Summary of March 21, 2012 Susquehanna 95002 Supplemental Inspection Public Exit and Regulatory Performance Meeting ML12093A1472012-04-0202 April 2012 Annual Assessment Meeting Summary ML1015304112010-06-0707 June 2010 Summary of Conference Call with Boiling Water Reactor Vessel and Internals Project Regarding Recent Operating Experience Associated with Replacement Steam Dryer ML0919101962009-07-16016 July 2009 Summary of Telephone Conference Call Held on June 25, 2009, Between the U.S. NRC and PPL Susquehanna, LLC, Comments on the Safety Evaluation Report with Open Items Related to the License Renewal of Susquehanna Steam Electric Station, Units ML0919404402009-07-13013 July 2009 Meeting Summary, Public Meeting with PPL Susquehanna, LLC Re SCWE at Site ML0919402172009-07-13013 July 2009 SCWE Public Mtg Sign-in Sheets, for July 6, 2009 ML0914800822009-06-0101 June 2009 Summary of Telephone Conference Call Held on May 21, 2009, Between the U.S. NRC and PPL Susquehanna, LLC, Concerning the Responses to RAIs Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0915204952009-06-0101 June 2009 Summary of Annual Assessment Meeting with PPL Susquehanna, LLC to Discuss the Nrc'S Assessment of the Safety Performance of the Susquehanna Steam Electric Station Units 1 and 2 for the Calendar Year 2008 ML0912502542009-05-0707 May 2009 Summary of Tele Conf Call Held on April 14th, 2009, Between the USNRC and PPL Susquehanna, LLC, Concerning Draft Requests for Additional Information Pertaining to the SSES, Units 1 and 2, License Renewal Application ML0900803792009-01-30030 January 2009 Summary of Telephone Conference Call Held on 12/18/08, Between the U.S. NRC and PPL Susquehanna, LLC, Concerning TLAA RAI ML0833101132008-12-0303 December 2008 Meeting Summary, Telephone Conference Call Between U.S. NRC and PPL Susquehanna, LLC, Concerning the Draft Request for Additional Information Pertaining to the Susquehanna Steam Electric Station Units 1 & 2, LRA ML0832209472008-11-19019 November 2008 Summary of Telephone Conference Call Held on October 10, 2008, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Llc., Concerning the Responses to Requests for Additional Information Pertaining to the Susquehanna Steam... ML0832307862008-11-19019 November 2008 11/13/2008-Summary of Telephone Conference Call Between NRC and PPL, Concerning the Responses to RAIs Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0830305912008-11-0303 November 2008 Summary of Telephone Conference Call Held on Sept 24, 2008, Between the U.S. NRC and PPL Susquehanna, Llc., Concerning Draft Requests for Additional Information Pertaining to the SSES, Units 1 and 2, License Renewal Application ML0828901522008-10-21021 October 2008 Summary of Telephone Conference Call Held on October 8, 2008, Between the USNRC and PPL Susquehanna, Llc. Concerning Draft Requests for Additional Information Pertaining to the, License Renewal Application ML0828205772008-10-17017 October 2008 09/18/2008 Meeting Summary, Meeting Between the NRC and PPL Susquehanna, Llc., Concerning Requests for Additional Information Responses Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0828004392008-10-17017 October 2008 09/15/2008-Summary of Telephone Conference Call Between Us NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna Steam Electric Station, Units 1 & 2, License Renewal Application ML0822603532008-10-0101 October 2008 06/25/2008 Meeting Summary, Telephone Conference Call Between the NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0814200522008-05-30030 May 2008 05/19/2008 Summary of Telephone Conference Call Held Between the NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0811307322008-04-22022 April 2008 Summary of Annual Assessment Meeting with PPL Corporation and Susquehanna Nrc'S Assessment of the Safety Performance of the Susquehanna Steam Electric Station (Susquehanna) for Calendar Year 2007 ML0734804472008-04-0404 April 2008 05/14/2007 to 05/17/2007 - Summary of Meeting with PPL Susquehanna, LLC, Environmental Site Audit Related to the Review of the License Renewal Application ML0808501552008-03-26026 March 2008 Units 1 & 2 - Summary of March 18, 2008, Meeting with PPL Susquehanna, on Submission Details for Susquehanna Units and 2, Pose-Extended Power Uprate (EPU) Power Ascension (Tac No. MD8079) ML0801405152008-02-11011 February 2008 Summary of Telephone Conference Call Held on December 28, 2007, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, LLC, Concerning Requests for Additional Information Pertaining to the Susquehanna Steam Electric Station, Un 2024-06-03
