Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica
ML23291A438
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/30/2023
From: Stephen Koenick
NRC/NMSS/DREFS/ELRB
To: Peters K
Vistra Operations Company
References
EPID L-2022-LNE-0004
Download: ML23291A438 (3)


Text

November 30, 2023 Ken J. Peters, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Comanche Peak Nuclear Power Plant Vistra Operations Company LLC 6322 N FM 56 P.O. Box 1002 Glen Rose, TX 76043

SUBJECT:

NOTICE OF AVAILABILITY OF THE DRAFT PLANT-SPECIFIC SUPPLEMENT 60, TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS REGARDING COMANCHE PEAK NUCLEAR POWER PLANT, UNIT NUMBERS 1 AND 2, LICENSE RENEWAL APPLICATION (EPID NUMBER: L-2022-LNE-0004)

Dear Ken J. Peters:

The U.S. Nuclear Regulatory Commission (NRC) staff has completed the draft plant-specific Supplement 60, to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GElS), regarding the renewal of Facility Operating License Nos.

NPF-87 and NPF-89 for an additional 20 years of operation for Comanche Peak Nuclear Power Plant, Units 1 and 2, respectively (CPNPP). The NRC staff has prepared a Federal Register (FR) Notice of Availability (NOA) (88 FR 75629 and 88 FR 78068) to advise the public that the draft supplement is publicly available at the following link:

http://www.nrc.gov/readingrm/adams.html.

The ADAMS number for draft Supplement 60, to the GElS is (ML23299A252). In addition, the draft Supplement 60 will be available to the public near the site at the following location:

Somervell County Library, 108 Allen Dr., Glen Rose, TX 76043 and Hood County Library, 222 N Travis St. Granbury, TX 76048.

As discussed in chapter 4 of the draft supplement, the NRC staffs preliminary recommendation is that the adverse environmental impacts of subsequent license renewal for CPNPP are not so great that preserving the option of license renewal for energy-planning decisionmakers would be unreasonable. This recommendation is based on: (1) the analysis and findings in the GElS; (2) the applicants Environmental Report; (3) the NRC staffs consultation with Federal, State, Local, and Tribal government agencies; (4) the NRC staff's independent environmental review; and (5) the NRC staff's consideration of public comments.

K. Peters A separate NOA of the draft supplemental environmental impact statement was placed in the FR through the U.S. Environmental Protection Agency (EPA) (88 FR 77308). The comment period ends 45 days from EPA FR date, which is December 26, 2023.

If you have any questions concerning the staffs environmental review of this license renewal application, please contact the Project Manager, Tam Tran, by telephone at 301-415-3617 or via email at Tam.Tran@nrc.gov.

Sincerely, Signed by Koenick, Stephen on 11/30/23 Stephen S. Koenick, Chief Environmental Project Management Branch 1 Division of Rulemaking, Environmental and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. 50-445 and 50-446 cc: Listserv

ML23291A438 concurrence via e-mail OFFICE PM:REFS LA:REFS PM:REFS NAME TTran AWalker-Smith TTran DATE 10/23/2023 10/31/2023 11/27/2023 OFFICE BC:REFS NAME SKoenick DATE 11/30 /2023