ML20206U579

From kanterella
Jump to navigation Jump to search
Summary of 841107 Feedback Interview W/Allegers A-44 & A-73 at Fort Worth,Tx,To Discuss Technical Review Team Evaluation & Conclusions Re Mechanical/Piping,Qa/Qc,Civil/Structural & Miscellaneous Allegations.Related Documentation Encl
ML20206U579
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/17/1985
From: Poslusny C
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
To: Noonan V
NRC - COMANCHE PEAK PROJECT (TECHNICAL REVIEW TEAM)
Shared Package
ML19284C882 List: ... further results
References
FOIA-85-59 NUDOCS 8607110033
Download: ML20206U579 (19)


Text

-

(, ,[na aeg'o,, UNITED STATES

. 8 o NUCLEAR REGULATORY COMMISSION

,y " ,I WASHINGTON, D. C. 20555 5

(

~%...../ .

MEMORANDUM FOR: Vincent S. Noonan, Director M If W$

Comanche Peak Project FROM: Chet Poslusny, Program Coordinator Comanche Peak Project

SUBJECT:

FEEDBACK INTERVIEW OF WITNESS A-44 On November 7, 1984, the TRT conducted a feedback interview with allegers A-44 and A-73 at a meeting at Fort Worth, Texas. The purpose of this meeting was to discuss the TRT evaluation and conclusions concerning these allegations which are in the mechanical / piping, quality assurance / quality control, civil / structural, and miscellaneous areas.

The TRT Attendees were as follows: J. Zudans, V. Noonan, A. Vietti, R. Philleo, L. Shao, J. Calvo, R. Keimig, W. Smith, D. Hunnicutt, and R. Bangart.

The, following is a summary of each addressed allegation and alleger's comments on each.

1. AC-52--It was alleged that several field-cured and standard-cured cylinders failed specification requirements and that Schmidt Rebound Hammer Test was then misapplied to resolve these failures. The TRT found that some procedures were violated and subsequently the Schmidt Hansner Test was correctly applied. The " low strength" cylinders were, in all cases, taken from pours where 2500 psi strength concrete was specified.
2. AC-66-- It was alleged that there were cracks in the concrete base mat on Unit One. The TRT determined the cracks had no structural significance.

The original alleger had been contacted, and he was satisfied with the TRT's findings. A-44 was concerned that the crack location and size had never been documented and the documentation may have been falsified. The pour cards and compressive strength tests were missing.

i A-44 stated she had heard Unit 2 used a revised procedure because of Unit .

1 problems; it was poured on a weekend to avoid problems with the inspectors. Philleo stated cracks are anticipated in that location, and the steel is designed to carry the load. The pour was made on a weekend, with a large complement of inspectors and crafts people. Also, the '

contractor had the option of making one or two pours and chose to make i only one.

l 3. AE-17--It was alleged that field run conduit, drywall, and lighting i

installed above the control room were classified nonseismic and l

inadequately supported. The TRT found Seismic Category Two equipment l (nonsafety conduits and lighting fixtures) requires analysis to show l failure would not affect the component. Construction is replacin L

l 8607110033 G60624 E 0 % Mth NDE 9 PDR s

l l

s 2

. ceiling. A-44 stated the construction was started without reviewing the -

results of the reanalysis or getting NRC's approval, which puts on added burden on the NRC.

4. AM-22--It was alleged that TUEC has not analyzed the HVAC supports for seismic loads. HVAC failure might lead to unacceptably high temperatures inside the containment. The TRT found all HVAC supports had been analyzed for seismic loading. Also, the containment heat removal system was designed so no single failure of an active component could prevent the system from accomplishing its design safety function. A-44 asked if the ducts up the side of the' containment were seismically supported. The TRT will investigate.
5. AE-13--It was alleged that tenninal lugs of improper size had been used in certain panels and improper cable splices existed in various panels. The TRT found the panel referred to was not a safety related system, and the tenninal lugs and cable splices were acceptable for that system.
6. AT-1--It was alleged that the Hot Functional Test was deficient in that

+

major components and equipment were not installed at the time of testing.

i The TRT found missing components and equipment were identified and reported as deficiencies in the test, and future tests were planned which -

would check out that equipment.

7. AT-2--It was alleged that significant equipment modifications have been made or planned which invalidate the Hot Functional Test. The TRT found i that outstanding testing which remained because components were not 1

installed at the time of the test was tracked by the applicant's tracking system and future tests were planned to test these components.

8. AT-3--It was alleged that TUEC does not intend to confinn performance of major components and equipment until after fuel loading. The TRT found TUEC had planned preoperational testing after fuel loading to pick up items omitted from the Hot Functional Tests. Those items which were deferred could not cause a radioactive release if done after fuel loading.

However, since fuel loading was deferred, additional Hot Functional '

Testing will be performed in the interim.

9. AT-4--It was alleged that neither Region IV nor TUEC noticed major j components and equipment were not installed prior to the Hot Functional j Test. The TRT found TUEC had an adequate tracking system which covered l

these items, and Region IV was monitoring that tracking system.

l 10. AT-5--It was alleged that the Hot Functional test was flawed because it

! IHTnot include accident conditions. The TRT found the safety systems l were indeed tested as far as possible, but NRC does not require tests under actual accident conditions.

L

1 e 3

11. AT-6--It was alleged that both the Applicant and Region IV were willing t'a accept Hot Functional Tests which were deficient and could not be relied
on to prove that CPSES is safe. The TRT found no deficient test results were accepted by the Applicant. Three minor cases were found where test

~

objectives were not completely met. These will be retested;

12. AT-7--It was alleged that problems revealed by the Hot Functional Test and related containment leak rate tests are so extensive and.such magnitude - '

that they must be corrected before fuel load. The TRT. found four leak.

rate tests were done before an acceptable test was accomplished.

13. AT-10--It was alleged that the ASLB should closely monitor successful i

completion of tests and reinspections. The TRT found nothing to report to the ASLB as far as testing deficiencies, component and equipment ~

l deficiencies, and safety issues are concerned.

14. AT-11--It was alleged that the ASL8 should recognize test result evaluations by the TUEC and are NRC are incompleted and inaccurate. The TRT found no lack of candor on the part of TUEC or NRC. A-44 asked where the NRC was when tests and retests are being done. Region IV covers all ,

4 testing on a random basis 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day. They have no needed to call in i

extra help.

l .

j 15. AT-12--It was alleged that separate tests should be required for Unit 2., y ,

rather than relying on tests performed on Unit I to reveal problems. The o:

TRT found that only systems which are shared by Units 1 and 2 and that  %

were fully tested during the Unit I test program are not scheduled for D retesting during Unit 2's preoperational test program. All other Unit 2 systems will be tested separately, n

16. AT-17--It was alleged that there were numerous problems with the Thermal .

Expansion Test. The TRT found approximately 50% of the monitored ,

locations still require measurements. Also, it was alleged traceability of measurement systems was not maintained, The TRT found this was correct, but traceability was possible through a test engineer's log.

Further testing is planned and a better correlation between predicted pipe

movement and measured pipe movement is anticipated. A-73 stated that.the utility is relying too heavily on the as-built system, as opposed to .

relying on CMC's (component modification cards), and that the unexpected pipe movements were caused by binding snubbers and piping which was prestressed by using hydraulic jacks, cranes, etc. to forge fitup.

i 17. AE-55--It was alleged that four safety related class IE meters were I removed from the main control panel, sent off site for modification, and l

reinstalled without procedure. The TRT will review this allegation.

l l 18. AE-56--It was alleged that a wire of a smaller size than specified was l used in one case. A-44 will furnish more detail to J. Calvo.

l

. , . . . . . , - . . . , , . . , ---..-.- _-.. - ~__. . - - - , , , ._ _ , - . -

. - _ - -. ~ . _. --- - __ - _ - .

1 .

4 4

19. AC-67--It was alleged that the concrete was not retested on the concrete pour for the Reactor No. 2 cavity wall. Mr. Philleo stated this may be a QA/QC matter, but the actual strength is more'than adequate for the applications.

, 20. AC-72--There was concern that where the 2500 psi concrete'm'ixes were used instead of the 4000 psi mixes, the analysis used the 2500 psi

characteristics. Most, if not all, of the 2500 psi concrete was used in nonstructural locations. However, the TRT will investigate this concern -

i further. ~

21. AC-71--There was concern that the TRT may not be able to determine where tTe 2500 psi concrete was used. The TRT will investigate.
22. AC-68--There was concern that Schmidt Hansner Tests were misinterpreted in N
determining the concrete strength. A-73 and Philleo agree on how the test '

j can be used. Philleo had not seen any applications where the test was -

misinterpreted. .

23. AE-17--It was alleged that field run conduit, drywall, and lighting installed above the control room panels were classified as nonseismic and were inadequately supported. The TRT agreed the allegation is valid. The additional calculations required to show the supports are seismically

(

a sound have been done, but the TRT is still studying the problem. y og

24. AC-69--There was concern that in analyzing field run conduit, the e, consequences of a Category 2 failure on adjacent Category 1 equipment may y
not have been considered. The TRT will study this further. N
25. AC-70--Alleger A-73 was concerned that the designer had not used the 1.5 y i factor when performing equivalent static load calculations. The TRT will 3 investigate. .

l

26. AC-79--There was concern that in calculating allowable stresses for the -

containment building cable tray supports; the Applicant used allowable stresses for the auxiliary building,' which are above the yield strength of #

! the steel used in the building. The containment building allowables are fa not permitted to exceed the yield strength of the steel used in the -

building. The TRT will investigate.

I

27. AC-78--There was concern that in connecting the cable tray to the cable l tray supports, holes were drilled .through the flanges of the channels,
which weakens the supports. This'may not have been considered in analyzing the support. The TRT will investigate.
28. AC-80--There was concern that an incorrect dye penetrant test was made on '

a stainless steel liner in the reactor building and fuel building. Also, MPSI had attached a horizontal plate to the liner to attach a support;

A-73 calculated it was overstressed. The TRT will investigate to assure

! design calculations on the support system were properly performed.

!l

t

l. -

t i

. 5 ,

29. AC-82--There was concern that the location of liner plate weld seams do -

, not match the drawing locations around the Unit I reactor building. The 1 TRT will investigate.

Noonan stated were not able to attend this meeting, but l Noonan would relay A-73's commen s to them.

30. AC-75--There was concern that no gap was provided at the doorway between the containment and the safeguards building. This would affect the -

l seismic analysis. The TRT was aware of this and will investigate.

31. AP-42--A-73 alleges that an NCR had been revised four times, that the violations had been removed improperly, and that 10CFR50.55(e) had been violated. The TRT will investigate.
32. AC-64--There was concern that a tie-in may exist between the basemat crack and other deficiencies. A-44 requested a study be made as to whether the basemat crack runs under the reactor. Philleo said it undoubtedly did, but was of no consequence structurally.
33. AC-65--There was concern that cracking of the floor slab concrete was not investigated thoroughly enough. Some cases of honeycomb and internal voids may exist. A-44 was concerned with the amount and variety of defects in the concrete. The TRT will investigate the repair of honeycombs and voids.
34. AC-63--There was concern that, in some cases, honeycomb and internal voids in the concrete may exist. A-44 was concerned with the amount and variety l of defects in the concrete. The TRT will investigate the repair of honeycombs and voids. ' }
35. AP-29 and AP-44--It was alleged that minimum wall thickness violations ,

occurred. A-44 requested an update on the status of various concerns 1 about violations of minimum thickness. '

36. AP-43--It was alleged that supports upgraded from Class 2 to Class 1 do'~

not meet all the requirements of Class 1. A-44 is concerned whether the

! calculations were also upgraded where the supports were upgraded from ,

Class 2 to Class 1.

  • j
37. AP-41--It was alleged that frame jacks were used toimaintain gap size in some hangers. A-44 states use 'of power tools to force pipe into place should be prohibited.

I i

4 -

--.---a. , , , . . . . .

P-1 6

Conclusion:

A-44 stated that the feedback meeting is an effective way to -

comunicate the results of the TRT's investigation of issues to the allegers.

