Schedule Revision for the License Renewal Application Review
ML23325A018
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/30/2023
From: Beverly Smith
NRC/NRR/DNRL/NLRP
To: Peters K
Vistra Operating Co. (VistraOpCo)
References
EPID L 2022-RNW-0018
Download: ML23325A018 (4)


Text

.

November 30, 2023 Ken J. Peters Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Comanche Peak Nuclear Power Plant Vistra Operations Company LLC 6322 N FM 56 P.O. Box 1002 Glen Rose, TX 76043

SUBJECT:

REVISION OF SCHEDULE FOR THE SAFETY REVIEW OF THE COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (EPID NO. L 2022-RNW-0018) (DOCKET NUMBERS: 50-445 AND 50-446)

Dear Ken J. Peters:

By letter dated October 3, 2022 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML22276A082), Vistra Operations Company LLC (Vistra or the applicant) submitted an application for license renewal of Facility Operating License Nos.

NPF-87 and NPF-89 for Comanche Peak Nuclear Power Plant (CPNPP), Units 1 and 2, to the U.S. Nuclear Regulatory Commission (NRC or staff), pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants.

By letter dated November 23, 2022 (ML22297A007), the staff concluded that the application was acceptable for docketing and included the staffs projected review schedule for the CPNPP license renewal application. By letter dated September 21, 2023 (ML23263A024), the staff issued a revised schedule to the environmental review of the CPNPP license renewal application.

The purpose of this letter is to inform you of changes in the safety review schedule for the CPNPP license renewal application, affecting the milestones for the Issue Safety Evaluation Report (SER), ACRS [Advisory Committee on Reactor Safeguards] Subcommittee Meeting, and ACRS Full Committee Meeting. Specifically, the Issue Safety Evaluation Report milestone will be revised from December 2023 to February 2024 to address an operating experience-related issue that was identified during the Inspection Procedure 71002, License Renewal Inspection, inspection, conducted September 11-15 and 25-19, 2023. The issue involved leakage in the spent fuel pool liner; therefore, its potential impact to the Structures Monitoring aging management program will need to be evaluated. Due to the timing of when this matter was identified, the milestone date to issue the staffs Safety Evaluation Report will be impacted. The revised date factors in the time that the applicant will need to review the

operating experience and its impact to its aging management activities, and the time that the staff will need to review any proposed changes.

For initial license renewal application reviews, both an ACRS Subcommittee and the Full Committee meetings are typically conducted in sequence. Based on discussions with the staff, the ACRS Committee has determined that, if a Safety Evaluation Report can be issued without open items, unresolved items, and confirmatory items, then only the Full Committee meeting would need to be conducted. Based on this determination, the ACRS Subcommittee Meeting milestone will be removed, and the ACRS Full Committee Meeting milestone will be revised from June 2024 to April 2024. If the staff decides to issue a Safety Evaluation Report with open items as a result of the staffs review of the operating experience-related issue noted above, then the license renewal review schedule will be revised to re-include the ACRS Subcommittee meeting.

The current milestone date to issue the renewed licenses for CPNPP Units 1 and 2 (September 2024) is not expected to be impacted by the changes described above.

The enclosure of this letter provides the staffs revised projected schedule for the CPNPP license renewal application review. The staff will strive to meet the milestones ahead of the revised schedule whenever feasible.

If you have any questions related to this review schedule, please contact Mark Yoo at Mark.Yoo@nrc.gov.

Sincerely,

/RA/

Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446

Enclosure:

License Renewal Application Review Schedule cc w/encl: Listserv

ML23325A018 OFFICE NRR/DNRL/NLRP/PM NRR/DNRL/NLIB/LA NRR/DNRL/NLRP/BC NAME MYoo SGreen LGibson DATE 11/21/2023 11/22/2023 11/27/2023 OFFICE NRR/DNRL NAME BSmith DATE 11/30/2023 COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVIEW SCHEDULE License Renewal Application Review Schedule from NRC Letter dated September 21, 2023 Milestone Scheduled Receive License Renewal Application (LRA) 10/2022 Publish Federal Register Notice (FRN) - LRA Availability 10/2022 Publish FRN - Docketing Acceptance/Rejection and Opportunity for 11/2022 Hearing Publish FRN - Notice of Intent to Prepare an Environmental 11/2022 Impact Statement and Conduct Scoping Public Meeting - Overview of License Renewal Process and 01/2023 Environmental Scoping Environmental Scoping Period Ends 01/2023 Deadline for Filing Hearing Requests and Petitions for Intervention 01/2023 Issue Draft Supplemental Environmental Impact Statement (SEIS) 10/2023 Public Meeting - Draft SEIS Meeting, If Needed 11/2023 End of DSEIS Comment Period 12/2023 Issue Safety Evaluation Report (SER) 12/2023 02/2024 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee 02/2024 Meeting Issue Final SEIS 04/2024 ACRS Full Committee Meeting 06/2024 04/2024 U.S. Environmental Protection Agency FRN Published 05/2024

- Availability of Final SEIS Decision - Director, Office of Nuclear Reactor Regulation 09/2024 Enclosure