IR 05000387/2024002
| ML24225A143 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna (NPF-014, NPF-022) |
| Issue date: | 08/12/2024 |
| From: | Jon Greives Division of Operating Reactors |
| To: | Berryman B Susquehanna |
| References | |
| IR 2024002 | |
| Download: ML24225A143 (1) | |
Text
August 12, 2024
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -
INTEGRATED INSPECTION REPORT 05000387/2024002 AND 05000388/2024002
Dear Brad Berryman:
On June 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Susquehanna Steam Electric Station, Units 1 and 2. On August 1, 2024, the NRC inspectors discussed the results of this inspection with Edward Casulli, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a an NCV consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Susquehanna Steam Electric Station, Units 1 and 2.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Susquehanna Steam Electric Station, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Jonathan E. Greives, Chief Projects Branch 4 Division of Operating Reactor Safety
Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000387 and 05000388
License Numbers:
Report Numbers:
05000387/2024002 and 05000388/2024002
Enterprise Identifier: I-2024-002-0044
Licensee:
Susquehanna Nuclear, LLC
Facility:
Susquehanna Steam Electric Station, Units 1 and 2
Location:
769 Salem Blvd., Berwick, PA
Inspection Dates:
April 1, 2024 to June 30, 2024
Inspectors:
J. England, Senior Resident Inspector
E. Brady, Resident Inspector
H. Anagnostopoulos, Senior Health Physicist
S. Haney, Senior Enforcement Specialist
J. Kulp, Senior Reactor Inspector
C. Lally, Senior Operations Engineer
Approved By:
Jonathan E. Greives, Chief
Projects Branch 4
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Susquehanna Steam Electric Station,
Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation (NCV) is documented in report section: 71111.2
List of Findings and Violations
Testing, Inspection, and Maintenance Were Not Performed on the Hardened Containment Ventilation System Power Supply Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000387,05000388/2024002-01 Open/Closed
[H.3] - Change Management 71111.15 A self-revealed Green finding and associated NCV of NRC Order EA-13-109 was identified when the licensee did not perform battery performance testing, inspection, or maintenance of the hardened containment vent system (HCVS) battery. Specifically, there were no activities to monitor battery health after installation, which would have identified degradation prior to the battery being identified as failed during containment isolation testing.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period shut down for the U123RIO refueling outage. On April 23, 2024, the unit was started up and achieved rated thermal power on April 29, 2024. On May 9, 2024, the unit was down powered to 59 percent due to 'B' reactor building closed-cooling water chiller shutdown and returned to rated thermal power May 11, 2024. On May 18, 2024, the unit was down powered to 75 percent for control rod exercising and returned to rated thermal power May 19, 2024. On June 29, 2024, the unit was down powered to 68 percent for a rod sequence exchange and returned to rated thermal power June 30, 2024.
Unit 2 began the inspection period at rated thermal power. On June 14, 2024, the unit down powered to 68 percent for rod sequence exchange and returned to rated thermal power June 15, 2024. The unit was at or near rated thermal power for the rest of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot temperatures on June 7, 2024.