V. Noonan stated that a similar meeting is planned on QA/QC a'llegations.

~

b  :. _

C. Poslusny', P1 gram Coordinator-p Comanche = Peak roject' cc: D. Eisenhut B. Hayes J. Youngbload '

L. Shao J. Calvo y

h Docket Files 50-445/446

'g

. e'

?YA

"?. '&l

.w:

fg !y 1 11 r

..y

,'r+_

e 4 E

'I

  • . w.we

R 17 3g5 i 7

Conclusion:

A-44 stated that the feedback meeting is an effective way to ' -

communicate the results of the TRT's investigation of issues to the allegers.

V. Noonan stated that a similar meeting is planned on QA/QC allegations.

M C. Poslusny, Program Coordinator Comanche Peak Project cc: D. Eisenhut B. Hayes J. Youngblood L. Shao '

J. Calvo M. Kline -

~'

Docket Files 50-445/446 -

1' K .

2, ..

2 Z-iFC :CPP.. :CPP  :  :  :  :  :

.____:_'___h ______:____________:____________:________....:.___________:____________:___________

IAME :CPbslusny :VSNoonan  :  :  :  :  :

IATE f / /85  : / /85  :  :  :  :  : '

7-/7-85~ntac 0FFICIAL RECORD COPY  :<

.-m -. - -w -

1 l

.m , , m ,_ .

. [ .,C,

~

] ..m$ l l l- l l l [ l g g g Jg j p g J ,J q l p gi lEr.

.1 1 I

III i

I i / l GM %77I fl l s si l -V.

. , n 'a_: _

x l i !!

t I lN '

l l 1 (, -P ) $

~

I!l X l  ! l l l , Wl l l l 1h7 t ,- .. -r

( , t.. I i i ,

i f -- ,. , , .-- j~.+c._, m ., e. c -. u c , i i k! t lx ! i

, ,, g.c. n g ., s ,. , . . . -

-, -- cm ,fu f , j , l i i g ;,

'.I 2i A"vA"rl /2" St rectcal Ttbire (A-500 GR B) 3 *-6" 1 2 W I<<Vihei im Ix i i i r e-,o www c. I i l I I I i l 3I ?-%x13 (SA-39 2 *-0 1/8" lont W=52a i 2 i zu m ',i/shS Ix, Ix ! !

. p i i - ,  ; - ~ . _. .- u : 7 < v. _: . r-,.m, .s - . _._o ,, i 3 __ i q< i j i.,e [ i f M 3't I d.MC e74 o/ I  ! I I i i i i I l t M i Wt __

tv\4r-=p IQi B9 F tG LD I I I I I I.l i i i i i i t t la t i i i SEI5?EC ASS:'BLY SETCH AND ENGLt._:dEG l 1 1 l i I l -1 i

! BUNI'iE AND TAG Pnm i 1 l- 1 I II I I I4P X d SM-1-010-C04-A33R Fl3 V h l?fe A s .

u I I i ! I

_ . , _ . _ _ . - i ' i en f i,t e ! : r. I i l i ; j L .nl- Ar.:ly cne coa ; or Carco Zine Ell to o i - - 4 ,'.%'fj n i I l'.

,% ' l A c' cove cat'1 exce=t th'ds uhich shell I i l' 4 /I I I i l "+.1 ,,

/Afl be cent =<tu/.i w n,..r -4 m_ i  ! l' I I I l }

u t/D' I i l l 11 J l 1-y5 1/s % /2~ .e-w 77 eso/7s ,, . _ ene i .4 1- I > I i i i !

~ - ~

cd:ls=: ' ' - , ,:u w . ,= c .:A - . .: ~- -. a := .: i I l 1 t I i i 1

&7 i M ~ n B".w.3 ' cs.assr pwE:S C.5A S/S c.r 65 o,e .sA .5& )

u.-

\ 2. I l. ;. van 1, fH/%i - l 1 I I l

~

=~,7.9 ., e e ,- - ,

~, ,, i g , o- m JMF" cec 6L i t

'l l s t s t p L J

%w / I I -

r i l i i i I gx l /4 2 .4d Nr ono t,2 I i 14/om lO-zs-141 1 i I i i e < -n i l I i i I ! I i 0.-D _lIjbn W C~ 2 Cm.:. 1 % of,2 / i c, I i j i i l i t- I --

T' - t <e-e s n%c c eS /C 8:et= o n G ? I i  ! i 1 l ! I l-i i d li , i l- -

4 i ! I i t-t i e LJ O l _.l_f .J__ i. I l . I i l- 1 I i t -- u .s , _ . . I i l l-l 1 .1 i l i T /M -P) nn=%,m _ '~~ M i 1 ie l l l 6 i

! P44W 4 41.1, -1.13 :4 a ci :1= W .e 3 , ,_ i i l i i t I i

! 1LJ11 c a nt , 'strion n a nJdt 'J -t o -# f wi t I i i i i i i i

! __..__~- _

=/u dyl.J.r i 1 4 14J M u 1 m .t 't I i l i i i l i !

I I' WEf.XTC GCfr~ W M e'5 E:7.=I=h h -5L4 J h il i i i ii! I i i  ! t a wi &~ e. a R_9,/s K!=i e Fs R W-9' m ' I i '

I i i i i i j l

-~- ~ a = .:.:m e., ,ae  ; j i u , ig e i 3.pproved.B  : hcM - . I u: L ..

2d.I::i%

=i !

7' . e _2

( Ia.t e : i /79 QUt.P'lS Hl i R t P .._ .. a:.t !<n t .

!FOR MATERI ALS 'AND OPERAT!ONS.' SEE SMETCH NO. ___ SHEET O?r I M - S rov.'n. Sloot, Inc. '

CONDITIONS j .'F: l fy] F: l M:-l My l M:

N _/ -- ' - ' - - - DESIGN l l l i l REF. DR A','llN G NUMBERS "YsIT u IM743 ~!  !~

?':E : N/-o7m ,t_lt// ELECT:m 'c veJ EMERGENCY 15 5739! j  !

37Efa'_

  • S/-, - . -o ocPrJ. / / -.

H.V. A.C.:,9- ow c' ~-W FAULTEC l I

1

.[Elc.w/ o/r m!l CESCR/?T/C// Ci[STC 1 Q , 3 %2 M M ithEf% r'dce, TU

.& *I 'h. j '. AdoM]l55U F la / , - G' FOR CCN5T Ace r,:e ORDER' 4 MR.J@ 5 5. a A.is tm-.c - c

@UU m ,_ _ _ - __

i _ . ,' i j 8

l Mt RX NO. Sa- /-O/O -c;c -F?2 e 0 53

7-P ' ' ' '

%-'*' U U y* .v.i. ,4jg *8

. ( 4 g

, . , .F* * "*

.'M / ",p . O C z {t C >

-f""I "i%, l '-9 Gj;.{* h.ig

\

8 "y *1 p d <-

m G 4 Q 7

\

i

  • ) .d
f. k *

y*

  • f If b :g

-Qm2 Q 1 a *

. t' d

n"""

[f M(w'h $ M "h .,,

.h A / '$

Og

,. ( g N

< f. a In h.

,4 l

S 3 $e gp 9 $

o ?6$..

os N 5\

O-h

,i

~,'F h  %- e 4

, $ b $ D [

O u<A( .*/,O

\

N. m" c

1

%3 o .p, h

A i,,3, h .J

.i f *40 .. O 4

s. g. e

.5, a ;-:

m f I m>

p j 5; s #

h ,

g yy 4 (.VMVfQ -

h o *d O '

? 3" QK

,; y C. l0

, i \.

g, i,o~ .

}

l. '

s.

T k.

N

,W *

/{,t.Nj-)Q k. ' ' 't . Qs-in .' % $ ~7

_ r. . . G\ *) \,/ \ / s . \/s/ - % m

' t,/ -

/ \: . .,/ \ / \ / \ / '

.;M r-M-

~

! .N /N c

(\ A /T.A. \/\/iri7 /k/.,\ /%_W \ / \ r_-\;/. \s.'\/ \ //\e-\.,N/\./\/\ ,%,./\/' r ~ .?.

' ' /\. . ./. 4./ \

H~A '\ /\ /

1 j

/\ '\A/\/\/\ '\/ V s/\ z ..

t^

EE 8 '.-

N ~' '

i AIn /\

N

./\A A A/>/T/\/\

/\ /\ /\ A 7 \W'\/\T'r/NL A \ r',\ /M/S 7/i.\//'r/\/\/9 , W /.3/'t ! i 1/ '\/'\$Os~ <' 4'b 1 i / A .,5 w %. '% .- b-i

.S,:.-i A /\ /\ A /\ /\ /\ /'i!. /i.// '/a'/lC/\ / \N[T$.~~. o s,.

. Of

.'. u ./'EZP-

>i. -~,. /\ /\ /\ l"fy i \ : . f\ \ r_\_/__,, ..m- Vp N

-/ ., . '.

p &,-K, .O g. .a

.A'\ /\ di /\, \/\/'/v_\/ \ .8

\ / .\  : \.1 7 ,::,A

/ . /\ S y W x. /\./. Y hi.,.:e.,. . N.c./ ~f ) 6 u

i'

.C0 /\ /\ A / rd\ A / \/?N

./

.N A./ \Cm.ge<

/' %/ b. D g i.A e y o .m 6 o;

/'g .<. -

Y/\/' i-. Z'

/^\,/\ <!\ A +a/\ /\ ..i4 f N /.<.=s.', 8. ~U'. /.\/\, \/ @

.2

.o 'H$. h o- .

.S co/\ /il/\ /' ./\ A / d'\ /\ d' / N. -'. . A/' \/ 9 ,' /\ /.k.yQf]S, .p ShgD

' ~ .

\,3 --

s./ ' %E .

. /i/\

/$jgfGN 3 ^/\/\

fl\ d'. \ A' f

,QF X E~C .~. M /\

/. \ cdtv -n

,\/\/

\ <

N \,

1-

\/ \ '  ?/^

/!1 cri Om- gg E ._-.

/gj q.

/v FE?- s T.V E.] .93 . . - @

.' a \ / \ /\ }\ /\A'\/',2

.. .(/\ , \./\,'- i .- ,, s. ./\r, cy\/\/ A A_/.\f

-3

.' /

J. .h . . . . .M '\/\ /y 7p 4 E~ cm 5 'r t

b

! (\ /\ f,\ /\ / XP /.

e, .

\/\ d. T ./. _'Us .3.-/\/\ / \/\/' d / ~1 ' . . f, .c, *, a7 m. 9 .O5

%/Nr' E g a .>

i, . Y\ W/_W/\ /\

/\ /ts /\/ .$'\ /\ / w.b \. f~ . Y /

/\ i ' \/ \/ '. /\/\e .

h/ V> \/ 'L , 'D A : ;i -

/\ ,N/ \,iN . F .5

/' / . ..

/ . \ 9 'O

\/.\/\Y\/\.. /\ /\/_\ / 9. ; L'

". dct n

-o \ b,6 . .

z z

/ ; /v\/ \. / \/ i.,'+t.a. p g.m&s, L

/\ /\ /4 /\ / \ /\ /\ v_r?. \ /\ / J.zi\ /r.;" l/ '. [l/ \ / \ A':

m

i a .

V/\ / \/A,: .! c .>. : .

. \ A A A /sy/Y/\ /' /\,.[\" (/'1,%!4vl.% lJi ' M\...a /W\/d 33j'Nni

~

en d a.

mn  !"a I.

/. .\ /\ /\ . '\ / \ /\ / \/.i/N Y y-. - .m

-J. ./. "/ \ / N'/i\/.V U -t #2 . d

~

L" d /a Ne%/' W\

/'s, 9,b/%W;2b'\

l k- n.

_\;/\

/\-A A /\/\ A

/\X\/.\A/7 /\/\/\/\i, \ . N

,\/\/hp/1 g g i .a.

n .o A t,f

= g J s/1/ \/%\

/

i/_34 f

P- O .'.

.\"/.'#1\ /\f._\f.\/1\ A/\ . L\ / \/ \w =/ \ 4,g60.L\// ~\)/ \// \/,X/4/ \/' FG? \ Ft .

._ A _ A A A A TS./; /\ Al '/ \ /\ /s n /At '. n. ii es e 'I /\ \ /s/\ -

I Q

y *

.O.' '

h_ I ih Ih "

g e m a tt-e s . p %.9 y _w I_, h = .s h

.- e Ca ra: L=r tp a

g. - .- x ,.

1 1u i

,m p

.gs +

- co .

