Category:Letter
MONTHYEARPLA-8145, Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-81452024-10-21021 October 2024 Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-8145 ML24291A1562024-10-16016 October 2024 Missed Annual Inventory Required by 40 CFR 266, Subpart in PLE 0026645 PLA-8148, Registration for the Use of Spent Fuel Storage Casks 311, 308, and 3102024-10-15015 October 2024 Registration for the Use of Spent Fuel Storage Casks 311, 308, and 310 PLA-8141, Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-81412024-09-18018 September 2024 Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-8141 PLA-8142, Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-81422024-09-18018 September 2024 Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-8142 ML24260A2312024-09-17017 September 2024 Senior Reactor and Reactor Operator Initial License Examinations 05000387/LER-2024-002, B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor2024-09-16016 September 2024 B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24233A2192024-09-0303 September 2024 – Authorized Alternative to Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code IR 05000387/20240052024-08-29029 August 2024 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2024005 and 05000388/2024005) 05000387/LER-2023-004-01, Manual Reactor Scram Due to Degraded Main Condenser Vacuum2024-08-26026 August 2024 Manual Reactor Scram Due to Degraded Main Condenser Vacuum 05000387/LER-2024-001-01, Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear2024-08-21021 August 2024 Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear IR 05000387/20240022024-08-12012 August 2024 Integrated Inspection Report 05000387/2024002 and 05000388/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification PLA-8117, 23rd Refueling Outage Owners Activity Report (PLA-8117)2024-07-23023 July 2024 23rd Refueling Outage Owners Activity Report (PLA-8117) ML24197A0982024-07-15015 July 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000387/2024010 and 05000388/2024010 ML24127A2262024-05-29029 May 2024 Issuance of Amendment Nos. 288 and 272 Adoption of TSTF-563 PLA-8126, Response to Request for Confirmation of Information Regarding Relief Request 1RR062024-05-29029 May 2024 Response to Request for Confirmation of Information Regarding Relief Request 1RR06 PLA-8122, Annual Radiological Environmental Operating Report (PLA-8122)2024-05-28028 May 2024 Annual Radiological Environmental Operating Report (PLA-8122) PLA-8123, Main Steam Isolation Valve Leakage2024-05-23023 May 2024 Main Steam Isolation Valve Leakage PLA-8115, Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115)2024-05-23023 May 2024 Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115) IR 05000387/20240012024-05-13013 May 2024 Integrated Inspection Report 05000387/2024001 and 05000388/2024001 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 ML24082A1372024-04-22022 April 2024 Issuance of Amendment Nos. 287 and 271 Adoption of TSTF-568, Revision 2 and Associated Technical Specification Changes PLA-8094, Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-80942024-04-22022 April 2024 Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-8094 PLA-8095, 2023 Annual Radiological Environmental Operating Report (PLA-8095)2024-04-22022 April 2024 2023 Annual Radiological Environmental Operating Report (PLA-8095) PLA-8101, Re 2023 Annual Report of Radiation Exposure2024-04-22022 April 2024 Re 2023 Annual Report of Radiation Exposure PLA-8102, Annual Environmental Operating Report (Nonradiological) PLA-81022024-04-11011 April 2024 Annual Environmental Operating Report (Nonradiological) PLA-8102 PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8112, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-81122024-04-0909 April 2024 Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 PLA-8110, Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110)2024-04-0404 April 2024 Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110) PLA-8100, Property Insurance Program (PLA-8100)2024-04-0101 April 2024 Property Insurance Program (PLA-8100) ML24092A4022024-04-0101 April 2024 Annual Financial Report (PLA-8098) PLA-8109, Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109)2024-03-21021 March 2024 Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109) ML24067A2512024-03-19019 March 2024 Authorized Alternative to Requirements of the ASME Code PLA-8107, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance2024-03-19019 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance ML24044A2532024-03-14014 March 2024 Associated Independent Spent Fuel Storage Installation – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0077 (Security Notifications, Reports, and Recordkeeping & Suspicious Activity Reporting)) IR 05000387/20240112024-02-29029 February 2024 Commercial Grade Dedication Inspection Report 05000387/2024011 and 05000388/2024011 IR 05000387/20230062024-02-28028 February 2024 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2023006 and 05000388/2023006) ML24039A1882024-02-27027 February 2024 Issuance of Amendment Nos. 286 and 270 Changes to Technical Specifications for Control Rods ML24037A3072024-02-22022 February 2024 Summary of Regulatory Audit in Support of Relief Request 5RR-02 PLA-8099, Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099)2024-02-13013 February 2024 Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099) IR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8088, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088)2023-12-0505 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088) PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 2024-09-06
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000387/20233012023-09-20020 September 2023 Initial Operator Licensing Examination Report 05000387/2023301 and 05000388/2023301 IR 05000387/20213012021-09-17017 September 2021 Initial Operator Licensing Examination Report 05000387/2021301 and 05000388/2021301 IR 05000387/20193012019-10-28028 October 2019 Initial Operator Licensing Examination Report 05000387/2019301 and 05000388/2019301 IR 05000387/20173022017-06-0505 June 2017 NRC Retake Operator Licensing Examination Report 05000387/2017302; 05000388/2017302 IR 05000387/20163012017-01-17017 January 2017 NRC Initial Operator Licensing Examination Report 05000387/2016301 and 05000388/2016301 IR 05000387/20153022015-10-0707 October 2015 Examination Report 05000387/2015302 and 05000388/2015302; August 17-21, 2015 and August 27, 2015-Susquehanna Steam Electric Station, Units 1 and 2 IR 05000387/20143012014-10-23023 October 2014 Er 05000387/2014301; 05000388/2014301; August 11-21, 2014; Susquehanna Steam Electric Station, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000387/20123012012-03-0101 March 2012 Er 05000387-12-301, 05000388-12-301; January 17 - February 23, 2012; Susquehanna Steam Electric Station, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000387/20113012011-02-16016 February 2011 Er 05000387/2011301; 05000388/2011301; January 18 - February 9, 2011; Susquehanna Steam Electric Station, Units 1 and 2; Initial Operator Licensing Examination Report IR 05000387/20083012008-02-0808 February 2008 Er 05000387-08-301 and 05000388-08-301; on December 7-18, 2007; Susquehanna Steam Electric Station, Units 1 and 2; Initial Operator Licensing Examination IR 05000387/20023022002-12-24024 December 2002 IR 05000387-02-302, IR 05000388-02-302; December 11, 2002; Susquehanna Units 1 & 2; Initial Operator Licensing Retake Examination. One Applicant Passed the Examination (1 SRO Upgrade Passed) 2023-09-20
[Table view] |
Text
September 20, 2023
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - INITIAL OPERATOR LICENSING EXAMINATION REPORT 05000387/2023301 AND 05000388/2023301
Dear Brad Berryman:
On August 10, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an examination at the Susquehanna facility. The enclosed examination report documents the examination results, which were discussed on September 11, 2023, with Justin Crocker, Training Director, and other members of your staff.
The examination included the evaluation of eight applicants for reactor operator licenses, three applicants for instant senior reactor operator licenses, and three applicants for upgrade senior reactor operator licenses. The facility licensee developed the written and operating examinations using NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 12. The license examiners determined all applicants satisfied the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55, and the appropriate licenses were issued on September 11, 2023.
No findings were identified during this examination. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Digitally signed by Donald Donald E. E. Jackson Date: 2023.09.20 Jackson 11:18:53 -04'00'
Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety Docket Nos. 05000387 and 05000388 License Nos. NPF-14 and NPF-22 Enclosure:
Examination Report 05000387/2023301 and 05000388/2023301 w/ Attachment:
Supplementary Information cc w/encl: Distribution via ListServ
SUMMARY
ER 05000387/2023301 and 05000388/2023301; July 31, 2023 - August 10, 2023; Susquehanna
Steam Electric Station, Units 1 and 2; Initial Operator Licensing Examination Report.
