| | Issue date | Site | Title | Topic |
|---|
| IR 05000445/2025004 | 9 February 2026 | Comanche Peak | Integrated Inspection Report 05000445/2025004 and 05000446/2025004 | Fitness for Duty Temporary Modification Cyber Security Functionality Assessment FLEX Significance Determination Process Large early release frequency Operability Determination Fire Protection Program |
| ML26034C134 | 5 February 2026 | Beaver Valley Davis Besse Perry Comanche Peak | Vistra Fleet - Regulatory Audit Report Regarding License Amendment Request Related to Online Monitoring Program | Government shutdown |
| CP-202500152, Implementation of a Vistra Common Quality Assurance Program Manual | 4 February 2026 | Beaver Valley Davis Besse Perry Comanche Peak 07201043 07200069 | Implementation of a Vistra Common Quality Assurance Program Manual | |
| IR 05000445/2025420 | 30 January 2026 | Comanche Peak 05000420 | Security Baseline Inspection Cover Letter 05000445/2025420, 05000446/2025420 | Affidavit |
| CP-202600008, (Cpnpp), NRC Form 536, Operator Licensing Examination Data | 15 January 2026 | Comanche Peak | (Cpnpp), NRC Form 536, Operator Licensing Examination Data | |
| ML26015A089 | 15 January 2026 | Comanche Peak | Inservice Inspection Request for Information | Boric Acid Nondestructive Examination Scaffolding |
| ML26012A070 | 14 January 2026 | Palo Verde Wolf Creek Grand Gulf Cooper Arkansas Nuclear Columbia River Bend Diablo Canyon Callaway Waterford South Texas Comanche Peak | Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV | |
| IR 05000445/2025010 | 30 December 2025 | Comanche Peak | Biennial Problem Identification and Resolution Inspection Report 05000445/2025010 and 05000446/2025010 | Functionality Assessment Condition Adverse to Quality Significance Determination Process Operability Determination Maintenance Rule Program |
| 05000445/LER-2025-002, Pressure Transmitter Inoperable for a Duration Prohibited by TS | 29 December 2025 | Comanche Peak | Pressure Transmitter Inoperable for a Duration Prohibited by TS | Time of Discovery Anticipated operational occurrence Past operability |
| IR 05000445/2025003 | 22 December 2025 | Comanche Peak | Integrated Inspection Report 05000445/2025003 and 05000446/2025003 | Safe Shutdown Boric Acid Time of Discovery Enforcement Discretion Functionality Assessment Operability Determination Very Low Safety Significance Issue Resolution Fire Protection Program Siren Thermography |