. u N=

i r0 i

.- h,J p- 3 '"

lls E h_ f"i% .._ Fha

<L.

1

. .L.

W, .e. -

.? -

., p i s S m W

m. M.c ".-.

2 ::.

.n  % .

m 1.i w _r_n. ,( -

O .c 3 .o w

_.O r;i, .

= h.s

.~ .

m G Q ._

s -C yy e

b e jl > c. ,* m

@  % ) .:  :

&" \

W .p9E m

'Qs w.

.-%w'f~

I w u ., j, c c c c c @ c. T m

C

-g.x s; ag *-- 2 0 ooGo > > > >

%.j c g

~

-d a m

m A

-. > 4 N m,'\> ^i f . ,

i e.c c4x i~ i

,,,_ O i

. _.=.d

!"'t m 1 *

( c' e  ; (s] N [ - _n

{

1 so CN c] - t M '

'[Qh. $ .hh.j.) h "

i \ [

i(-:, - " .'. M... .t'2, Z.y:/..h' @... /.Ty' :. W 2 W h. W '.,f:. . f 'P. '--5.2 r:@WM'h.. I65.# E'-

l 4 . . , -- . %,:, . '- m@c.. . M,a.

i u..f.i .g;N:.~.;; -. e. .%.-... .,- d. } ..n/ y g :Y.4. .?....-..,. . . . .-lh ",-..=.

w. -

s  :. .+. . <:

l  ;'.,,<. ,  :.. s. ,.. ,. -- .*

> z.,.a.. .:.:.,. .. .... . .. ~ m.

n. .

-e, -,.. .o. . ..

Mt, . i&g

  1. '. O q e% 5.L

. ;.. .; *d W~

f .*B. . 'i i:.W. 3TA_t ev=y.?! a. .' .:.

J -

i '

t; ., ::. ' P-- e. . . . . :i..fi..' .

. s...E.. . . # ,t.V. ..s AS' BUILT' RECORD c M '.' . . .

21.:.". 3 P c ' g.eier , ,. . n. . ... ..

e : ;.g

,_., . ,,, . - , . . ..  ; t :. rp- gp. . . .s. .

WR.. ..f se . .

s,.. . .( ,

. _ A .. . .

L.. :

e.

8 ,',

.s . .t : 8

., 4 b .

,~,7.,i . . ,. , .

, ;. .',; .y b .:

._.,,..._'y 1

.. ... - .~;. .

c. .:. .:.. .. v -. . . . ...t~.,.,,,_.,..-s.,.:,...

.3. .: ~/

-_- V..

-.,.'7.,,,

, t .. . ,.o..-. .... .- . . ., ... .(: . , ~ . ,. .

t... . . .r 1- , .

a. .:m:.:l.. 1_.Q.  :. ..._, w, .

.a_ s .. . r.

. , .cr. ,-. .:.n.

~ *

. ...3 .

!. 6. . i,:- - . g ,'. s :; ;. 2[mt ,- '. .... . . :;, v..th, e 7 n ,N. . *

.Y.YN...

e.

. ..  :.. . . ::a ..@M:ra.

. <- -  : .r--- e .rs. >

9,. p:a . k*\ . .t .T:. ...: .h

.t,
  • :
  • ? .R.

. N'-* .*.

,;g f.*

.;.e ce .:.s.. .

a y. . .

..a... ... . .s . ; .> - 1 n,. . .w. . -

3I. l~.3% < 08 C E.G

{.M '-/g'.,7

. r,.. : '* *O i#h'.:& 2A -',28::.E 'C 7.

--* T":

@- 0- *O"^. * * * * *' ". M '- M ".rp

. l.-""r-1.*"".T

~~ . -l % .: ~;. &

s. e .

rs

!..'r&i.W

. . f _,: , ~ . , - :1 .

%.e .. .

'b  ? . :- .n ' . " ,* * :.. '.-~ ;:**....':...

~.i W --~1 Q' ?- y - :. --_5.~c;i.n

  • ' 'y'.?O t:ET20 -
  • MUCD:!:.Y wi.f..

r , ..w s...a<.

. * . . . W .r.w n 's *. . -

. .=

. ,@i"::.dy ":5YtGM."eM 1W &ip 3:s tuM1k. '. ? U W. .:%.m~. ; V N '. , .

g .

"3 3 P.R E'*W -?*-M.qtX' m! ~ M 5'-3:.- :s g S krund  !:C d fu2i M F J'd OJ l'P- W3.U' 4 w rmt y+:W.di  ::.serw s e m i m .? @m N

v. a. @,c>w '

i@ Ew 92 m 8 20 k;;.w M t.::rv.u,

..,  ::w=.c, n . A. e.m .

. . ... :: G. [, .. ,

.. u .w../ -// ,sm-a-,.. s ,2.. .. . . .s :

r-

. .: :y,. .u,.. . ~. -

m,, z a ., .

.... n.

c.,. e. -

.-. w.r.v.s, ..... ; w., s .,n . .

W r5 - ...9 .

--a

.. - . . . , , .,0;. *e.,.,

.a.,-  :*

..t

- -- 1 , ,, . q . .

... .. .. 2

- e

u

. < a

-O *I s --. . . . .. ...n..c ei. ,. ) . g , ,- .,s .-<4.

.w. . '3 -. 3.s s L. i r., *4 ..~1

.. J . . . , .:

.:;r.u <

...s. -

s .. HS ~--e r9 t r 3. y'.;+. .-*--- c ..d ~

-::._  ; .a- .c...

,. u. .. .; go9
: .c . ,f. , , .., efr; f M..N,s .s,,..

g

. . . .. t .

9.C.I'. . N.W,

. . . .. s

,~irit . / i .d  ! .

~?igsd '. ?s b' . :'?i' 21.f f c

  • d.~ .95 % y 7 " ,.14 ..

!. W r _ -

.).

, .7?"n.

,. . ,. [ .oi....... . . ...

},

ca - . ' .,i:: r1 C.

gg. 09. - 6t:43 4 ' .n s .

Igs.  %. , , ;.;,, . - - _. .

r .. -..~] , r ,

,,a

s. . . ,. 'l .
  • L.

UM. M.. ,:e h?$.5,.. -i .t- . .. i.e .:sf

5. 4 ' .c 7':'b

... N.. . IUI54_. 'd -

.- ?- N V 3 r,i ~

.~

' .d. ' . . .I E i'I".

. i

. . . , ." : *. O ..ws. ..".-: . n-

[a- .s. .. -

  • .c .i -a L. 'c i f. . M.,.s. .

. .+-

.- . *. r.* "g.

\

s . *- * .

t.

L.%, i4... 3. . , . . .

  • =

t

- .~.3..

.t g , . . .

r ., . ,' =-

eu g,A_ . .*. ,=

.~ . - ~ . --

.. :4 , \ n >.

'k.. ::l:.~. . . .

    • .u ,.* . .

/ . .

. .. i 1,c.:,..rs '*

rA -l3 ' ,,. =-

I ae  ?.* .~;

, ~. .'

A. . .q)5

~* . **s ,.. . 4~{. .

, *l.$ 'Z,,1,*g i .

1 z

'. - 0,'/

..~. *

..-.ge.,se

,m K . ~11 .

i sa ~ .; .c.

. :%.r.s., . .. * '

. v;t e t's' y .;. .

&T:.. b

T; e-r
,t s
S':* .w--*d" T 'g 4*- '
,M.Y .
  • e.~.~;[.2**:*.M L%. * ~

. . " '-? .

..s ..t

..[..

..u.. .~rN e.e,.(a w. . . v. : -

'...L=.

  • . t dhg *
  • g

,,sej

. .es . -

.~4.

. w ,. ~

,.: 1. . : ..

w. . ...

. . r.

. .s .. ... . , . .- ..

1. H$.nger Numbe%.. - - ..W-FOt0-OM R2fd. O

'.'.#'.'. Rev.

u .k.:  ::e.o . ..e' . ..

>u ..w...

2. Icdicat: Plate' Orientation on ~abov- sketc G. . T k..'$ .;.,-[ .. . . . .

-' W .z .

(b...L$ ob .s.$.0.5 r <;- C e c, s

~

~ t <s v .Mn w., < ':: -

m.:

Pla. Mae.E.alY..

t ..-:.

' s- -

, . .':. .-.y--

Igs

,, -l . . . . ,

4. Plate Thickness.

-, -a -

,,_.. . , u.. u .

. . .i. . . ... . . .

4 ; 3. N . .!!!! c,,. .

olt S,ze i  ; ... ...

- - ~

A . .

....~.--a.~

m e f==r-' . . ,. .

'y i

.s .

v ... .

~.s.,

3 l 6. If hanger has more thanEnipla'ts, indicate which plate is covered. Attach additionalforms forother . . .'*

M",i . .

plates as required. -

.. e ' -

M!

g #..

.q

.,. .'. . . .t,. ... -

7 -

4.a . .e .5. -.

. Pipe Support Foreman .. Date ."% s

. . . . .d. .., , .v

, . . ..e .. . ..

.->.~.

r  :

.? F

. QC Inspector Date

,. i, : --

...,,.~\ .. .

. .. . ~ . . . . .

n:

, ,r, .  :;g . s.

. , a c. .

. . g,. - _ .. : :-

.s .

-s Fic!d Mechanical Orioinator ~e . . f.

. Date .-4 1-~

.. [g ..

o

......r.

. . . , . , . , . . . . 3 s.-.. x. ,..;.. . --

.. . .  : . .. .....u.

Wl, ml.5; & :$ h&&.=5=h.Q. ... .~ lW_..:. .,.W . ..iQ$t pp

..n .u.M M &, i

. ' . . . . . . . ..:. w.

n. .::. . ...:. .. ..>. . - .

. .:. ., . A. ' : a.- .4. ..Ju : .. .. . qi t . , . .-,.u.=. :. .::...

. ~ . . . - -. -

v .v n.. . . . . - .

4 es NOTES REGARDING CASE EXHIBITS 498 AND 497, NCR M-1802 and M-1802 R1 Perhaps the most important change is the deletion (page 2) in Revision w

1 of the following statement which was contained in the original NCR:

SUMMARY

" Exhibits I & II attached show loss of control and failure to conform to sections V and VIII of 10CFR50, Appendix B by both craft and Engineering personnel. The drawing control and design change controls as specified in site Procedures has been neglected such that both these documentation packages cannot support these applicable regulatory requirements."

A re iew of this NCR, CASE believes, demonstrates that the above-quoted statement was correct. In any event, the statement should have been left in, with whatever additional information or changes were desired, rather than its being deleted. Other questions: What was the reason for item 15, page 1 (Corrective Action Request) being changed from Required to Not Required? What was the reason for the Document Violated being changed to ASME Section III from 10CFR50 App. B Pt. V & VIII? What explanation (if any) was given to J. Patton, the originator of the NCR?

l NOTE: The following are some miscellaneous notes which we typed up when we were first reviewing this NCR; we have not reviewed them with Mark Walsh for many months, but will do so if you would like to discuss this further.

Page 2:

I.C. What are actual dimensions of base plate (since nothing voided out). Why NPSI? Who is vendor?

I.D. 10 CFR App. B. According to Grinnell drawing, sheet 10 of 28 of TUSI's AF-1-001-007, sheet 1 of 2, they are vendor shop welds; if shop weld, why is NPSI involved if it is a Grinnell drawing?

1 F0A-85-59 l

4,.

Sheet 12 of 28, disposition. NPSI clamp -- Grinnell drawing???

Final As-Built Drawing: Brown & Root, NPSI, or Grinnell? (Believe it is Brown & Root.)

Only 8 welds indicated on drawing. Welds going to base plate have got to be field welds. At least 2 of them are field welds; and one that is not necessary.

I.G. Not shown anywhere. May not catch at as-built; may think it is already built and not go look at it again.

II.A. Not identical; dimensions 4" off. According to ASRF there is a difference in the dimensions between the bolts. Writer was right.

II.B. Problem was rewritten in Rev. 1 from what it was in the original NCR. Rev. 1 did not address the original problem; came up with a new problem. They are two different base plates. If these are already as-built drawings, something is wrong because they are not as-built correctly.

Page 18 of 28 (Rev. 1):

Reason for CMC is misfabrication by NPSI.

2

?

