{{#Wiki_filter:March 12, 2012 Rafael Flores, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company, LLC Comanche Peak Nuclear Power Plant P.O. Box 1002 Glen Rose, TX  76043
==SUBJECT:==
==SUMMARY==
OF MEETING WITH LUMINANT GENERATION COMPANY, LLC REGARDING PLANNED MODIFICATIONS TO RESOLVE FIRE PROTECTION CIRCUIT INTERACTIONS 
==Dear Mr. Flores:==
This public meeting was conducted in Arlington, Texas on March 6, 2012, between the  U.S. Nuclear Regulatory Commission and your staff. The participants discussed the scope and timeline for implementing modifications planned to resolve circuit faults related to multiple spurious operations.
This meeting was classified as a Category 1 public meeting, as communicated in the meeting notice (ML12048A861). It provided an opportunity for members of the public to discuss regulatory issues with the Nuclear Regulatory Commission after the business portion of the meeting, but before the meeting adjourned. No comments were brought forward by the public. 
The attendance list for the meeting is included as Enclosure 1. A copy of the Luminant Generation Company, LLC planned modification schedule is provided in Enclosure 2.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosures, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV1600 EAST LAMAR BLVDARLINGTON, TEXAS 76011-4511
Should you have any questions concerning this matter, please contact me at 817 200-1137.
Sincerely,  /RA/        Geoffrey Miller, Chief  Engineering Branch 2 Division of Reactor Safety Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89
==Enclosures:==
: 1. Attendance List 2. Luminant Generation Company, LLC Presentation Slides cc w/
==Enclosure:==
Electronic Distribution - Comanche Peak Nuclear Power Plant
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov)  Deputy Regional Administrator (Art.Howell@nrc.gov)  DRP Director (Kriss.Kennedy@nrc.gov)  DRP Deputy Director (Troy.Pruett@nrc.gov)  DRS Director (Anton.Vegel@nrc.gov)  DRS Deputy Director (Tom.Blount@nrc.gov)  Senior Resident Inspector (John.Kramer@nrc.gov)  Resident Inspector (Brian.Tindell@nrc.gov)  Branch Chief, DRP/A (Wayne.Walker@nrc.gov)  Senior Project Engineer, DRP/A (David.Proulx@nrc.gov)  Project Engineer, DRP/A (Jason.Dykert@nrc.gov)  Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov)  Project Manager (Balwant.Singal@nrc.gov)  Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov)  RITS Coordinator (Marisa.Herrera@nrc.gov)  Regional Counsel (Karla.Fuller@nrc.gov)  Congressional Affairs Officer (Jenny.Weil@nrc.gov)  OEMail Resource  RIV/ETA: OEDO (Lydia.Chang@nrc.gov)     
R:\_REACTORS\CP\CP MS MSO MODs 3-6-201-GAP.docx      ADAMS ML12072A343 ADAMS:    No      Yes  SUNSI Review Complete Reviewer Initials:  GAP Publicly Available  Non-Sensitive Non-publicly Available  Sensitive DRS\EB2\SRI DRP\PBA\BC DRS\EB2\BC GPick WWalker GMiller  /RA/ /RA/ /RA/
03/07/2012 03/07/2012 03/12/2012  OFFICIAL RECORD COPY                                        T=Telephone          E=E-mail        F=Fax Enclosure 1 Enclosure 2}}

Revision as of 02:28, 30 July 2018

3/6/2012 Summary of Meeting with Luminant Generation Company, LLC Regarding Planned Modifications to Resolve Fire Protection Circuit Interactions
ML12072A343
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/12/2012
From: Miller G B
NRC/RGN-IV/DRS/EB-2
To: Flores R
Luminant Generation Co
Pick G A
References
Download: ML12072A343 (5)


Text

March 12, 2012 Rafael Flores, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company, LLC Comanche Peak Nuclear Power Plant P.O. Box 1002 Glen Rose, TX 76043

SUBJECT:

SUMMARY

OF MEETING WITH LUMINANT GENERATION COMPANY, LLC REGARDING PLANNED MODIFICATIONS TO RESOLVE FIRE PROTECTION CIRCUIT INTERACTIONS

Dear Mr. Flores:

This public meeting was conducted in Arlington, Texas on March 6, 2012, between the U.S. Nuclear Regulatory Commission and your staff. The participants discussed the scope and timeline for implementing modifications planned to resolve circuit faults related to multiple spurious operations.

This meeting was classified as a Category 1 public meeting, as communicated in the meeting notice (ML12048A861). It provided an opportunity for members of the public to discuss regulatory issues with the Nuclear Regulatory Commission after the business portion of the meeting, but before the meeting adjourned. No comments were brought forward by the public.

The attendance list for the meeting is included as Enclosure 1. A copy of the Luminant Generation Company, LLC planned modification schedule is provided in Enclosure 2.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, and its enclosures, will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV1600 EAST LAMAR BLVDARLINGTON, TEXAS 76011-4511

Should you have any questions concerning this matter, please contact me at 817 200-1137.

Sincerely, /RA/ Geoffrey Miller, Chief Engineering Branch 2 Division of Reactor Safety Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89

Enclosures:

1. Attendance List 2. Luminant Generation Company, LLC Presentation Slides cc w/

Enclosure:

Electronic Distribution - Comanche Peak Nuclear Power Plant

Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) DRP Director (Kriss.Kennedy@nrc.gov) DRP Deputy Director (Troy.Pruett@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) DRS Deputy Director (Tom.Blount@nrc.gov) Senior Resident Inspector (John.Kramer@nrc.gov) Resident Inspector (Brian.Tindell@nrc.gov) Branch Chief, DRP/A (Wayne.Walker@nrc.gov) Senior Project Engineer, DRP/A (David.Proulx@nrc.gov) Project Engineer, DRP/A (Jason.Dykert@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Project Manager (Balwant.Singal@nrc.gov) Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) OEMail Resource RIV/ETA: OEDO (Lydia.Chang@nrc.gov)

R:\_REACTORS\CP\CP MS MSO MODs 3-6-201-GAP.docx ADAMS ML12072A343 ADAMS: No Yes SUNSI Review Complete Reviewer Initials: GAP Publicly Available Non-Sensitive Non-publicly Available Sensitive DRS\EB2\SRI DRP\PBA\BC DRS\EB2\BC GPick WWalker GMiller /RA/ /RA/ /RA/

03/07/2012 03/07/2012 03/12/2012 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax Enclosure 1 Enclosure 2