Draft Request for Additional Information Replacement of Load Center Transformers
ML16245A205
Person / Time
Site: Susquehanna Talen Energy icon.png
Issue date: 09/01/2016
From: Tanya Hood
Plant Licensing Branch 1
To: Mcintosh R
Susquehanna
Hood T, NRR/DORL/LPL1-2, 415-1387
References
CAC MF7298, PLA-7384
Download: ML16245A205 (4)


Text

DRAFT REQUEST FOR ADDITIONAL INFORMATION OFFICE OF NUCLEAR REACTOR REGULATION LICENSE AMENDMENT REQUEST REGARDING REPLACEMENT OF LOAD CENTER TRANSFORMERS SUSQUEHANNA NUCLEAR, LLC ALLEGHENY ELECTRIC COOPERATIVE, INC.

SUSQUEHANNA STEAM ELECTRIC STATION, UNIT 2 DOCKET NO. 50-388 By letter dated January 28, 2016, as supplemented by letter dated April 6, 2016, (Agencywide Documents Access and Management System Accession Nos. ML16029A031 and ML16097A4896, respectively), Susquehanna Nuclear, LLC (the licensee) submitted a license amendment request (LAR) for Susquehanna Steam Electric Station (SSES), Unit 2. The proposed amendment would modify SSES, Unit 2, Technical Specification (TS) 3.7.1, Residual Heat Removal Service Water (RHRSW) System and the Ultimate Heat Sink (UHS), and TS 3.8.7, Distribution Systems - Operating, to increase the completion time for Conditions A and B of TS 3.7.1 and Condition C of TS 3.8.7 from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days, in order to accommodate replacement of the 480 volt (V) engineered safeguard system load center transformers for SSES, Unit 1.

The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information submitted by the licensee and determined that additional information is required to complete its review.

The specific request for additional information (RAI) is addressed below.

RAI 1

When extending the Completion Time (CT) of a TS in the proposed system lineup (i.e., 1X210 or 1X220 de-energized), the licensee will make one train of RHRSW and Emergency Service Water (ESW) inoperable by disabling power to the RHRSW array valves and the bypass valve.

If during the revised CT of 7 days, the station experiences a dual unit loss of offsite power (LOOP) with a single failure of the redundant RHRSW train, both trains of RHRSW and ESW would be inoperable. The scenario presented in the Enclosure to the LAR dated January 26, 2016 (pages 6 and 7 of 30) does not address this concern. Based on this concern:

Provide results of an analysis stating how the station will mitigate a dual unit LOOP when in the revised CT of 7 days. The results of the analysis should provide either:

1

a. Reasonable assurance with specified compensatory actions in place at the start of the planned maintenance, that the probability of failure of the remaining train of RHRSW has been significantly reduced to justify the 7 day CT, or
b. Assume the only remaining train of RHRSW has failed with the LOOP, and with defined compensatory actions in place at the start of the planned maintenance, demonstrate that RHRSW can be restored such that safe shutdown and cooldown to Mode 4 can be achieved for both units including cooling of the spent fuel pool. In your analysis, (i) assume the LOOP duration is the full 7 days, (ii) identify the minimum time Unit 1 must be shut down in order for your analysis to be valid, since Unit 1 will already be in Mode 4, (iii), describe the operator actions and the associated timeline needed to restore an RHRSW header to service in order to provide decay heat removal for both units.

RAI 2

In Table 1 in the Enclosure to the LAR dated January 28, 2016 (pages 16 through 27 of 30), the licensee listed Unit 2 and common loads that are powered by Unit 1 Class 1E 480 V transformers and are affected by de-energization with the associated Limiting Conditions for Operation (LCO) and Technical Requirements for Operation (TRO) implications.

In Enclosure 1 to the licensees letter dated April 6, 2016, the licensee provided a listing of loads from the motor control centers (MCCs) powered by the Unit 1 Class 1E 480 V transformers that will be replaced as identified in the LAR.