XXVII - 42 C<J CREDIBILITY AND/OR COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor Omission of Reinforc:ng Steel -- On pages VII - 21 through 23 of these Findings, there is a discussion regarding the omission of reinforcing steel.

In addition to what is contained therein, the following should be noted. .

The following documents, all of which have been accepted into the record, are pertinent: .

CASE Exhibit 364, NCR C-520 (especially pages 1, 35, 39, 40, 42-45) --

Large number of interior wall dowels in mat of Safeguard #2 out of tolerance; interior wall dowels mislocated and sufficient concrete cover cannot be obtained. 1/2" concrete cover for vertical wall bars is acceptable. "For horizontal wall bars a minimum clearance of 3/4" must be maintained." "

. . . potential effects on the structure if each of the 45 dowels identified . . . were bent to bring them back into tolerance. These bars are so scattered that. the bending would not 4 '

impair the performance of the walls which they reinforce . . . "

Discussion of calculated stresses.

Interoffice Memo (page 44): "In the past week, Construction has been @

raviewing the 5 instances in which reinforcing steel has been omitted y Tr concrete pours. We feel this is a very serious concern ano are taking all steps possible to eliminate this as soon as possible in the future , ,

. . . " Set up procedures to eliminate recurrence. (Emphases added.)

The NCR was dated 3/3/77; the memo was dated 11/4/77. $,

a CASE Exhibit 479, NCR C-669 (especially pages 1-8) -- ,

M Approximate 112 - #9 reinforcing bars required were not installed  ?

prior to concrete placement #101-4812-001, made on 5/25/77. Disposition: N Use as is. CAR (Corrective Action Repor^.) not required.  ;

Gibbs & Hill letter (page 4): " . . . a series of rebars had been ,

omitted from the reactor cavity concrete between Elevations 812'-0" and @

819 ' -Oh",. The missing rebars were located adjacent to the neutron de-tection slots and had been added only recently as a change in G&H draw-- (sj 7 ings 2323-51-0572, 2323-S1-0574 and 2323-S1-0575 . . . the omission of 4 this additional reinforcement does not in any way impair the structural integrity of the reactor crimary shield structure under any postulated loading condition. The additional rebar had been added by G&H as a precaution against cracking which might possibly occur in the vicinity of the neutron detector slots following a LOCA (loss-of-coolant accident).

They provide a means of uniformly distributing accident loading stresses around the slots precluding the possibility of local cracking . . ."

As stated in our 10/18/82 pleading: CASE had not recognized the potential tie-in between this NCR and the crack in the Unit I base mat or radiation shield urtO we were doing this analysis; this was because this NCR deal t with the neutron detection slots and the NCR about the crack stated nothina about anythina but the base mat. It was not until the testimony in the June (1982) hearings that the possibility was pre- '

T G ter sented indicatesthat thatthe crack they could beabout were concerned in the radiation clTtfM M th shield.O ea {

FUltVOW gr

n XXVII - 43 9

CREDIBILITY AND/0R COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor (continued):

CASE Exhibit 479 (continued): .

Also, Applicants Exhibit 38 which was used in identifying the crack is Drawing 2323-S1-0572, which is one of the specific drawings referenced in the G&H letter. .,

(From page 8:) In regard to CAR's (Corrective Action Requests), the Office Memorandia to Bussolini from Mr. Tolson states: ". . . this mandatory requirement is considered to be redundant and does not contri-bute materially to the timely investigation and resolution of report-aole deficiencies . . . By copy of thi s memo to your Houston office we are requesting an immediate deviation to the subject requirement folTowed .

by a timely fonnal revision to the procedure." (Emphases added.)

CASE Exhibit 482. NCR C-809 (especially page 1) --

6 - #10 horizontal additional bars omitted for beam, Aux. slab

~

placement r002-7831-002 -- NCR is dated 10/26/77.

" Delete remaining additional beam reinforcement, leaving shoring in the Construction opening untill (sic) the 831'-6" slab and walls above -

that area are poured and cured. Then shoring can be removed."

" CAR #14" required.

CASE Exhibit 483, NCR C-810 (especially pages 1 and 8th) --

9 - 49 and 2 - #4 additional reinforcement bars around the elevator shaft door on the 832'-6" mat of Containment #1 were omitted, pour

  1. 101-7832-003. Repaired. "

" CAR #14" required.

Back-up file page (8th page of NCR): "

. . . design engineer has 4 concluded that if the rebar for the Reactor Building Elevator Shaft as j identified in the NCR No. C-810 and DC/DDA-477 had been omitted, cracking P of the concrete in this area could have occurred under some bending con- ..~

ditions, such as a seismic event. However, this cracking of the concrete in this area would not have had an effect on the nuclear safety of the plant." (Emphases added.) '

CASE Exhibit 484, NCR C-811 (especially 1, 4-6) -- "

46 - 49 rebar dowels.on the face of the excess letdown heat exchange room in Reactor Building #1 were omitted. CAR #14 required.

It was not possible to drill all of the re-drilled holes or obtain the specified embedded depth on some of the drilled holes; (one of them were plugged, one was embedded only 5", one was 11"7 one llh", 4 others were less than 2',13 were less than 3', 7 were less than 3', etc., out of a listing of 35;.see page 6). " Hole depth to be 484"."(Page 1.)

And on page 4 it is stated:

"The design engineer has reviewed all of the data provided by the above references and has determined, that with the following corrective action, the steam generator compartment wall will be capable of performing its design function at the location identified by the above." (Emphases added.)

l l

1 i . -

A*

XXVII - 44 CREDIBD.ITY AND/OR COMPETENCE OF NRC STAFF WITNtSSES (continued):

Mr. Taylor (continued):

It may be that Mr. Taylor was not aware of the preceding items, since he did not become NRC Resident Inspector at Comanche Peak until 1978 (Robert Stewart, who,also testified in these proceedings, was Resident Inspector before Mr. Taylor). However, consider the following, which occured after 1978:

CASE Exhibit 534, NCR C-1314 -- (especially pages 1-4) -- dated 1/17/79.

In Reactor Bldg. #1 elevation 808'-0" 9 Az.1800 between columns 9 and 10, specification was violated, due to the installation and removal of shoring and scaffolding in this area. A total of 57 #5 dowels partially embedded in set concrete have been bent and another 10 #5 dowels have been broken off at the concrete. Repaired. .

Page 3: Design Change Authorization 5080; " Applicable Dwg: 2323 0519, 2323-S1-0520, 2323-51-0521. Add foundations for the neutron detector well cooling units at El. 808'-O' per the attached figure.

See consnents regarding potential tie-in with crack in base mat.

CASE Exhibit 479, NCR C-669, preceding.

Also, Applicants' Exhibit 23 which was used to identify the crack is Drawing 2323-S1-0519, which is specifically referenced in the DCA on page 3 of this NCR.

As stated in CASE's 10/18/82 pleading, page 34 (emphases added):

"WITH REGARD TO EXHIBITS 364 (C-520) beginning on page 31 of this plead-ing- through Exhibit 534 (C-1314) above, THERE IS NO INDICATION THAT ANY-DE HAS EVER DONE ANY ANAL" SIS OF THE POSSIBLE TIE-IN BETWEEN Exhibits 479 and 534 AND THE CRACK LN THE BAS E MAT OR RADIATION SHMELD DISCUS 5ED IN THE JUNE (1982) HEARINGS. NELTHER IS THERE ANY INDICA" ION THAT ANY-ONE HAS EVER DONE A S"RESS OR SESMIC ANALYSIS BASED ON THE DELETION OF REBAR. ETC. IN VARMOUS LOCATIONS. EspECIALLY CONTAIMENT *1. THE DOCUMENTS REFERENCED HEREIN ARE ONLY A SAMPLING OF SUCH DELETIONS."

From Inspection and Enforcement (I&E) Report 79-18, covering inspections during August and September 1979 (NRC Staff Exhibit 70), page 13:

" Unit 2 Contairinent Concrete Placement Activities

"...b. Placement 201-5805-032 "On September 4,1979, the licensee Site QA Supervisor notified the RRI (Resident Reactor Inspector, Projects Section, R. G. Taylor - see page 1 of attachment to cover letter) that a quantity of shear tie re-inforcing steel (cross-connecting the reinforcing steel on the inside 1

.. . I

r

?

X XVf f - 45 e

CREDIBILITY AND/OR COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor (continued):

face of the wall to the outside face steel) had been omitted from place-

- ment 201-5805-032. The omission was reported by an ironworker foreman.

The shear ties are additional steel comparable to reinforcement utilized throughout the entire elevation and were called for in the design to take localized stresses just below the springline of the wall to the building hemispherical dome.

"The licensee stated that the engineer had directed the placement of the missing steel in the next placement (201-5805-033) and that the ,

structural integrity of the containment was not affected. The RRI inquired as to why this matter had not been reported to the RRI as a ' potential' significant construction deficiency in accoroance with 10 CFR 50.55(e) at the time of initial identification of the proolem on August 27 rather than after the fact on September 4,1979.

"The licensee informed the RRI that he had applied the various judge-mental factors involved in 50.55(e) and had determined that the matter was not significant and therefore, not reportable. The RRI reviewed the documentation and reported the situation to Region IV management. Subsequent discussions betaeen licensee and NRC manage-ment resulted in the licensee issuing a stop-work order on further concrete placement in the Unit 2 wall and dome penoing a thorough technical review of the matter. These discussions and confirmation of the stop-work order were documented in a Region IV letter to the licensee dated September 7,1979." (See CASE Exhibit 248.)

"The licensee's Architect / Engineer developed an engineering analysis indicating that the additional steel placed into concrete placement zone 201-5805-033 adequately compensated for the added steel missing in 201-5805-032. . . "

(Emphases added.)

(See also CASE Exhibits 617 and 618, the formal report and supplementary report from Applicants to the NRC regarding this matter.) As indicated by Applicants (CASE Exhibit 617, page 2, Attachment), this was an apparent breakdown in the QA/QC Program.

It should be noted that Applicants did not intend to report this omission of rebar in the Unit 2 Containment at all under 10 CFR 50.55(e). It should also be noted that this occurred during the same time frame when Mr. Taylor stated (NRC Staff Exhibit 195, page 3,1979 NRC Trend Analysis):

f XXVII - 46 e

CREDIBILITY AND/OR COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor (continued):

". . . It seems likely to me that the licensee will use his full powers to be less open with us in the area of identified construction deficien-cies than he has in the past. I think he will take maximum advantage of part 50.55(e) and the guidance to go throuch the necessary formalities but avoid, if at all possible, having to report to us. . ." ( Emphases added.) ,

During October of 1979, Resident Reactor Inspector Taylor did a special investigation into allegations by a former site construction worker. These allegations were discussed by Mr. Taylor in I&E Report 79-26/79-25(CASE Exhibit 253) and concerned the following allegations:

Allegation 1: "In the Unit 1 Auxiliary Building at elevation.807', rebar was omitted in four columns in the EA wall." (Emphasis added.)

Allegation 2: Concerned a 20' x 20' honeycomb area in the concrete slab acting as the ceiling above elevation (floor) at 832' in the Unit 1 Auxiliary Building, in the area just before entry into the Unit i Safeguards Building.

Allegation 3: Concerned a mixuo in anchor bolts which had been inter-changea in Unit 1 Containment.

Allegation 4: "There is general cracking of floor slab concrete in the plant buildings." (Empnasis added.)

Allegation 5: " Horizontal tie rebar was omitted in Unit 1 Containment /

Containment Wall ." ( Emphasis added.)

Regarding Allegation 1, as stated by Mr. Taylor in the ISE Report at page 5:

" Reference to design drawings revealed that there are only four columns in the EA wall of the Auxiliary Building. . .These columns, as well as the entire EA wall, extend virtually from the building foundation to the roof. Brown and Root NCR C-806, dated October 27, 1977," (this is in addition to the NCR's previously identified in this pleading) " stated that it had been discovered, while erecting reinforcing steel for the EA wall above elevation 831', that reinforcing steel in four columns had been omitted in the preceding erection activity; i.e., between ele-va tion 80 7 ' througn 831' . The NCR stated that twelve bars, each one inch in diameter, were omitted from each column and that four separate earlier concrete placements were involved during a period from May tnrough October 1977. The NCR information was submitted to the Architect / Engineer

XXVII - 47 CREDIBILITY AND/0R COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor (continued):

for resolution which was provided by Design Change / Design Deviation Authorization No. 486, dated November 1,1977, authorizing not only the omission of the steel between 807' and 831' elevation, but further directing that it be omitted in the balance of the columns through elevation 873'. . . the omitted steel constituted 50% of the vertical steel on one of the four column faces and .. . . the remaining steel is of the same spacing as the comparable steel in the wall face continu-ing from column to column. .