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24150A3362024-05-29029 May 2024 Request for Confirmation of Information Relief Request 1RR06 (Proposed Alternative) Susquehanna Nuclear, LLC Susquehanna Steam Electric Station (Susquehanna), Unit 1 Docket No. 50-387 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 ML24102A1252024-04-10010 April 2024 Request for Additional Information for Susquehanna, Unit 1 Alternative Request 4RR-11 ML23334A1502023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-02 ML23277A0412023-10-0505 October 2023 Notification of Commercial Grade Dedication Inspection (05000387/2024011 and 05000388/2024011) and Request for Information ML23013A2082023-01-13013 January 2023 Request for Additional Information ML22146A1022022-05-26026 May 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000387/2022404 and 05000388/2022404 ML22146A0742022-05-25025 May 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22111A3132022-04-21021 April 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22041A1562022-02-10010 February 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000387/2022013 and 05000388/2022013 ML21316A1242021-11-18018 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Emergency Core Cooling Technical Specifications ML20056E4392020-02-21021 February 2020 Ti 2515/194 Inspection Documentation Request ML20010D2012020-01-0909 January 2020 Request for Additional Information Related to Request to Allow Application of Framatome Analysis Methodologies Necessary to Support a Planned Transition to Atrium 11 Fuel Under Maximum ML19319A0092019-11-14014 November 2019 NRR E-mail Capture - Draft RAI for SSES Units 1 and 2 LAR to Replace ESW Piping ML19319B1922019-11-14014 November 2019 NRR E-mail Capture - RAI for Susquehanna, 1 and 2 License Amendment Request - Replace the Emergency Service Water System and Residual Heat Removal Service Water System ML19128A0232019-05-0707 May 2019 Request for Additional Information: Susquehanna Steam Electric Station, Units 1 and 2 License Amendment Request for ESW Piping Replacement ML18352B1832018-12-13013 December 2018 Enclosurequest for Additional Information (Letter to K. Cimorelli Request for Additional Information Regarding Susquehanna Nuclear, Llc'S Decommissioning Funding Plan Update for Susquehanna Steam Electric Station Independent Spent Fuel Stor ML17180A2002017-07-0707 July 2017 Request for Additional Information Regarding License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits ML17059D2142017-03-0606 March 2017 Susquehanna Steam Electric Station - Supplemental Information Needed for Acceptance of Requested Licensing Action Re: License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage Frequency Limits ML16251A0652016-09-0909 September 2016 Susquehanna Steam Electric Station, Unit 2 - RAI Regarding Temporary Change of Unit 2, Technical Specifications 3.7.1 & 3.8.7 to Allow Replacement of Unit 1, 480 Volt Engineered Safeguard System Load Center Transformers(CAC No. MF7298) ML16245A2052016-09-0101 September 2016 Draft Request for Additional Information Replacement of Load Center Transformers ML16243A0952016-08-30030 August 2016 Draft Request for Additional Information Application for Approval of Indirect Transfer of Control of Licenses ML16060A2302016-03-24024 March 2016 Acceptance of Requested Licensing Action License Amendment Request for Temporary Change of Unit 2 Technical Specifications 3.71 and 3.87 to Allow Replacement of Unit 1 480V Ess Load Center Transformers ML15316A5632015-11-13013 November 2015 Request for Additional Information Regarding Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval(Cac Nos. MF6302 Through MF6307) ML15292A1782015-10-15015 October 2015 TSTF-425 LAR Draft 3rd RAIs ML15230A0802015-08-26026 August 2015 Request for Additional Information Regarding License Amendment Request to Adopt NEI 99-01, Revision 6, EAL Scheme Change ML15209A9742015-08-24024 August 2015 Request for Additional Information License Amendment Request to Adopt Technical Specifications Task Force Traveler (TSTF)-425 ML15230A0462015-08-17017 August 2015 Draft RAIs SSES EAL Scheme Change LAR in Accordance with NEI 99-01 Rev 6 ML15229A2092015-08-17017 August 2015 SSES Draft Request for Additional Information Licensee Request to Adopt TSTF-425 ML15229A2002015-08-17017 August 2015 E-mail from J. Whited to J. Jennings SSES Draft TSTF-425 RAIs ML15183A3502015-07-0202 July 2015 SSES Relief Requests 3RR-19, 3RR-20, and 3RR-21 Draft