71111.04 - Equipment Alignment
Partial Walkdown (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit Common 'D' emergency diesel generator (EDG) support systems during the week of April 22, 2024
- (2) Unit 1 high-pressure coolant injection during the week of May 6, 2024
- (3) Unit Common 'C' EDG on May 30, 2024
- (4) Unit 1 residual heat removal service water train 'A' on June 20, 2024
71111.05 - Fire Protection
Fire Area Walkdown and Inspection (IP Section 03.01) (6 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit 1 drywell, fire zone (FZ) 1-4F, on April 7, 2024
- (2) Unit 1 main steam pipeway, FZ I-4G, on April 9, 2024
- (3) Unit Common emergency service water pumphouse, FZs 0-51 and 0-52, on April 22, 2024
- (4) Unit 2 reactor building, FZs 2-2A, 2-2B, 2-1C, and 2-1D, on May 1, 2024
- (5) Unit 1 turbine building common generator area, reactor coolant recirculation pump motor generator area and heating and ventilation equipment room, FZs 0-35A, 1-35C, and 1-36A, on May 23, 2024
- (6) Unit Common lower cable spreading room and lower relay room, FZs 0-25A and 0-25E, on June 17, 2024
71111.08G - Inservice Inspection Activities (Boiling-Water Reactor)
Boiling-Water Reactor Inservice Inspection Activities - Nondestructive Examination and Welding
Activities (IP Section 03.01)
The inspectors evaluated boiling-water reactor nondestructive testing by reviewing the following examinations from April 1 to 4, 2024:
- Automatic Encoded Phased Array Ultrasonic Examination of the BM Reactor Pressure Vessel Weld (VE-24-008)
- Manual Ultrasonic Examination of Residual Heat Removal Pipe to Elbow Weld DCA1101-FW-5 (UT-24-006)
- Ultrasonic Thickness Measurements of Reactor Water Bottom Head Drain - 90 Degree Elbow (FAC-U1-24-050)
- Ultrasonic Thickness Measurements of Reactor Water Bottom Head Drain - Straight Pipe (FAC-U1-24-051)
- Ultrasonic Thickness Measurements of Reactor Water Bottom Head Drain - Expander Inlet (FAC-U1-24-052)
- Ultrasonic Thickness Measurements of FAC-U1-24-053, Reactor Water Bottom Head Drain - Expander Outlet (FAC-U1-24-053)
- Enhanced Visual Examination (EVT-1) Top Guide Beam Location 02-19 (1-B13.40.0409)
- Manual Ultrasonic Examination of N5A Nozzle to Safe End Dissimilar Metal Weld (UT-24-009)
- Manual Ultrasonic Examination of High-Pressure Core Injection Steam Line Pipe to Elbow Weld DBA-1021-2-G (UT-24-008)
Pressure Boundary Weld
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Unit 2 control room during the residual heat removal 'A' loop flow surveillance on May 8, 2024.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed a Unit 1 simulator scenario evaluation that included an earthquake and suppression pool flooding on May 9, 2024.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:
- (1) Unit Common 250 volts direct current system, batteries, and battery chargers due to multiple recent issues on May 15, 2023
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management (IP Section 03.01) (1 Sample)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit Common failure of fiber optic board on 'E' EDG during the week of June 10, 2024
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Units 1 and 2 hardened containment ventilation functionality assessment due to degraded batteries on April 4, 2024
- (2) Unit 1 expected voltage not received during performance of anticipated transient without scram recirculation pump trip functional test due to degraded relay 62X-14725D1 on April 19, 2024
- (3) Unit Common 'A' EDG trip due to Gen Loss Field Trip on April 29, 2024
- (4) Unit 1 main steam isolation valve due to continuity light out with low voltage on May 14, 2024
- (5) Unit Common 'B' EDG due to Hi Priority alarm received on June 9, 2024
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Unit 1 Implementation for GL-89 MOVs a Four Rotor Design Modification - Engineering Change Package 2107077 (permanent modification)
- (2) Unit Common Licensing Document Change Notice, LDCN-5814, Elimination of Secondary Containment Bypass Leakage Testing Requirements for Feedwater Penetration (permanent modification)
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated Unit 1 refueling outage U123RIO activities from March 25 to April 29, 2024.
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (IP Section 03.01) (9 Samples)
- (1) Unit Common 'E' EDG jacket water heater temperature control valve repairs on August 23, 2023
- (2) Unit Common 'C' EDG run following replacement of bus 1C sync selector switch on April 3, 2024
- (3) Unit 1 SO-149-201 following regulator and elastomer replacement of an HV151F122A
'A' residual heat removal testable check valve on April 3, 2024
- (4) Unit 1 SM-104-002, 4kV 1A202 24-Month Undervoltage Channel Calibration, following relay replacement on April 5, 2024
- (5) Unit 1 SO-100-023A, ASME Class 1 Boundary System Leakage Test - 10-Year Test, following control rod drive mechanism replacement on April 16, 2024
- (6) Unit 1 SO-152-002, Quarterly HPCI Flow Verification After Repair of the HV155F001, HPCI Steam Admission Valve on April 24, 2024
- (7) Unit Common SO-024-014, Monthly Diesel Generator 'E' Operability Test, following emergency service water valve work on week of June 10, 2024
- (8) Unit Common MT-024-033E, Diesel Generator 'E' Relay Testing, following Agastat relay preventive maintenance and 'G' fiber optic board replacement on June 12, 2024
- (9) Unit Common SO-216-A03, Quarterly Residual Heat Removal Service Water (RHRSW) System Flow Verification Division 1, following spray pond nozzle cleaning and residual heat removal service water pump 2A discharge check valve disassembly and inspection on June 25, 2024
Surveillance Testing (IP Section 03.01) (3 Samples)
- (1) Unit 1 inspection of blowout panels on April 1, 2024
- (2) Unit 1 SO-149-101, Residual Heat Removal Logic System Functional Test Division I Outage Partial on April 11 and 12, 2024
- (3) Unit 1 SI-183-321, Quarterly Calibration of Drywell Pressure Channel PS-E11-1N010A, B, C, D (Automatic Depressurization System Permissive, Reactor Core Isolation Cooling Exhaust Vacuum Breaker Isolation) on May 2, 2024
Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)
- (1) DC-B5B-100, Depressurization of Reactor Pressure Vessel Using Automatic Depressurization System Safety Relief Valves with a Portable Power Supply Connected in the Upper and Lower Relay Room on May 29,
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.
