April 27, 2016, Summary of Public Meeting on Susquehanna Steam Electric Station
ML16131A194
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 05/10/2016
From: Daniel Schroeder
Reactor Projects Region 1 Branch 4
To:
SCHROEDER, DL
Shared Package
ML16039A095 List:
References
Download: ML16131A194 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 May 10, 2016 MEETING

SUMMARY

LICENSEE:

SUSQUEHANNA NUCLEAR, LLC.

FACILITY:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2

SUBJECT:

SUMMARY

OF PUBLIC MEETING On April 27, 2016, at 4:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Susquehanna Energy Information Center in Berwick, PA. The NRC conducted the Annual Assessment Meeting to discuss its assessment of the safety performance at Susquehanna Steam Electric Station (SSES) Units 1 and 2 for 2015.

A notice of the open house was issued on March 21, 2016, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML16081A366.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards and handouts and met with members of the public to discuss its assessment of the safety performance of SSES Units 1 and 2 for the period of January 1 through December 31, 2015, as documented in our letter dated March 2, 2016 (ADAMS Accession No. ML16061A135). The NRC poster boards presented included background on the Reactor Oversight Process (ROP) and SSES performance highlights.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of SSES Units 1 and 2 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, the press, and Susquehanna Nuclear officials attended the open-house and were offered the opportunity to question the NRC regarding SSES Units 1 and 2s performance and the role of the agency in ensuring safe plant operations.

______/RA/______________

Daniel L. Schroeder, Chief Projects Branch 4 Division of Reactor Projects Enclosures Attendee List (ML16119A115)

ML16061A135). The NRC poster boards presented included background on the Reactor Oversight Process (ROP) and SSES performance highlights.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of SSES Units 1 and 2 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, State and local officials, and Susquehanna Nuclear officials attended the open-house and were offered the opportunity to question the NRC regarding SSES Units 1 and 2s performance and the role of the agency in ensuring safe plant operations.

Enclosures:

Attendee List (ML16119A115) /RA/

Daniel L. Schroeder, Chief Projects Branch 4 Division of Reactor Projects DISTRIBUTION w/encl: (via e-mail)

DLew, actg RA SFlanders, actg DRA MScott, DRP DPelton, DRP RLorson, DRS BSmith, DRS DSchroeder, DRP SBarber, DRP ATurilin, DRP PMeier, DRP JGreives, DRP, SRI TDaun, DRP, RI AGould, DRP, AA JBowen, RI, OEDO RidsNrrPMSusquehanna Res RidsNrrDorlLpl1-2 Res ROPreports Res DOC NAME: G:\\DRP\\BRANCH4\\Communications\\Public Meetings\\2016\\2016 SSES Annual Assessment Meeting Summary.docx ADAMS Accession No.: ML16131A194 SUNSI Review Non-Sensitive Sensitive

Publicly Available

Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SBarber / GSB DSchroeder/ DLS DATE 05/05 /16 05/ 06 /16

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 May 10, 2016 MEETING

SUMMARY

LICENSEE:

SUSQUEHANNA NUCLEAR, LLC.

FACILITY:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2

SUBJECT:

SUMMARY

OF PUBLIC MEETING On April 27, 2016, at 4:30 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted a public open house at the Susquehanna Energy Information Center in Berwick, PA. The NRC conducted the Annual Assessment Meeting to discuss its assessment of the safety performance at Susquehanna Steam Electric Station (SSES) Units 1 and 2 for 2015.

A notice of the open house was issued on March 21, 2016, and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML16081A366.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards and handouts and met with members of the public to discuss its assessment of the safety performance of SSES Units 1 and 2 for the period of January 1 through December 31, 2015, as documented in our letter dated March 2, 2016 (ADAMS Accession No. ML16061A135). The NRC poster boards presented included background on the Reactor Oversight Process (ROP) and SSES performance highlights.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of SSES Units 1 and 2 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, the press, and Susquehanna Nuclear officials attended the open-house and were offered the opportunity to question the NRC regarding SSES Units 1 and 2s performance and the role of the agency in ensuring safe plant operations.

______/RA/______________

Daniel L. Schroeder, Chief Projects Branch 4 Division of Reactor Projects Enclosures Attendee List (ML16119A115)

ML16061A135). The NRC poster boards presented included background on the Reactor Oversight Process (ROP) and SSES performance highlights.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of SSES Units 1 and 2 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, State and local officials, and Susquehanna Nuclear officials attended the open-house and were offered the opportunity to question the NRC regarding SSES Units 1 and 2s performance and the role of the agency in ensuring safe plant operations.

Enclosures:

Attendee List (ML16119A115) /RA/

Daniel L. Schroeder, Chief Projects Branch 4 Division of Reactor Projects DISTRIBUTION w/encl: (via e-mail)

DLew, actg RA SFlanders, actg DRA MScott, DRP DPelton, DRP RLorson, DRS BSmith, DRS DSchroeder, DRP SBarber, DRP ATurilin, DRP PMeier, DRP JGreives, DRP, SRI TDaun, DRP, RI AGould, DRP, AA JBowen, RI, OEDO RidsNrrPMSusquehanna Res RidsNrrDorlLpl1-2 Res ROPreports Res DOC NAME: G:\\DRP\\BRANCH4\\Communications\\Public Meetings\\2016\\2016 SSES Annual Assessment Meeting Summary.docx ADAMS Accession No.: ML16131A194 SUNSI Review Non-Sensitive Sensitive

Publicly Available

Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SBarber / GSB DSchroeder/ DLS DATE 05/05 /16 05/ 06 /16