Identified Information Insufficiencies (TAC Nos. MF6302 Through MF6307) ML15103A3962015-05-22022 May 2015 Request for Additional Information License Amendment Request to Adopt Technical Specifications Task Force Traveler (TSTF)-425 (TAC Nos. MF5151 and MF5152) ML15128A5092015-05-0808 May 2015 E-mail from J. Whited to D. Filchner SSES Draft Request for Additional Information LAR for Implementation of TSTF-425 ML15128A5162015-05-0808 May 2015 SSES Draft Request for Additional Information LAR for Implementation of TSTF-425 ML15008A4702015-01-30030 January 2015 Request for Additional Information Request to Revise Technical Specification 3.4.10, RCS Pressure and Temperature (P/T) Limits. ML15016A2742015-01-16016 January 2015 Draft RAIs License Amendment Request for Change to TS 3.4.10 P/T Limits (TAC Nos. MF4597 and MF45980) ML15016A2722015-01-16016 January 2015 E-mail from J. Whited to D. Filchner Draft RAIs License Amendment Request for Change to TS 3.4.10 P/T Limits (TAC Nos. MF4597 and MF45980) ML14343A9842015-01-0808 January 2015 Request for Additional Information Relief Request 4RR-01 ML14345A2412014-12-16016 December 2014 Request for Additional Information Request for Order Approving Indirect Transfer of Control and Conforming License Amendments ML14346A4022014-12-12012 December 2014 Draft RAIs Relief Request 4RR-01 ML14346A4012014-12-12012 December 2014 E-mail from J. Whited to D. Filchner Susquehanna Steam Electric Station Draft RAIs Relief Request 4RR-01 ML14346A1022014-12-12012 December 2014 Draft License Transfer Revised 2nd RAIs ML14346A1002014-12-12012 December 2014 E-mail from J. Whited to R. Sgarro Susquehanna Steam Electric Station Draft License Transfer Revised 2nd RAIs ML14342A8132014-12-0808 December 2014 SSES Units 1 and 2 Draft RAIs Application for Approval of Indirect Transfer of Control of Licenses ML14342A8082014-12-0808 December 2014 E-mail from J. Whited to R. Sgarro (PPL) SSES Units 1 and 2 Draft RAIs Application for Approval of Indirect Transfer of Control of Licenses ML14233A2772014-08-27027 August 2014 Request for Additional Information License Amendment Request to Change the Low Pressure Safety Limit ML14233A3392014-08-21021 August 2014 Draft RAIs for Susquehanna Steam Electric Station Units 1 and 2 License Amendment Request for Changes to the Low Pressure Safety Limits ML13298A7582014-03-0707 March 2014 Request for Additional Information Regarding Request for Changes to Technical Specification Surveillance Requirements to Increase Diesel Generator Minimum Steady State Voltage (TAC ME9607 and ME960) ML13298A7812014-03-0707 March 2014 Request for Additional Information Regarding Request for Changes to Technical Specification Surveillance Requirement 3.8.1.19 to Increase Diesel Generator Minimum Steady State Frequency (TACs ME9609. ML14013A1502014-01-31031 January 2014 Request for Additional Information Regarding Relief Requests for the Fourth 10-Year Inservice Testing Interval 2024-05-07
[Table view] |
Text
October 24, 2007 LICENSEE: PPL Susquehanna, LLC FACILITY: Susquehanna Steam Electric Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 26, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PPL SUSQUEHANNA, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of PPL Susquehanna, LLC held a telephone conference call on September 26, 2007, to discuss and clarify the staff's requests for additional information (RAIs) concerning the Susquehanna Steam Electric Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staff's RAIs.
provides a listing of the participants and Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/ Evelyn Gettys, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosures:
As stated cc w/encls: See next page
ML072760276 OFFICE PM:RLRA:DLR LA:DLR BC:RLRA:DLR NAME EGettys IKing LLund DATE 10/06/07 10/06/07 10/24/07 Enclosure 1 TELEPHONE CONFERENCE CALL SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS SEPTEMBER 26, 2007 PARTICIPANTS AFFILIATIONSEvel yn Gett ys U.S. Nuclear Re gulator y Commission (NRC)Simon Shen g NRC Neil Cuddin gham PPL Sus quehanna, LLC (PPL) Jeff Weik PPL Mike Ma y PPL Enclosure 2 REQUESTS FOR ADDITIONAL INFORMATION SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION SEPTEMBER 26, 2007 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of PPL Susquehanna, LLC held a telephone conference call on September 26, 2007, to discuss and clarify the following requests for additional information (RAIs) concerning the Susquehanna Steam Electric Station, Units 1 and 2, license renewal application (LRA).