Instructions to Workers (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)
The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:
- (1) Workers exiting the radiologically controlled area at the Unit 1 access control point during a refueling outage
- (2) Controls for high dose rate water filters (used for desludging) stored under water in the suppression pool
Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)
The inspectors evaluated the licensees control of radiological hazards for the following radiological work:
- (1) Suppression pool diving activities with desludging and coating inspections (RWP 20241115)
- (2) Transfers of high radiation material during the refueling outage (RWP 20241403)
- (3) Fuel movements and in-vessel inservice inspection activities (RWP 20241002)
- (4) Control rod drive mechanism removal and replacement under vessel (RWP20241351)
High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)
The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:
- (1) Unit 1 drywell and associated access control points at the personnel hatch and the equipment hatch
- (2) Locked high radiation area associated with desludging water filter storage in the suppression pool
- (3) Control rod drive removal hatch, removal track, and path to the control rod drive mechanism rebuild room
Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
- (1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.
71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,
and Transportation
Shipment Preparation (IP Section 03.04)
- (1) The inspectors observed the preparation of radioactive shipment 24-023 on April 2,
OTHER ACTIVITIES - BASELINE
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Review of corrective actions associated with the following condition reports (CRs):
- (1) CR-2023-12632, entered ON-PWR-201 on July 31, 2023;
- (2) CR-2023-06833, reactor vessel/cavity level lowering prior to initiating letdown while performing OP-2RF-001 6.16;
- (4) CR-2024-02302, residual heal removal service water heat exchanger 'B' outlet HV-21215B found open during panel walkdowns
- (2) Unit 2 review of corrective actions associated with CR-2023-05057, for feedwater penetration local leak rate test failure and secondary containment bypass leakage violation, the week of May 13, 2024
71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)
- (1) The inspectors reviewed the licensees corrective action program for trends in the first and second quarters of 2024 that might be indicative of a more significant safety issue.
INSPECTION RESULTS
Testing, Inspection, and Maintenance Were Not Performed on the Hardened Containment Ventilation System Power Supply Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000387,05000388/2024002-01 Open/Closed
[H.3] - Change Management 71111.15 A self-revealed Green finding and associated NCV of NRC Order EA-13-109 was identified when the licensee did not perform battery performance testing, inspection, or maintenance of the HCVS battery. Specifically, there were no activities to monitor battery health after installation, which would have identified degradation prior to the battery being identified as failed during containment isolation testing.
Description:
The licensee was required by NRC Order EA-13-109 to have a reliable, severe accident capable HCVS. The HCVS was implemented using an existing drywell penetration and contains two primary containment isolation valves. These valves are air operated valves that require nitrogen to open and use a spring to close. Nitrogen is directed to the valve for opening using an AC powered solenoid valve, which directs nitrogen from bottles to the HCVS valves. In addition to the solenoid valve operation, power is needed for the control room switches, instrumentation for vent status, and instrumentation for effluent discharge.
The control room switches allow remote system operation from the control room. Vent status is determined with valve positions indication, pressure instruments, and temperature instruments. Radiation sensors are used to monitor effluent discharge. The system is required to provide adequate power and motive gas to support 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of operation without normal AC power. A 125 DC voltage battery is designed to provide the power during the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in the event of an extended loss of power, with a portable EDG used to power the system after the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
On June 6, 2013, the NRC issued order EA-13-109, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, following the Fukushima Dai-ichi nuclear plant earthquake and tsunami.