"The only unaccounted for disparity between the allegation and the referenced NCR is that of dates of occurrence, a difference of five to six months. The RRI has concluded that the allegation and the NCR are related to the same event since the allegation, as stated, was hearsay information and the construction of the columns involved was a a one time event. Therefore the alleged time frame is in error."

(Emphases added.)

It would appear that this was the incident to which Mr. Taylor was referring at Tr. 6495.

The I&E Report states on page 4:

"d. Two unsupported general allegations were also made regarding general crackina of floor slab concrete in the plant buildings and omitted horizontal tie recar in the Unit 1 Containment wall. Without s 3ecifics, the alleger was advised that these could not be pursued."

( Empnases added.)

In the further discussion on page 7 of the Report, it is stated:

" Allegation 4.b: Omitted Horizontal Ties in Containment 1 Walls "The RRI has not been able to either effectively substantiate or to refute this allegation. It is hypothesized that the alleger misconstrued an event wnicn occurred in the Unit 2 Containment wall just before his final period of empicyment. This event involved the initial omission of horizontal ties (more commonly referred to as shear ties) in the upoer part of the Unit 2 Containment wall and is discussed in Inspection Report No. 50-446/79-18. This hypothesis is based on substantial indi-

. cations that all of the allegations made were essentially based on hearsay information relative to events about which the alleger had little or no personal knowledge." (Emphases added.)

It should b'e noted that there is no indication as to why the RRI believed the alleger was even mistaken about which Unit was involved; it appears that

r .

0 .

XXVII - 48 CREDIBILITY AND/0R COMPETENCE OF NRC STAFF WITNESSES (continued):

Mr. Taylor-(continued):

the RRI is inferring' that the alleger didn't even know which Unit he was work-ing in.

It is difficult to understand how Mr. Taylor, in answering the Board Chairman's specific question as to "whether from any source of infomation whatsoever do you know of portions of the containment from which steel has been omitted because of engineering judgment?", would have remembered that he (Mr. Taylor) had performed an inspection based on a nonconfomance report regarding reinforcing steel being left out of the auxiliary safeguard building primary wall -- while at the same time he did not remember the far more serious omission of' shear tie reinforcing steel in the Unit 2 Containment, which should have been reported by the Applicants under 10 CFR 50.55(e), about which subsequent discussions were held with Region IV and Applicants with the result that the NRC told the Applicants to issue a s'too work order (see ,

CASE Exhibit 248), and which resulted in the reinforcement's being left out based on the A/E's engineering analysis. It is especially puzzling in light of the fact that Mr. Taylor referred specifically to the omission of rein-forcing steel both in Unit 1 Auxiliary B;ilding and in Unit 2 Containment Wall in the same investigation report. .

To be as charitable as possible, this raises serious questions about Mr. Taylor's memory -- so serious, in fact, that it calls into question his credibility as a witness in these proceedings, since there.may be other, equally serious problems which he has forgotten to inform the Licensing Board about.

ov ~ u ? h A:CEZ CC.Y- 55:C5

~

.i

s == .s=== cc:

Texas Utilities Generating Company  :

DOCKET No. 50-445 Comanche Peak Steam Electric Station, : 50-446 Units 1 & 2 -  : .

=A:lllr: e.... w 3. 3oa3 ?At-s'e:. 4838 thru 5178 A:::: Fort Worth, Texas -

T4AI 1I.D19N j NTG

.J~.

4 C 0 71 , ' d .1. Ave. . ; 5 . N . Wm * - ' :;--- , 3. C.

22C 4 Ta'.r " - = (20:} !!4-2 45

-e pc41.;rM.*4 8:09 i S PDR ADOCK 05000445 gg F0lA-85-59 g ,,

4953 l

1 BY MR. WALSE:

.- 8 2 l 4 Mr. Finneran, you stated that there was one 3 support in March of ' 81 that had been uns table similar to ,

l 4 this one shown on 4-o?

1.

g 5 BY WITNESS FINNERAN:

N j 6 A, Yes.

R A 7 4 okay. What measures were taken after the j 8 discovery so that no more reoccurrences of these uns tab le d

c 9 supports would come about?

I

@ 10 BY WITNESS FINNERAN:

3 II 5 A The possible question of the instability of R i y 12 ' the supporu I was talking about was raised as a result of 13 the normal review process by the responsible design b I'4 organi:ation.

t T

15 5 The support that I'm talking about is a

I' '

E identified by --

e Y 17 l d i 4 Well, was the --

5 <

II

$ BY WITNESS FINNERAN:

c w

I' g A May I finish my....

20 JUDGE MILLER: Finish your answer, please.

21 1 WITNESS FINNERAN: The support that I was i 22 i I talking about as identified in March of '81, I believe the 3

23

, original design of that support, to the best of my 24 !

l knowledge, was similar to this one here on 4-0, and it t

'l i was a strut and a clamp arrangement.

(

l l l ALDERSON REPORTING COMPANY,INC.

.  ?

6' \

4954 w9 1 The field engineers, as I related yes terday, 2 had modified the support to this configuration 'shown here.

3 The field engineers, and I reiterate again, do 4 not have any design responsibility for the support.

  • 5 In the normal review process of that field b

] 6 change, I believe it was identified that the field R

& 7 engineers had done something that was questionable as far N

l 8 as the stability of this support was concerned, and d

a 9 requested that a change be made to it to improve t.5e t

i 10 stability of the support.

II That was done.

  • l

$ II BY MR. WALSH:

E g 13 What procedures -- Jus t a moment, please.

s

, O m I g 14 1 What measures were taken to stop the reoccurrence I

f g

15 'i of these configurations?

d I0 BY WITNESS FINNERAN:

w II h A Well, I indicated that I believe the problem I

E I8 f with support was identified in the normal review cycle by c

19 l the

) responsible design organization, and I would assume 20lI they would continue to pick up those same kinds of problems i

21 as they reviewed changes that we made in the field to the 22 i j supports.

23 0 Therefore, no measures in regards to the 24 l l instability of the support was promptly --

25 i

j MR. REYNOL DS
That's argumentative, I

L ALDERSON REPORTING COMPANY. INC.

o' 4955

-10 '

1 Mr. Chairman.

l 2 JUDGE MILLER: It is. You',ve had the answer, 3 and I think you've had full information. The objection is 4 sustained.

y 5 BY MR. WALSE:

N I

j. 6 g Eas there been an NCR written in regards to R

& 7 unstable pipe supports?

2 l 8 MR. REYNOLDS: He answered that question before, d

n 9 Mr. Chairman.

i o

g 10 JUDCE MILLER: I'm not sure. Did you answer E

= .

4 II it before? I donLt recall.

f E

12 l i

MR. REYNOLDS: Someone on the panel did.

fa 13 l .

JUDGE MILLER: Well, perhaps, but he's asking x f 5 14 ' him.

E j

s 15

\

Do you have the information?

g 16 WITN ESS FINNERAN: To the best of my a

y 17 knowledge, I know of no NCR written because of unstable 5 l .

'd 18 i pipe supports, nor do I know why there should be one I'

n written on these.

A 20 i They were picked up in the normal design 21 review process.

22 I i BY MR. W ALS H :

i 23 g Did you say field engineers had modified the 1

24 '

l pipe support to make it unstable?

25) //

t i

ALDERSON REPORTING COMPANY. INC.

i 4956

,-11, 1 BY WITNESS FINNERAN:

2 L The field engineers made modifications to the 3 support. They are not responsible for the design of the 4 support.

3 5 g What is their responsibility?

R

] 6 , MR. REYNOLDS : Objection, Mr. Chair =an.

R E 7 JUDGE MILLER: Well, he may tell. It's been l 8l gone into.

d >

d 9 WITNESS FINNERAN: I think I explained this I

f10 yesterday. The field engineers that work for me interface 11 directly with the craft.

f 12 l JUDGE MILLER: In this connection; I think he's E

g 13 asking for a particularized interconnection there.

m j

u 14 i In terms of the subject th at he's been j

m 15 discussing.

/ 16 '

WITNESS FINNERAN : Yes.

g" 17 j

JUDGE MILLER: Rather than general, could you E

18 3 be more concrete?

=

II {

f WITNESS FINNERAN: I'm trying to be specific 20 as to exactly what their functions is, field engineers.

I 21 JUDGE MILLER: Well, the function in regard to i

22

, the changes made in the field. This is the context.

i 23 I

WITNESS FINNERAN: Yes, I believe so.

24 I l JUDGE MILLER: Okay. In that context, go 25 i

ahead.

I ALDERSON REPORTING COMPANY. INC.

~

. 4957

-12, I WITNES3 FINNERAN: They interface directly

, 2 with the craf t. Their function is to resolve interferences 3 with the craft, and make and document changes that will 4 resolve these interferences, and that's all their function i 5 is.

j ,

j 6 JUDGE McCOLLOM: Mr. Finneran, may I ask this 7 question. Who told them what to do to make the change of 3

l 8 this interference? i d

i 9 WITNESS FINNERAN: The field engineers?

t h 10 JUDGE McCOLLOM: Did the field engineers decide I

h 11 i what the change was going to be?  !

a j ,

f 12 WITNESS FINNERAN: Yes, they do.

3 13 l JUDGE MILLER: They did. We're talking about ln 14 l a specific area now.  !

15 5

a WITNESS FINNERAN: Yeah.

I' d JUDGE MILLER: Okay.

  • I II h , JUDGE McCOLLOM: All right, and yet they are e 1 II

$ not responsible for determining whether it's stable or j 19 not?

20

, WITNESS FINNERAN: No. They j us t document what 21 I

! they have done, and that documentation will go on to the 22 l l responsible design organization for the support, and they 23! . will review what the field engineers have done.

24 JUDGE McCOLLOM The responsible design 25 organi:ation is the one that designed the original one?

i l

ALDEPSON REPORTING COMPANY. INC.

! 4sse 013 1 WITNESS FINNERAN: Yes. In the particular case t

2l of the support I'm alluding to in March, I think the 3 original design organization was ITT. ,

4 I think there 's some confusion as to how the e 5 field group operates. They have no design responsibility.

N i j

6l All they do is interf ace with the craft and E

E 7l make changes, document those changes; and that change will N

j 8 then be reviewed by the responsible design organi:stion.

J

9 If the responsible design organization decides i

@ 10 l that the change that th'e field made is not appropriate, z

=

a II l then We will modify the support in accordance with their y 12 i request.

3 I g 13 l JUDGE MILLER: I have a problem with that in n

5 14 l the sense that all this interfacing business doesn't E

15 5 j explain to me why this particular instance, the fis1d

=

g 16 : engineers made certain changes which ultimately turned out s

II h to result in s cme ins tability.

c 18

$ i Why did they go ahead and do it without first s

I9 j I i

obtaining clearance or consultation with those who have the 20

! responsible job? Why is it coming af terwards , as you are 21 l .

describing all this interfac!ng business?

l 22 i WITNESS FIMMERAM: The purpose of the group is 23 '

to resolve interference problems with the craft in the field 24 l aspeditiously. .' . . . .

25 l j JUDGE MILLER: That neans speedily.

i

ALDERSON REPORTING COMPANY. INC.

i.. .- 4959 f,-14 ,

I WITNESS FINNERAN: Yes.

l 2 JUDGE MILLER: We ll , then, was it because of r i 3 speed that they went ahead and made a certain change that 4 ultimately was determined to result in instability?

g 5 WITNESS FINNERAN: From a s tudy of the comple te 2

j j 6 situation, these gentlemen, these field engineers make  !

7 their judgments based on a certain amount of knowledge f i  : - '

l 8 i and -- ,

e '

I 8 9 JUDGE MILLER: I'm talking about this I g .

10 particular thing now. I don' t want generalities or their l

4 _ ,

j II *'

3 general knowledge. You keep giving general answers 'to i a j y 12 I specific inquiries. ,

l E I l 13 l Please, sir, address yourself to this

!I4 f

particular instance, because we know that there was a t

!  !* 15 result of instability.