RAI 4.7.3-2 (as revised in letter of September 12, 2007, ML072640134)
LRA Appendix C discussed the applicants response to the Boiling Water Reactor Vessel and Internals Project (BWRVIP) report application action items. The BWRVIP reports addressing the time-limited aging analyses (TLAA) regarding irradiation-assisted stress corrosion cracking (IASCC) in austenitic stainless steel reactor pressure vessel (RPV) internals are BWRVIP-25, " BWR Core Plate Inspection and Flaw Evaluation Guidelines," BWRVIP-26-A, "Boiling-Water Reactor (BWR) Top Guide Inspection and Flaw Evaluation Guidelines," BWRVIP-76, "BWR Core Shroud Inspection and Flaw Evaluation Guidelines," and BWRVIP-47-A, "BWR Lower Plenum Inspection and Flaw Evaluation Guidelines." Although managing TLAA using aging management programs (AMPs) or other measures is stated in Appendix C in your response to BWRVIP report application action items, IASCC in austenitic stainless steel RPV internals should be discussed in the TLAA section to build the connection between LRA Section 4.0 and Appendix C. The safety evaluation for BWRVIP-76 was issued on July 28, 2006. Therefore, you need to perform a plant-specific evaluation using BWRVIP-76, and make a commitment to follow all BWRVIP-76 requirements and limitations, as modified by the NRC staff's safety evaluation on the BWRVIP-76 report. Also, the statement in Appendix C, that a BWRVIP-76 is not included because the safety evaluation report has not yet been issued, needs to be revised.
During your plant-specific evaluation using BWRVIP-76, please address the following:
Section 4.1 Item 5 of the BWRVIP-100-A report, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds, dated August 2006, states that fracture toughness values of stainless steel materials that are exposed to neutron fluence values greater than 1 X 10 21 n/cm 2 (E > 1 MeV) are lower than those used in Appendix C of the BWRVIP-76 report. It is likely that during the license renewal period, core shroud welds and base materials will be exposed to neutron fluence values exceeding 1 X 10 21 n/cm 2 (E > 1 MeV). Since the inspection frequency in the BWRVIP-76 report is based on fracture toughness values which are not consistent with the BWRVIP-100-A report, the staff requests that you reevaluate the inspection frequency and the inspection methods that are specified in Section 3 of the BWRVIP-76 report, taking into account the lower fracture toughness values identified in the BWRVIP-100-A report for core shroud welds that would be exposed to a neutron fluence value greater than 1 X 10 21 n/cm 2 (E > 1 MeV).
Discussion: In this discussion with the applicant the staff indicated that the NRC staff has not approved BWRVIP-76 for license renewal; however, the staff wants a commitment from the applicant to the future staff's position. The RAI has been revised as the following:
RAI 4.7.3-2
LRA Appendix C discussed the applicant's response to the BWRVIP report application action items. The BWRVIP reports addressing the TLAA regarding IASCC in austenitic stainless steel RPV internals are BWRVIP-25, "BWR Core Plate Inspection and Flaw Evaluation Guidelines," BWRVIP-26-A, "BWR Top Guide Inspection and Flaw Evaluation Guidelines," BWRVIP-76, "BWR Core Shroud Inspection and Flaw Evaluation Guidelines," and BWRVIP-47-A, "BWR Lower Plenum Inspection and Flaw Evaluation Guidelines." Although managing TLAA using AMPs or other measures is stated in Appendix C in your response to BWRVIP report application action items, IASCC in austenitic stainless steel RPV internals should be discussed in the TLAA section to build the connection between LRA Section 4.0 and Appendix C. Further, although the NRC review of BWRVIP-76 license renewal for complience with the license renewal rule has not been completed, you need to make a commitment to follow all BWRVIP-76 license renewal requirements and limitations and to address the conditions imposed by the staff in the pending NRC staff's safety evaluation on this report.
Letter to PPL Susquehanna, from E. Gettys dated October 24, 2007
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON SEPTEMBER 26, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND PPL SUSQUEHANNA, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION
- HARD COPY: DLR RF E-MAIL: PUBLIC SSmith (srs3) SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter
RGuzman BRogers EGettys Susquehanna Steam Electric Station Units 1 and 2 cc: Cornelius J. Gannon Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467
Robert M. Paley General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179
Walter E. Morrissey Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Ronald E. Smith General Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Steven M. Cook Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467
Bryan A. Snapp, Esq. Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179
Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179
Richard W. Osborne Allegheny Electric Cooperative, Inc. 212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266
Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035 Susquehanna Steam Electric Station Units 1 and 2 cc: Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803