EA-13-109, Section 1.2.13, states the HCVS shall include features and provisions for operation, testing, inspection, and maintenance adequate to ensure that reliable function and capability are maintained. Sections 1.2.8 and 1.2.9 describe two of the system functions.
Section 1.2.8 states the HCVS shall include means to monitor the status of the vent system (e.g., valve position indication) from the control panel. Section 1.2.8 further states the monitoring system shall be designed for sustained operation during an extended loss of AC power. Section 1.2.9 states the HCVS shall include a means to monitor effluent discharge for radioactivity that may be released from operation of the HCVS. The monitoring system shall provide indication from the control panel. The section further states the system shall be designed for sustained operation during an extended loss of AC power. Sections 1.2.8 and 1.2.9 functions cannot be maintained without functioning batteries. Section 1.2.13, states, in part, the HCVS shall include features and provisions for testing, inspection, and maintenance adequate to ensure that reliable function and capability are maintained. Following battery installation, the licensee created an action on May 1, 2015, AR-2015-12620, to evaluate and implement a maintenance strategy for the 125 DC voltage batteries. The action was extended multiple times without inspection, testing, or maintenance activities being implemented.
On April 4, 2024, the station performed local leak rate testing of the primary containment isolation valves in the HCVS. The procedure required a breaker to be closed which provides battery power to the solenoid valves and valve position indication. The breaker tripped when closed, and the system did not receive power. CR-2024-05592 was generated to investigate the issue. On April 29, 2024, during troubleshooting the licensee determined that the HCVS batteries for both units were degraded. In both batteries, multiple cell-to-cell connections were found corroded and disconnected. The batteries were determined to be non-functional. Based on the inspectors' questions, the batteries were added to the equipment important to emergency response (EITER) non-functional list. Once the batteries were added to the EITER list, the battery replacements were prioritized and completed within 90 days of identification of the non-functionality.
Corrective Actions: Units 1 and 2 HCVS batteries were replaced on June 25 and 26, 2024, respectively. The station created a corrective action to determine and implement the required testing, inspection, and maintenance of the HCVS battery.
Corrective Action References: CR-2024-09634, CR-2024-09636
Performance Assessment:
Performance Deficiency: A self-revealed Green finding and associated NCV was identified because the licensee did not perform battery testing, inspection, or maintenance as required by EA-13-109.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, since the licensee had not conducted battery testing, inspection, or maintenance of the HCVS battery from installation in 2015 and 2016, there was reasonable doubt that the equipment maintained the capability to meet the requirements of the associated FLEX strategies (i.e., that no portable equipment should be required to operate the HCVS within the first 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />).
Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power. The finding screened as very low safety significance (Green) because it was associated with equipment, training, procedures, and/or other programmatic aspects credited for the sole purpose of satisfying the requirements of Order EA-13-109.
Cross-Cutting Aspect: H.3 - Change Management: Leaders use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority.
The station created an action to determine and implement the testing, inspection, or maintenance of the HCVS battery, but the required changes were not implemented in a timely manner.
Enforcement:
Violation: NRC Order EA-13-109 was issued to Susquehanna Steam Electric Station, Units 1 and 2, effective June 6, 2013. NRC Order EA-13-109, Attachment 2, Section 1.2.13, states, in part, the HCVS shall include features and provisions for testing, inspection, and maintenance adequate to ensure that reliable function and capability are maintained.
Contrary to this, since installation, the licensee did not provide provisions for testing, inspection, and maintenance adequate to ensure that the reliable function and capability of the HCVS batteries were maintained. As a result, the HCVS batteries were found degraded and non-functional on April 4, 2024, for Unit 1 and April 21, 2024, for Unit 2.
Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Licensee-Identified Non-Cited Violation 71111.24 This violation of very low safety significance was identified by the licensee and has been entered into the licensees corrective action program and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Violation: Title 10 of the Code of Federal Regulations Part 50, Appendix B, Criterion XVI, Corrective Action, states measures shall be established to assure conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and non-conformances are promptly identified and corrected. Contrary to the above, from August 2023 through January 2024, the licensee failed to take appropriate corrective actions associated with the E EDG temperature control valve, which was previously identified as having internal leakage resulting in abnormally low jacket water temperatures when emergency service water was in service. As a result, the E EDG was declared inoperable on January 22, 2024, when the jacket water temperature dropped below the technical specification limit. Engineering later determined that the EDG remained operable with the condition because the impact would have increased EDG start time from 7.6 to 9.3 seconds, which is below the required value of 10 seconds.
Significance/Severity: Green. The inspectors assessed the significance of the finding using IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, and determined it screened as very low safety significance (Green) because it did not represent a loss of the probabilistic risk assessment function for greater than its technical specification allowed outage time.
Corrective Action References: CR-2024-01353
Observation: Review of Feedwater Penetration Leakage Corrective Actions 71152A The inspectors reviewed the licensees corrective action program CRs, action requests, and the associated corrective actions including corrective maintenance WOs to repair feedwater system containment isolation valves that experienced test leakage exceeding administrative leakage limits during the Unit 2 spring 2023 refueling outage. The inspectors also reviewed procedure changes made to ensure proper valve reassembly and preventive maintenance scheduling. The inspectors did not identify any violations or performance deficiencies during the review.
Observation: Semiannual Trend 71152S The inspectors conducted a semiannual trend review by evaluating a sample of issues that occurred in the first and second quarters of 2024. During the evaluation, the inspectors verified the issues identified were addressed within the scope of the corrective action program. The inspectors reviewed related databases for trends and considered prior issues while performing routine walkdowns and attending the plan of the day meetings. The licensee has identified an adverse trend of deficiencies of the EDGs. The licensee has generated an action to review the last 5 years of EDG issues and use this information to adjust the maintenance strategy, as needed. The inspectors will continue to monitor the corrective action program and maintenance effectiveness during routine inspection activities.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 4, 2024, the inspectors presented the radiological hazards inspection results to Paul Ervin, Manager Nuclear Oversight, and other members of the licensee staff.
- On April 4, 2024, the inspectors presented the inservice inspection results to Paul Ervin, Manager Nuclear Oversight, and other members of the licensee staff.
- On May 9, 2024, the inspectors presented the operations department event review problem identification and resolution inspection results to Katie Brown, NRA Supervisor, and other members of the licensee staff.
- On August 1, 2024, the inspectors presented the integrated inspection results to Edward Casulli, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Plant
Status
Corrective Action
Documents
Resulting from
Inspection
AR-2024-05542
AR-2024-06210
CR-2024-06619
CR-2024-07578
CR-2024-07645
CR-2024-07779
CR-2024-07782
CR-2024-07783
CR-2024-07784
CR-2024-07785
CR-2024-08164
CR-2024-08648
CR-2024-08925
CR-2024-08927
CR-2024-08928
Procedures
NDAP-00-1913
Seasonal Readiness
Revision 18
Corrective Action
Documents
CR-2024-07135
CR-2024-07138
Corrective Action
Documents
Resulting from
Inspection
CR-2024-08791
CR-2024-08807
Drawings
M-112