Five NRC examiners evaluated the competency of eight applicants for reactor operator licenses, three applicants for instant senior reactor operator licenses, and three applicants for upgrade senior reactor operator licenses. The facility licensee developed the examinations using NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 12. The written examination was administered by the facility on August 10, 2023. NRC examiners administered the operating tests July 31, 2023 - August 4, 2023. The NRC examiners determined that all applicants satisfied the requirements of 10 CFR Part 55, and the appropriate licenses have been issued.
NRC-Identified and Self-Revealing Findings
No findings were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Initial Operator License Examination)
.1 License Applications
a. Scope
The examiners reviewed all license applications submitted by the licensee to ensure the applications reflected that each applicant satisfied relevant license eligibility requirements.
The applications were submitted on NRC Form 398, Personal Qualification Statement, and NRC Form 396, Certification of Medical Examination by Facility Licensee. The examiner also audited three of the license applications in detail to confirm that they accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings were identified.
.2 Operator Knowledge and Performance
a. Examination Scope
On August 10, 2023, the licensee proctored the administration of the written examinations to all applicants. The licensee staff graded the written examinations, analyzed the results, and presented their analysis to the NRC on September 1, 2023.
The NRC examination team administered various portions of the operating examination July 31, 2023 - August 4, 2023. The applicants for reactor operator licenses participated in at least two dynamic simulator scenarios, in a control room and facilities walkthrough test consisting of eleven system tasks, and an administrative test consisting of four administrative tasks. The applicants for instant senior reactor operator licenses participated in at least two dynamic simulator scenarios, a control room and facilities walkthrough test consisting of ten system tasks, and an administrative test consisting of five administrative tasks. The applicants for upgrade senior reactor operator licenses participated in at least one dynamic simulator scenario, a control room and facilities walkthrough test consisting of five system tasks, and an administrative test consisting of five administrative tasks.
b. Findings
All applicants passed the operating test and the written examination. For the written examinations, the reactor operator applicants average score was 90.8 percent and ranged from 82.6 to 93.3 percent. The senior operator applicants average score was 92.6 percent and ranged from 87.0 to 95.0 percent. The text of the examination questions may be accessed in the ADAMS system under the accession numbers noted in the Attachment. In accordance with current NRC policy, the release of the written examination in ADAMS to the public will be delayed for two years.
Chapter ES-403 and Form ES-403-1 of NUREG 1021 require the licensee to analyze the validity of any written examination questions that were missed by half or more of the applicants. The licensee conducted this performance analysis and submitted the analysis to the chief examiner.
.3 Initial Licensing Examination Development
a. Examination Scope
The facility licensee developed the examinations in accordance with NUREG-1021, Revision 12. All licensee facility training and operations staff involved in examination preparation and validation were listed on a security agreement. The NRC conducted an onsite validation of the operating examinations during the week of June 26, 2023.
b. Findings
No findings were identified. The examiners determined that the written and operating examinations initially submitted by the licensee were within the range of acceptability expected for a proposed examination.
.4 Simulation Facility Performance
a. Examination Scope
The examiners observed simulator performance with regard to plant fidelity during the examination validation and administration.
b. Findings
No findings were identified.
.5 Examination Security
a. Examination Scope
The examiners reviewed examination security for examination development during both the onsite preparation week and examination administration week for compliance with NUREG-1021, Revision 12 requirements. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings were identified.
4OA6 Meetings, Including Exit
The chief examiner presented the examination results to Justin Crocker, Training Director, and other members of the licensee's staff on September 11, 2023. The licensee did not identify any information or materials used during the examination as proprietary.
ATTACHMENT:
SUPPLEMENTARY INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- K. Kline, Exam Support
- C. Michaels, Exam Support
ITEMS OPENED, CLOSED, AND DISCUSSED
NONE
ADAMS DOCUMENTS REFERENCED