} d a

I' ! We're trying to find out why. We're also trying ,

h II f to find out why it was done in the field without a ,

g \

II

);

3 c

clearance from these people who apparently have the sole t j j j9 authority.

i 20 Now there's something here that we would like i i 21  !

j to have explained. '

ii 12 I WITNESS FINNERAN: That's what I'm trying to

j. 13 3

. explain.

i 24 I JUDGE MILLER: All right, then, keep away 25 ,  !

from generalities.  ;

q i <

1 t 1

j

{ ALDERSON REPORTING COMPANY. INC.

f  !

l

49G0 15- 1 .

What happened in this ins tan ce , and if you don't 1

2 know, we'll tr; to find out; but I think maybe you have 3 enough information.

4 WITNESS FINNERAN: I think the ques tion will 5 be clarified if the function of the field engineers is j 6 understood.

7 JUDGE McCOLLOM: Let me ask a question.

2 l 8 It seems to me like -- I'm being disturbed by d

n 9 the fact that you say they have no design responsibility, j

i E 10 and yet they made a change which I consider to be design.

I .

k II I . If you change something in the field from a 1 y 12 l what the original design was, that's a new design. Is I3 '

l that a wrong concept?

fM I4 l WITNESS FINNERAN: No, it's -- Until that 15 6 change would be approved by the original design a

f d

II l organization, I would not consider it to be design.

17

$ It's simply a change that's made to .h e

$ 18

= support that allows the craft to continue, and if the 19

) i change is not acceptable to the design organization, it will be =odified.

21 l JUDGE MILLER: Isn't that putting the cart 22

, before the horse? 3efore you go ahead and make changes 23 '

out there in the field that can have some effect on 24!

stability, why didn't you get the appropriate clearance 25 from the people who have the expertise and the responsibility ALDERSON REPORTING COMPANY. INC.

l 4961

  • 16 1 first, not last, not because of what the. general practice 2 is, not because of interfacing, but before it's done, why 3 don't they see to it that expertise is brought to bear, 4 rather than go ahead and do it and leave it to all these 3 5 concepts of who is going to catch it and when?

2 j 6 WITNESS FINNERAN: Well,.if you compare the two 7 processes that could occur. If there was an interference 8 problem with the support in the field, and it was -

0 9 idesitified that a change needed to be made, and then if you 10 went back to the original design organization for the s

! 11 support and identified to them that there was an interference problem with the support, they wot11d pull out all the

  • f12' 13 applicable documents and try to research the change that

!I4 I

might be made. They aren't necessarily in the field, okay?

5" e

The original desisn ervanisation in this case l'

ai .is in -- in ITT's case -- is in Providence, Rhode Island, e

h II i so they are not accessible to the site.

II Ry the time they produce the design change and E

j I' it got back to the field, that's a very long iterative 20 complicated process and took a lot of time and very I

expensive.

JUDGE McCOLLOM: Let ra ask this. Do the l qualifications of the' field engineers prepare them to de j such design? Are they prepared and have the ability to do

"' the design of those kind of hangers?

i I ALDERSON REPORTING COMPANY. INC.

j 4962

.17 1 WITNESS FINNERAN: Generally, yes.

l 2 JUDGE MI LLER : They are design qualified, then?

3 WITNESS FINNERAN: Well, no.

4 JUDGE MILLER: That's what we're asking.

e 5 Don't be under any misapprehension of the thrust of our P l j 6! questions . in this regard.

R R 7 WITNESS FINNERAN: Well, I'm not. I want to A

j 8 understand exactly what your question is.

O  !

o 9l JUDGE MILLER: We want to know that the I

@ 10 people in the field who are going ahead and making these z i

= i ,

j 11 changes for the reason you've indicated and all the rest a

'g 12 l of it, we want to know they are qualified to do it, and 4 l g 13 ' we're not trying to look at some organizational chart to a  :

m l'4 find out.

G ,

[g 15 We want to know who these people are and what

  • i g 16 l qualifications that they have to reasonably enable them to W I h

x I7 l go in and do this, as you've described it.

y 18 WITNESS FINNERAN: Well, let me finish the h

i I9 i three examples that I, started.

A 20 I described the one process to you of the way 21 I a design change might be made to a support.

2 JUDGE MILLER: Okay.

WITNESS TINNERAM: The second process would be 24 t if an interference was identified and someone s o m e w h a t ' .. l./.

25 -

knowledgeable about supports --

I i

ALDERSON REPORTING COMPANY. INC.

4963

-18 1 JUDGE MILLER: "Somewhat knowledgeable," did 2 you say? ,

3 WITNESS FINNERAN : Yes.

4! I JUDGE MILLER: "Somewhat knowledgeable"?

g 5 WITNESS FINNERAN: Yes.

N j 6' JUDGE MILLER: Go ahead.

R 2 7 WITNESS FINNERAN: He wouldn't need to be K

l 8 someone who had a great deal of experience in design d

= 9 supports, but he would be somebody that was f amiliar with Y

E 10 basically the interference problems that could occur on

$ 11 the site and what could be done that might be acceptable m

  • f 12 support design to correct the support to solve those E I g 13 I interference problems, 215 he would go ahead and make a

M j I4 that change immediately on an interim piece of change W

j

  • 15 l pnper, and then allow the craft to go ahead and continue g 16 l construcuion on that hanger based on that change, d

l I7 I

( Then that design change paper go back to che e

3 18 1 original organization for their review and approval or not.

c 8

19 e Those two processes, the first one is very a

20 expensive, and the second one is less expensive and they 21 are both as effective in coming up with a design document 22 that does describe the support.

23 '

! 77 l

//

3

; //

! I

! ALDERSON REPORTING COMPANY, INC.

  • J0f '

4964 9-1 1 our ex'perience in these cases has been that 2 less that about five percent of the changes these field 3 engineers made, had to be modified by the original design 4 organization. So, it has proved to be a sound economic I

i 3 5 decision on our part to proceed that way.

N j 6 JUDGE MC COLLOM: How many times, roughly, R

$ 7 have changes had to be made out in the'fleid?

3

$ 0l WITNESS FINNERAN:I would say many times.

d

  1. 9 JUDGE MC COLLOM: What percent of the time or --

j g 10 WITNESS FINNERAN: Almost every support, to my 3

=

II E

B knowledge, requires some type of minor change.

y 12 JUDGE MILLER: Well, a minor change to one E I 13 l g person with.certain expertise might be a whale of a lot

a  ;

m 5 I4 I different than that of some other person, with more or 5 l jm 15 less expertise.

j 16 You see, what we're trying to' find out is, the

' 17 3 somewhat qualification or sone of these words that you use

=

E 18' to dilute a little bit the expertise and the responsibility E

19 of the person in the field who is. causing changes to be .

20l' made which could have some stability factors and we want l

21l to know how it's done or to trace it through.

1 22 Now, I think you've given the two methods. I 23 ' can't say that it's a subject of criticism but you obviously 24 have excluded the first method because of the time it takes

'. 4 l 25 , and the expense. I know those are not inconsiderable 4

ALDERSON REPORTING COMPANY. INC.

i l

_ .y . _ , _ , . _ . _ _ _ . _ , _ . . . . . . _ . - . _ - . _ . - . , - -

_ . _ _ . _ . _ _ . - , _ - . _ . _ _ _ _ _ . . _m_- . . _ . _ _ _ _ _ , . _ . . _ _ , _

4965 9-2 1

f actors but when you .come to safety matters, they aren't 2 paramount either. '

3 That's why I want to be sure that since you 4 have indicated that the second method is the reasonable s 5 one, in your judgment, then in order to test it's adequacy, a

j 6 as far as our record is concerned, we need to know the R

A 7 qualifications the people actually have. You say somewhat.

l 8 We need to know what the somewhat is and that the residue, d

2 9' after you subtract.the somehwaty enables these people toe.do a 2

o y 10 professional safe job in the field.

3_ .

]t 11 Now, that's what we're really probing at.

j 12 j\ Y cu are helping us but I don't think you've yet given us E I g 13 --

and maybe you don't-have the total information on it.

m

=

s

% I4lI WITNESS FINNERAN: Well, the two key issues, j

=

15 I believe, are that the changes that they do make are g 16 documented on change paper and that will g'o right to the

, = -

fc 37 I

original design organization for their review and approval, I8 JUDGE MILLER: That takes months.

?

I l 9 3

II l WITNESS FINNERAN: No.

l 20 JUDGE MILLER: Oh. I thought you said that took

  • 21 l time to ge to the original group up in Podunk or wherever 1

22 I it was.

1 i

23 I WITNESS FINNERAN: In this case, to expedite 1

24 f that review, we do have a staff of those people on site, i

15l 1 then, to review those.

i l

l ALDERSON REPORTING COMPANY. INC.

l l

t I

9-3 4966

)! JUDGE MILLER: That tells me something.

I 2' Go ahead and tell me about that.

3 I thought we were taking all this time and 4 expense because it took so long to go past A, but maybe e

5 you've got something in the field that helps and, if so, j 6 we would like to know about it.

R

{ 7 WITNESS FINNERAN: Well, that group is there G

j 8 to review these CMC's_ as they are produced and d

2 9 z,

modifications will be made if they are required.

C y 10 JUDGE MILLER: Okay.

_z Il h You may ask.

E i 12 BY MR. WALSE:

z 5 I i 13 ! O You stated that five percent of the supports E I l$ 14 I had to redone; is that correct?

E 15 BY WITNESS FINNERAN:

j 16 i A The figures that I recall were that .the changes u

d 17 l\that these field engineers have made that less than five

=  ! -

}C 18 percent of them have been required. The people who 19 I a

reviewed the changes have required that less than five 20 percent of them had to make some kind of modification.

2I 4 l

Do you recall what documentation that was?

22! BY' WITNESS FINNERAN:

23 A No. It is, to my knowledge, based on discussion 24 , with people.

15! MS. ELLIS: I jus wanted to clarify something

~

J

'l 4

3 ALDERSON REPORTING COMPANY. INC.

l 9-4 f 4967

. 1 for the record.

2 I believe we did this yesterday but for the 3' record, in case anyone was getting this today, when you 4 say ITT, you referred to ITT Grinnell; is that correct?

g 5 WITNESS FINNERAN: Yes, that's correct.

N j 6 JUDGE COLEi.. Mr. Finneran, your comments R

$ 7 about field changes, that less than five percent of them j 8l required correction, that applied to all of the aspects, d

y 9 did it not, not just to pipe supports?

2 5 10 z WITNESS FINNERAN: Well, I can only answer on II

! the matter of pipe supports.

3 I I2 JUDGE COLE: All right. Thank you.

=

~

,3 5 37 33, gangg

= l 3

? 14 l O Is there any documentation on the cost and

= I' 15 ~'

! h installation and removal or reinstallation of a new support

=

k= '0 ' compared to the cost of having some engineer evaluate the N I7 CMC before the modification is made?

E  :

= 18 SY WITNESS FINNERAN:

P_

19 A Well, I personally wasn't involved in the g

n 20 decision to proceed with the field engineering group but 2I I believe the decision was made on the basis of an economic l

22 decision and all of the appropriate procedures to make sure 23l that the field engineers would do nothing that would l 24 ' encumber the design or stability of the-support where I

installed.

ALDERSON REPORTING COMP ANY. INC. l

4968 9-5 11 MR. REYNOLDS: Mr. Chairman, might this be a 2 convenient time to take a break?

3 JUDGE MILLER: Yes. We'll take a ten-minute 4 l recess. -

g 5i (Short recess.)

e n -

e j 6 JUDGE MILLER: Everybody be seated, please.

R E 7 Mr. Walsh, are you ready to interrogate?

l 8 li MR. WALSH: Yes.

d

=; 9 JUDGE MILLER: You may proceed.

2 O

y 10 BY MR. WALSH:

3 '

)

B Il 4 Mr. Finneran, is it,to your knowledge, a I 12 standard engineering practice to make changes in the field E I g 13

= and document it later and to verify that the thing is okay -

m 5 I'4 I later?

t iu 15 BY WITNESS FINNERAN:

=

f 16 A It's not documented later. It's documented at

^ l

@ 17 : the same time the change is made.

u i

=

5 18 G Are you saying that they make a calculation m -

h

{ 19 before they make the modification to the support?