Unit 1 P&ID RHR Service Water System
Revision 56
M-134
P&ID Diesel Auxiliaries Jacket Water and Lube Oil Systems,
Sheet 4
Revision 8
M-156
Unit 1 P&ID High-Pressure Coolant Injection Turbine - Pump
Revision 40
Procedures
CL-024-0016
Diesel Generator 'C'
Revision 13
CL-024-0018
Diesel Generator 'D'
Revision 14
CL-116-0012
Unit 1 RHRSW System A
Revision 11
CL-152-0012
Valves, Unit 1 HPCI System
Revision 29
Corrective Action
Documents
CR-2024-09642
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
Resulting from
Inspection
AR-2024-08712
Fire Plans
FP-1-CS-698-A
Control Structure-EL. 698
Revision 1
FP-1-CS-714-A
Control Structure-EL. 714
Revision 1
FP-1-ESSW-685-A Prefire Plan Unit 1 Pump House-ESSW Elev. 685'6"
Revision 0
FP-1-RB-719-2
Main Steam Pipeway
Revision 0
FP-1-RB-719-3
Emergency Personnel Decontamination Station
Revision 0
FP-1-RB-749-7
Circulation Space 2
Revision 0
FP-1-TB-729-0
U1 Turbine Building El. 729
Revision 0
FP-1-TB-762-1
U1 Heating and Ventilation Equip. Room
Revision 0
Drywell (I 400, I 516, I 607) Fire Zone 1 4F Elevation 704'
thru 807'
Revision 4
FP-2-RB-670-0
Susquehanna S.E.S. Prefire Plan U2 Reactor Building
El. 670
Revision 0
FP-2-RB-670-2
Susquehanna S.E.S. Prefire Plan U2 Remote Shutdown
Panel
Revision 0
FP-2-RB-670-4
Susquehanna S.E.S. Prefire Plan U2 Open Area
Revision 0
FP-2-RB-670-5
Susquehanna S.E.S. Prefire Plan U2 RCIC Valve Room
Revision 0
FP-2-RB-670-6
Susquehanna S.E.S. Prefire Plan U2 HPCI Valve Room
Revision 0
FP-2-RB-670-7
Susquehanna S.E.S. Prefire Plan U2 Open Area
Revision 0
71111.11Q Procedures
GO-100-02
Plant Startup, Heatup, and Power Operation
Revision 126
SO-249-A02
Quarterly RHR System Flow Verification Division 1
Revision 30
Corrective Action
Documents
CR-2022-09837
CR-2022-11036
CR-2022-13732
CR-2022-17631
CR-2022-17707
CR-2023-04998
CR-2023-05211
CR-2023-05298
CR-2023-05433
CR-2023-07804
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CR-2023-09775
CR-2023-11656
CR-2023-11930
CR-2023-12897
CR-2023-13577
CR-2024-03496
CR-2024-03710
CR-2024-03717
CR-2024-05753
CR-2024-06251
CR-2024-06719
CR-2024-06791
CR-2024-06963
CR-2024-08019
Corrective Action
Documents
Resulting from
Inspection
CR-2024-08383
Work Orders
RTSV 2250016
RTSV 2420466
RTSV 2496598
RTSV 2542436
Procedures
NDAP-QA-0340
Protected Equipment Program
Revision 46
Corrective Action
Documents
AR-2015-12620
CR-2024-05592
CR-2024-06852
CR-2024-06998
CR-2024-07001
CR-2024-07335
CR-2024-07371
CR-2024-08057
CR-2024-09234
Corrective Action
Documents
Resulting from
Inspection
AR-2024-08943
CR-2024-08721
CR-2024-09353
CR-2024-10013
CR-2024-10014
Drawings
E-157
Alternate Rod Injection Schematic Diagram, Sheet 7
Revision 2
M1-B21-131
Nuclear Steam Supply Shutoff Sys Susquehanna 1,
Sheet 3112
Revision 15
M30-124
Susquehanna S.E.S. Common DG Control Schematic
Starting Sequence, Sheet 1
Revision 24
M30-124
Susquehanna S.E.S. Common DG Control Schematic
Starting Sequence Control Panel 0C521A, Sheet 4
Revision 6
M30-124
Susquehanna S.E.S. Common DG Control Schematic
Shutdown and Alarm System 0C521A, Sheet 11
Revision 16
M30-124
Susquehanna S.E.S. Common DG Control Schematic
Starting Sequence Control Panel 0C521B, Sheet 1A
Revision 12
M30-124
Susquehanna S.E.S. Common DG Control Schematic
Starting Sequence Control Panel 0C521B, Sheet 4A
Revision 1
Engineering
Changes
Hardened Containment Vent System Battery Sizing
Revision 0
AVCO Coil and Stem for MSIV Solenoids
Revision 0
MSIV Pilot Solenoid Valve Current Monitoring
Revision 1
Miscellaneous
Venting Suppression Chamber Through the HCVS
Calculations
EC-059-1024
Design Requirement for and Evaluation of Potential
Secondary Containment Bypass Leakage (SCBL) Pathways
Revision 17
Engineering
Changes
Implementation for GL 89-10 MOV'S a Four Rotor Design
Change
Revision 0
Procedures
Emergency Planning Forms and Supplementary Instructions
Revision 24
TSC Technical Support Coordinator
Revision 44
Corrective Action
Documents
Resulting from
Inspection
CR-2024-06683
CR-2024-06686
CR-2024-06691
CR-2024-06773
CR-2024-06850
Procedures
GO-100-02
Plant Startup, Heatup, and Power Operation
Revision 126
Corrective Action
Documents
EWR-2024-02815
CR-2023-04344
CR-2024-01353
CR-2024-05401
CR-2024-09208
CR-2024-10499
Corrective Action
Documents
Resulting from
Inspection
CR-2024-06686
CR-2024-08749
CR-2024-09388
Drawings
M-151
Susquehanna SES Unit 1 P&ID Residual Heat Removal.