From a correlation of the loads listed in Table 1 of the LAR letter dated January 28, 2016, with the loads identified Enclosure 1 of the letter dated April 6, 2016, the NRC staff notes that a small percentage of the loads listed in Enclosure 1 are subsequently identified in Table 1 of the LAR as affecting Unit 2 LCOs and TROs. Many of the affected loads listed in Enclosure 1 have identifiers that do not clearly distinguish between Unit 1, Unit 2 and common loads. Therefore, the NRC staff requests that the licensee:

a. Provide a listing of all Unit 2 or common loads powered from the Unit 1 480 V transformers (1X210, 1X220, 1X230, and 1X240) listed in Enclosure 1 and that are: (1) safety related or Class 1E, and (2) not already identified in Table 1.
b. For any loads identified above, determine if any LCOs or TCOs are associated with these loads and discuss additional actions (if applicable) necessary to justify the LAR.

RAI 3

In Table 1 in the Enclosure to the LAR dated January 28, 2016, the licensee has identified TRO 3.7.6 associated with the Engineered Safeguard Service Water (ESSW) Pumphouse Ventilation System. When either transformer 1X210 and 1X220 is being replaced, four ESSW fans are inoperable. The licensee stated in Table 1 that two ESW pumps and one RHRSW 2

pump would be declared inoperable after 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> in accordance with TRO 3.7.6. The NRC staff does not have TRO 3.7.6 to review and it is not clear why only one RHRSW pump would be inoperable. The staff requests that the licensee:

a. Explain why only one RHRSW pump becomes inoperable after 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />, with two RHRSW fans out of service when either 1X210 or 1X220 is being replaced.
b. Provide a copy of TRO 3.7.6, 3.8.6, 3.7.9, 3.3.4 and 3.11.2.6 (i.e., TROs referenced in Table 1).

RAI 4

On page 8 of the Enclosure to the LAR, the licensee provides the sequence/flow path for replacement of a 480 V Engineered Safeguard System (ESS) Load Center (LC) Transformer and information that applies throughout the evolution. The following questions relate to provisions that the license will make in order to limit the potential loss of power to Unit 2 equipment during the replacement of all Unit 1 480 V ESS LC Transformers that feed both units:

a. The licensee provided a list of surveillances that will be performed prior to the transformer replacement sequence. What test/surveillance will the licensee perform to verify that all structures, systems, and components are operable, prior to entering the transformer replacement sequence?
b. What compensatory measures will the licensee take in order to limit the potential loss of power to Unit 2 during the replacement of all Unit 1 480 V ESS LC Transformers (e.g.,

scheduling the evolution in order to avoid anticipated severe weather conditions, corridor the work zone as a Protected Area, restrictions on the maintenance of the switchyard, contacting the grid system load dispatcher to ensure no significant grid perturbations are expected)?

RAI 5

On page 3 of the Enclosure to the LAR, the licensee stated that the ESS LC supplies power to the individual 480 V loads and to MCCs that power instrument alternating current (AC) distribution panels, 125 and 250 V direct current (DC) battery chargers, and essential plant lighting. Discuss in detail the impact of the replacement of a Unit 1 480 V ESS LC Transformer on the Unit 2 instrument AC and DC power system loads. Explain how the Unit 2 DC power system continues to permit functioning of structures, systems, and components important to safety during the replacement of a Unit 1 480 V ESS LC Transformer.

RAI 6

In Enclosure 1 to the April 6, 2016, letter the licensee provided a table with the affected loads listed by transformer. For the Unit 2 Class 1E loads powered from Unit 1, identify the alternate source of power/alternate train that would be used during the Unit 1 transformer replacements.

3

RAI 7

The Enclosure to the LAR dated January 26, 2016 (pages 8 and 9 of 30) presents a list of bulleted items that will apply throughout the evolution and a flow path for replacement. Provide more complete justification including time estimates for why a full 7 day CT is needed.

4