20 BY WITNESS FINNERAN:

21! A Yes. The field group that I am referring to is 22 the staff of some engineers and technicians with experience l

23l in pipe supports and they do do some calculations before 24 they make some of these changes, yes.

25 WITNESS REEDY: Mr. Chairman, may I make a ALDERSON REPORTING COMPANY. INC.

l 4969 9-6 I comment?

2 JUDGE MILLER: Yes, you may.

3 WITNESS REEDY: There is a question as to 4 whether things are standard and I would like to point out g 5 that'the. design of a piping system with obr" supports-is R

j. 6 an . iterative process. You have two different groups, a R

R 7 piping group and a support group and they have to work j 8 together and do their independent design and work back and d

=; 9 forth as an iterative process, usually around five times.

I

@ 10 It is not unusual to do this.

E 11 In fa'et, there is'no other way you can do it a

y 12 on a piping design system and I feel that the impression

=

~

l 13 i

here is that this is something abnormal.

m E I4 I've been associated with at least fifty C

15 .I g nuclear sites and this is the way it's done.

=

y 16 7.d also like to point out that in the design

= l 37 ,

y of nuclear reactors, which I have designed at least twenty,

=

6 g 18 you must have a design group make.some assumptions, order 19 material and start fabrication at the time prior to the

20 start of the anlysis, and design and analysis on a l

l 21 l reactor, also is an . iterative process, and you can change l

22 l your design loadings by modifying the structure, the same 23 ' as you can in piping.-

l 24 ; If you have a support that may be unstable or 15 ' in one certain direction, that can be accomodated quite I

1 ALDERSON REPORTING COMPANY, INC.

~

4S70 9-7

~

1' a few ways. Changing your loads, adding more supports or l

2 l not necessarily even requiring stability in one or more 3 directions.

4 So, I haven't heard anything here that is '

s 5 unusual. We keep bearing on it and I just wanted to clear 2

5 0 the record. This is the way it's done. I've have extensive R

$ 7 experience and I don't see anything unusual.

A 5 8 JUDGE MILLER: Thank you.

e I i

e 9

, I think the Board will probably have some 3

@ 10 z questions in that regard when we finish the examination,

= 1 Il '

@ so we appreciate your giving us your overall view. It's a

12 helpful.

E i

_E 13 l All right, Mr. Walsh.

= i n

5 14 ' BY MR. WALSH:

M j 15 g So it is true, they do provide calculations E

f 16 , prior to making a change in the field; correct?

  • i d' 17 i BY WITNESS FINNERAN':

x- ,

~

v 18 ' A Depending on the nature of the change required, "g 19 ' they do do some calculations,yes.

n 20 i

G Are those calcula tions incorporated at that I

2Il  !

time in the design package?

12 BY WITNESS FINNERAN:

i I

23 :' x go,The calculations a r e, d o.n e - t o try and a.s s,u r e 1

24 the change we are making will be a good change. .

25 O All right.

1 ALDERSON REPORTING COMPANY. INC.

1 -

9-8 i

i -

4971

(

This particular support that's shown on 40, L 1 ll 1 2i did you say the field engineers made the changes?

I 3' No . That's two questions there.

4 Is it true that the field engineering group e 5 makes the changes?

n l

" l 3

6: Is that correct?

I E

6 7 BY WITNESS FINNERAN:

j 8l- A The field engineering group does make some d

c} 9 changes, yes.

I h 10 i: G And they do sometimes provide calculations; z

= l

{ II l correct?

I I I2 l BY WITNESS FINNERAN:

E. I

]

13 !.

A They do sometimes make. calculations; yes.

=

5 I4 l 0 Those calculations are not' included in the

-r 0

t 15 , pipe support package; correct? -

=

E Ib , BY WITNESS FINNERAN:

  • 1
  • 17 '

y A No, they are not. The changes made will go

=

~

18 to the original design organization and they will review 19 i'

n I

it and make all their own calculations for that change.

l .

I l 20
G Are you aware if any pressure may be put on l

21 I the engineers when they finally do receive the package, 22 ' for exampic, en a support like on 40, to claim that this is i

23 'I now stable, so that as no rework would have to be required?

24 i' BY WITNESS FINNERAN:

25 l A I'm aware of no pressure to that point.

I k ALDERSON REPORTING COMPANY. INC.

- - , - w -

~

4972 9-9 1 The design engineers, when they discover a 2 condition that they don't like which was made to their 3 support in the field, they document what they want done to 4 correct it, send it out and we do it.

e 5 g I don't thin'k I really got the answer to my R

d 6 first question after. the break.

e R

$ 7 JUDGE MILLER: What was the question?

s 8 8 MR. WALSH: Does he know if it's a standard a

d

9 j procedure to make a modification to.a support without doing i

O .

$ 10 calculations? Standard procedures in the industry.

2

= .

j 11 WITNESS FINNERAN: I think I stated that 3

j 12 l depending on tne nature o: the change, we would indeed make 5 I .

t,,, g 13 l calculations before we make the change.

= t x -

5 I4 l BY MR. WALSH:

b  !.

=

5 15 l 4 But the question is, do other companies in the

=  !

j 16 l industry make changes without doing calculations?

M  !

N I7 To your knowledge?

5-E 18 BY WITNESS FINNERAN:

P g 19 , A To my knowledge --

I couldn't answer the n

20 question based upon my knowledge.

21 4 How about you, Mr. S cheppele ?

I 22 - BY WITNESS SCHEPPELE:

i 23 A I don't know, quite frankly. Although I think 24 i there could be a judgment made and that is, when you do i

l '

25 ) ge t involved in any extensive structural changes, I think i.

i ALDERSON REPORTING COMPANY. INC.

'4973 9-10

. , 1  ! it's very difficult to render purely a judgment in the 2 i field without doing something in the way of calculations.

3 0 Thank you.

4 How about you, Mr. Reedy?

e 5 BY WITNESS REEDY:

E a

6 A From my e xperience, I know of a number of R

2 7 cases where it could be possible that slight modifications A

j 8 would be made, telephoned back to the engineers, ask for d

9 calculations of verifications, for a verbal okay with I

$ 10 calculations, to proceed.

z

I j

m 11 This is based on eng.ineering judgment.

y 12 In other words-, if someone asked me if it were f: ~ 13 permissable to put a clip in a certain location, just by I

m -

5 14 describing that, reviewing the drawing, I could answer that i

2 15 , without making calculations and follow up on calculations 6

- i, J 16l e ,

later. And, yes, that is standard. That is done.

l y" 17 l I would say a significant change, however, -he-e i

I E 18 l would probably do calculations n

- I 19 3

n 0 Would removing a clamp around.aa pipe and boxing 20 it in, as s hown ca +0, be considered a significant change?

i 21 BY WITNESS REEDY:

22 A I'm sorry. I don't have the drawing you are i

23 i referring to.

i 24 l (Document handed to witness.)

l 25 Now, wculd you ask me the question?

,1 ALDERSON REPORTING COMPANY. INC.

g_11 l 4974 I I

i i

  • 1I i C If a field engineer removed a clamp that was 2i attached to the pipe and put this frame up, w 'ould this be 3 i considered a significant change?

4 BY WITNESS REEDY:

3 5 A N I In my mind it's a significant change.

e 3 0 l 4 Thank you.

E  !

6 7 BY WITNESS REEDY:

[ 8 ,

A However, I would like to point out that this d I

" 9 z

from your description of removing a clamp and putting O I

' 10 j

=

on this type of framework around, is,a much more conservativ:

3 11 l answer. So, I think, again, that you might be able no

- I f 12

. = <

approve this type of change and make your calculations 13 I g l to- verify it.

m i

= 14 d

w As long as you're going in a more conservative E IS '

g way and not harming the situation.

T j 16 l C i

Mr. Reedyi-Mr. Finneran has already said that H 17 '

y this unstable. Do you disagree with.him?

n

  • 18 l

_ BY WITNESS REEDY:

19 i l A Stablility depends on direction of load. It

" I 20 ! depends on the loads themselves.

i i

It depends on the adjacent 21 1 j support. It depends on a.. number o f things .

i It appears to me, from a glance, that for a 23 '

vertical upward load, this is unstable.

24 !

I don't know that it is designed to accomodate 25 that type of load, however.

H h ALDERSON REPORTING COMPANY. INC.

~'

9-12 4975

, 1 g The load sheet is on the following page.

2 Is that support stable?

3 MS. ELLIS: That would be on Page GP.

4 WITNESS REEDY: Again, Mr. Walsh, if I can --

I e

5iI and I don't have the concept --

I don't have the whole H i j 6I piping design system with me --

this does not appear capable R

b 7 of taking a vertical upward load.

3

$ 8 B Y MR. WALSH:

d n; 9 Thank you. ~

3 5 10 BY WITNESS REEDY:

E E

II A I do not know the full condition of loading.

E

=

12 l I haven't looked at the design of the piping system. It's 13 an iterative process.

A 1-4 g Mr. Finneran, you said the field engineering f

e 2

w 15 group makes the modifications; is that correct?

=

j 16 l BY WITNESS FINNERAN:

i i 17 i A That's correct.

E t

t G

18 l .

4 You said that their qualif$ cation -- did you

[

a 19 , ever state what_theirl.q alifications would have to be?

20 i BY WITNESS FINNERAN:

i 21 l A Well, I think I did state in part of answer 22 earlier that this group is staffed by some engineers and 23 by some technicians with experience with pipe supports.

24 j g Mr. Finneran, how many in that group are 25 engineers, at a percent?

I i

i ALDERSON REPORTING COMPANY. INC.

. D o

4976.

9-13 1 BY WITNESS FINNERAN:

2 A I couldn't guess. I know they have some 3 engineers in the group and I couldn't guess the percentage.

4 G Half?

g 5 MR. REYNOLDS: Objection.

?.

j 6 WITNESS.EINNERAN: No.

g

! R 7 JUDGE MILLER: Sustained.

. T.

j 8 BY MR. WALSH:

d

= 9 G Are there any. registered professional engineers

?,

$ 10 in that group?

E

]

11 3Y WITNESS FINNERAN:

3 12 A

$ *I don't know.

E 5 13 jl G Do the technicians do any of the calculations?

l
n g 14 :l He said there were engineers and echnicians

_t:

j= 15 in the group and I was wondering if the technicians did the y 16 calculations.

^ l x

I7 '

BY WITNESS FINNERAN:

l t

=.

L m 18 A I think the technicians do some of the more t

in g l9 , simpler calculations. If /a ;more complicat&d. calculation-20 l is required on a support, very often they will go to an i

2I engineer.

22 ' C Mr. Finneran, on the bottom of Page 42, under I

i 23 ' the approval, draw and check and revision.section of-that d

24 drawing, it's in the lefthand bottom left corner.

25 , This appears to be an approved drawing.

1 ALDERSON REPORTING COMPANY. INC.

. ,.j

.

  • i 4977

- I 1 What is the significance of that and why isn't 4-14 2 there a date there?

3 i BY WITNESS FINNERAN:

I 4 A I really don't have enough knowledge to answer s 5 '

that. This cycle of approving a drawing, I believe, is 2

j 6 a drafting cycle only. I believe each of these blocks, R

$ 7 I believe, are just drafting personnel.

j 8

4 Does that mean engineering has not approved d .

=; 9 this drawing?

3 E 10 BY WITNESS FINNERAN:

i l

11 A To the best of my knowledge, this is just a

~

{ 12 l drafting approval cycle.

,s 13 4 Mr. Scheppele, is th a t- the standard Gibbs and n

5 14 l Hill uses, of having the draftsmen approve the drawings?

i

=

E 15 l MR. REYNOLDS: Objection. This is a Brown &

6 l

16 Root document. The question is irrelevant.

d 17 l Jt*DGE MILLER: Overruled.

N

~

g 18l l .

WITNESS SCHEPPELE: I would say as far as c

{

5 19 Gibbs and Hill's standard practice of producing the kinds 20 : of drawings that we produce, and I don't put pipe supports l

I 21 ! necessarily in this, we would have the drawings approved i

1 22 normally by an engineer.

23 BY MR. WALSH:

24 ! O Mr. Finneran, should Class 1 pipe supports be 1

25 approved by an engineer or a draftsman?

i ALDERSON REPORTING COMPANY. INC.