Sheet 1
Revision 72
Miscellaneous
PCWO 2629500-0 Investigate TCV03412E JW Temp Control Vlv (Priority 4)
Procedures
DC-B5B-100
Depressurization of Reactor Pressure Vessel using
Automatic Depressurization System Safety Relief Valves
with a Portable Power Supply Connected in the Upper and
Lower Relay Room
Revision 14
MT-024-033E
Diesel Generator E Relay Testing
Revision 2
MT-GE-040
Agastat Inspection, Calibration, Removal, and Installation
Revision 13
OT-054-076
ESW Flow Balance
Revision 9
SI-183-321
Quarterly Calibration of Drywell Pressure Channel PS-E11-
1N010A, B, C, D (ADS Permissive, RCIC Exhaust Vacuum
Breaker Isolation)
Revision 25
SM-104-002
4kV 1A202 24-Month Undervoltage Channel Calibration
Revision 18
SO-024-014
Monthly Diesel Generator 'E' Operability Test
Revision 54
SO-100-023A
ASME Class 1 Boundary System Leakage Test - 10-Year
Test (Infrequently Performed Test or Evolution)
Revision 2
SO-104-102
4.16KV Class 1E Bus 1C (1A203) Offsite Supply Check
Revision 4
SO-149-101
RHR Logic System Functional Test Division I Outage Partial
Revision 11
SO-149-201
1035 PSIG LLRT of LPCI Loop 'A' Injection Pressure
Isolation Valves
Revision 4
SO-152-002
Quarterly HPCI Flow Verification After Repair of the
HV155F001, HPCI Steam Admission Valve
Revision 75
SO-216-A03
Quarterly Residual Heat Removal Service Water (RHRSW)
System Flow Verification Division 1
Revision 23
Work Orders
PCWO 2047642
PCWO 2629500-0
PCWO 2735356-0
RTPM 2506956
RTPM 2575640-0
RTPM 2590952
RTPM 2665769
RTSV 2542431
RTSV 2643242
RTSV 2714671
RTSV 2718984
Calculations
EC-RADN-1189
CRHE Dose Analysis Input for LER 50-388/2023-001-00
U2-21RIO SCBL Results
Revision 0
Corrective Action
Documents
AR-2021-03120
AR-2023-05354
AR-2023-05752
AR-2023-06362
AR-2023-06772
AR-2023-06921
AR-2023-07688
CR-2023-05314
CR-2023-06833
CR-2023-05557
CR-2023-06444
CR-2023-12632
CR-2024-02302
Corrective Action
Documents
Resulting from
Inspection
CR-2024-07779
CR-2024-07782
CR-2024-07783
CR-2024-07784
CR-2024-07785
CR-2024-07788
Procedures
Diesel Generator Abnormal Operating Procedure
Revision 5
MT-AD-504
Scaffold Erection, Review, and Inspection
Revision 38
NDAP-QA-0027
Concurrent and Independent Verification Requirements
Revision 18
NDAP-QA-0340
Protected Equipment Program
Revision 41
NDAP-QA-1902
Integrated Risk Management
Revision 43
ON-PWR-201
Reactor Power
Revision 8
OP-1RF-001
RX Vessel/Cavity Flood-up and Let Down During Refueling
Outages
Revision 40
OP-2RF-001
RX Vessel/Cavity Flood-up and Let Down During Refueling
Outages
Revision 36
OP-AD-300
Administration of Operations
Revisions
49-51
On Line and Shutdown Nuclear Risk Assessment Program
Revision 29
Performance of the Independent Pre-Outage Shutdown
Safety Risk Management Plan Assessment
Revision 3
Work Orders
PCWO 2631477-0
PCWO 2631477-1
PCWO 2658495-0
RACT 2629364
RLWO 2647852