~ . - ._, _

4975I 9-15 1 BY WITNESS FINNERAN: .

2 A I think Class 1 pipe supports should be

. 3 approved by an engineer.

4 4 Is that stated on the drawings?

e 5 BY WITNESS FINNERAN:

R 3 6 A I don't see it as stated on the drawings.

R b 7

% Is it mated in any procedure that engineers j 8 will approve the drawings?

d" 9

2

~. BY WITNESS FINNERAN:

-C 10

'j A Until the design is complete and approved by

!. II engineering, the drawing is not released for construction.

i f 32 I 4 Isn't this built?

13 g j BY WITNESS FINNERAN:

E 14 5 A This approval cycle on this drawing only n '

r 15 g indicates, as I stated earlier, that all field changes have 16 l been incorporated into the drawing by the draftsmen.

p 17 i a Therefore, this approval does not necessarily i

E 18 mean engineering. approval; correct?

g 19 BY WITNESS FINNERAN:

n l 20 A That's correct.

l Just partic'ular approval h'ere.

2I : 0 Is that true on che Class 1, also?

I 22 l BY WITNESS FINNERAN:

I 23 A I don't have the answer to your question.

24 S Do you know of any procedures that would 15; establish the approval cycle for drawings?

I ALDERSON REPORTING COMP ANY. INC.

I 1

s 4379 I <

BY WITNESS FINNE?lAN:

. 9-16 1, 2 A Well, I think you have to get into how the 3 . drawings are handled at the site, to understand that 4 what this drawing here represents.

e 5 Is it 0 a standard practice within the industry 9 I j 6 to __

R^

S 7 MR. REYNOLDS: Were you finished with your ei j 8 question, sir? I mean, your answer?

d 2

, 9l WITNESS FINNERAN: No, I wasn't.

E l 5 10 MR. REYNOLDS: May the witness finish his answer, E

@ 11 l Mr. Chairman?

N 12 JUDGE MILLL'R: Yes. If he has more to say, g 13 he may finish.

14 WITNESS FINNERAN: Well, the process of the d I

=

2 15 drawing- and how it's used at Comanche Peak to install pipe w

=

g 16 j supports, is a very complicated one.

m  :

M 17 ) JUDGE MILLER: Well, wait a minute, now.

x  :

= -l

$ 18 ! This is getting non-responsive.

3 19 j WITNESS FINNERAN: Well, he's:asking- questions n l l

20 l about --

I 21 l JUDGE MILLER: If you know of any procedure, I 22 think was the question.

23l WITNESS FINNERAN: Okay.

24 JUDGE MILLER: Do you know of -- the first 25 thing, answer yes or no, if you know of.

1 I

l ALDERSON REPORTING COMPANY. INC.

i 4

j 4980 I

9-17 1 {. WITNESS FINNERAN: Could I hear the question 2 again? ,

3 BY MR. WALSH:

4 4 Do you know of any procedures for approving 5 the drawings at Comanche Peak?

A j 6 BY WITNESS FINNERAN:

??

$ 7 A.

Yes, there are procedures for approving drawings j 8 at Comanche Peak.

d 9

. 4 Do you know how their approval cycle is?

?

10 g BY WITNESS FINNERAN:

=

=

! II I

A. In soma cases I do. - -

E" 12 l 4 What are they?

13 - .

E i

i E

ii 14l' 5 / / /

15 id c

N l

" i i 17 N'

5 18l I'

i C 19 l

/

20

! 21 22 I

23 '

1 24 I

l ALDERSON REPORTING COMPANY, INC.

t 4981 l

0-1 1  ! BY WITNESS FINNERAN:

e ,

2 l A From my own organization, I can answer it in 3

how we --

4 0 How do you do that?

s 5 i BY WITNESS FINNERAN:

l 3 6 A Could I ask Mr. Chang to answer one paru of l

u I g 7 i that?

j 8 g No. Since you are the supervisor within the j

d

9 PSE group --

2 0

$ 10 JUDGE MILLER: Well, he's asking you. If you 3

h t

11 i

caa't,' you may so indicate; but if you can, you should '

E 12 'I tell us what you can tell us.

4 I g 13 l WITNESS FINNERAN : Well --

= i w

j y

I'4 JUDGE MILLER: If you can ' t, it's all righ

15 h to tell us.that - x you don't have any information.

=

E Ib ! WITNESS FINNERAN: Well, in PSE drawings, as M l 3

17 l '

far as sign-off on the drawings by the engineer, Mr. Chang E 18 i

_ could answer that question better than I could.

E 19 l M BY MR. WALSH:

20 G All right.

21 BY WITNESS CHANG:

22 i A Okay. For PSE, which means unsigned original 1

i i

design, basically the small boreapiping, we'do'. original, i

24 i i design.on site.

25 '

'That approval on the drawing for small bore is I

! ALDERSON REPORTING COMPANY, INC.

1

' I

> l

. 498.2 L. -

3-2 ii concerned is engineer approval, which usually is on the I

2 approval list, on the QA list, and is at supervisor level, 3 whether drawing, checking or drafting.

4 G Are you stating that there are two different e 5l procedures being used out at Comanche Peak , one group 5 l j 6! having engineers' approved drawings, and another group R

$ 7l draftsmen approving drawings?

s j 8 MR. REYNOLDS: It's argumentative, Mr. Chairman, d

d 9 JUDGE MILLER: Well, let's find out. I don't

@ 10 know what he's arguing..

E 11 Are there two different me thods ?

.h .

8  !

d 12 l WITNESS CHANG: No. I think Mr. Finneran =ight E I g 13 ! be referring to something else. There is a PSE,

= \

  • h 5 14 lI original design on site, which is only one procedure.

2 f 15 BY MR. WALSH:

a

=

  • i g 16 G Is this drawing generated at Comanche Peak, e

N 17 i Mr. Finneran?

E i e i g 18 l JUDGE MILLER: What is "this" drawing?

"s 19ll MR. WALSE: Excuse me. It's 4-0.

5 I

20 l WITNESS FINNERAN: This drawing is generated 21 from a drawing that is issued to the site by the original 22 l designer.

23 ' I believe that drawing by the original designer 24 Ii is approved by the engineer.

i

! //

i l

1 ALDERSON REPORTING COMPANY. INC.

I 4963 0,- 3 , 1l BY MR. WALSH:

I 2' O The approval on this drawing that's shown on 3 4-P, you said that approval is of a draftsman and not an i

4 l engineer.

i 1

3 5' Is.that in conflict with what Dr. Chang has E

j 6, just said?

R

& 7 BY WITNESS FINNERAN :

M j 8 A No, I don ' t think so.

d

[ 9 g Didn't he just say --

I

$ 10 JUDGE MILLER: Well, wait a minute. Let him I

h 11 j explain.

a  !

12 ll WITNESS FINNERAN: This is not a PSE 5

. g 13 l design. Dr. Chang just answered for the case of a PSE

=

x 5 14 design.

b j 15 ,i JUDGE MILLER: Yes, I think that's it.

=

j 16 MR. WALSH; Okay.

m N I7 BY MR. WALSH:

l 5 I l

g 18 :l 4 So PSE engineers approve the drawings, and

I 8

g I 9 li for this particular drawing on 4-0 and 4-P a draftsman n l 20 l approves the drawing; is that correct?

21 37 g;73333 7 333333 22 li A Well, I'm not clear as to who signed this 23 approval block on this drawing. The original issue of 24 I I the drawing, the approval block would have been signed by 25

! an engineer.

ALDERSON REPORTING COMPANY. INC.

4

6- .

i 49S4 0-4 i l It's a very cEmplicated process.

I 2 0 How do you know that an engineer --

3 MR. REYNOLDS : Mr. Chairman, the witness is 4 lheinginterruptedinhisanswers.

e 5 JUDGE MILLER: We'll strike that remark. The M

K j 6 witness may complete his response.

R

$ 7 WITNESS FINNERAN: The original pipe support j 8 drawing, to the best of my knowledge, is released by e

n 9 the original designer, which we call the vendor designer.

i o

y 10 It would have been issued to the site.

E

)s 11 The site would have turned that drawing into '

f 12 I what we call a 3RE, which is the drawing that's used to

~

s 13 install the support in the field. It 's bas ically"the a

n 5 I4 same drawing.

a s' i g 15 ' It's just for the -- see this Brown & Root

=

j 16 designation on the drawing?

= l .

. U 17 i 3Y MR. WALSH:

1 E l c 18 3 G Yes.

C g 19 l BY WITNESS FINNERAN:

20 ll A They just paste that over the ITT designation 2I on the drawing.

3 22 4 So what is the significance of the approval on Rev. 3?

24 37 g;73333 3 333,y3, i

I n5

' t-1 A On Rev. O of that drawing it would be the l

l l  !

ALDERSON REPORTING COMPANY. INC.

p 4985 9-5 1 original design organization.

2 4 Yeah, but haven't modifications been 3 incorporated on that drawing, and then indicated as 4 approved by a draftsman now, on Rev. 3?

e 5 BY WITNESS FINNERAN:

N j 6, A I can't answer that question very clearly. I R

^

t 7 really would have to confer with the draf ting organization j 8 to see who exactly signed that approval block, d

9 4 So you are saying the Draftsman Department did I

@ 10 z sign,that part, correct?

=

i

' jj i .

E l BY WITNESS FINNERAN:

a 32 A I

=

I don't know. I was 6nder the impression chat

. 13 they did approve that.

E 14 E G Then there is a possibility that on MPSI or E

15 b ITT drawings, an engineer may not have signed off, correct?

a 16 s

m BY WITNESS FINNERAN:

C 1:7'!

y A No, I do,n ' t think so. On a drawing that would-E 18

= be used for construction, I don't think that's possible.

9-19 3

n 4 How about the revisions?

20 BY WITNESS FINNERAN:

21 A No, I don't think so. You have to realize that 22 j the CMC's that =ay have been incorporated in this drawing 23 l' were approved by engineering personnel.

' 24 l l I might point out that after the final review 3

25 ' of these drawings, they are stamped and signed by an l

! l ALDERSON REPORTING COMPANY. INC. .

6170

?M i 8m i UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION-3 DEFORE THE ATOMIC SAFETY & LICENSING BOARD J


-----x In the matter of: ,.

TEXAS UTILITIES GENERATING  :

COMPANY, et al.

7  : Docket Nos. [0-445 20-446 ,

6 (Comancho Peak Steam  :

Electric Station, Units 1 and 2)  :

  • i 4  !

.e k <

, :t Roon 5814 ,

{

  • The Frit: Lanham Buildinc t i 819 Taylor Street

." ort Worth, Texas

,' l i 2 l Tuesday, May 17, 1983 N

The hearing in the above-entitled 4

' .a t cr convene :, e I

i pursuant to notice, at 9:00 a.m.

BEFORE: I i

18  :

JUDGE PETER BLOCH I 4

i

.* Chairman, Atomic Safety & Licensina Board i

.o JUDGE KENNETH MC COLLOM Member, Atomic Safety & Licensino Board

'I ,

L JUDGE WALTER JORDAN  !

Member, Atomic Safety & Licensinc Soard 23 2.s 1

25 k

i i

i 1

i

~ -_ - . - . . . ---- - _ - -_ , - - .- - _ _ _ , _ _ _ . _ - _

4

a6' -6403 i

l gr' '

    • 3

[ MR. MIZUNO: I have a few additional direct 2

questions before turning them over for cross-examination.

3 JUDGC BLOCH: Please proceed.

SY MR. MIZUNO:

j 5 G Mr. Taylor, on page 7 of the SIT report, the 6

SIT indicates that of the 19 broad concerns raised by i

7 Messrs. Walsh and Doyle, 6 specific items of these concerns l.

s were id.entified and are being or have been corrected

}

by the Apolicants.

s

! I'I 1 (WITNESS TAYLOR) That's correct.

j G Por,these 6 items, could you briefly describe i'

j the fundamental source of these design *!eficiencies?

J 1

' t

'3

, A (WITUCSS TAYLOR) The source of these design i

"l  !

deficiencies?

1 f A somewhat inexperienccd cnaineering staff.

'O

JUDGC MC COLLOM
l t

14 hat was that? >

'7 JUDGE BLOCH: A somcwhat-- would the reporter i t I '8 repeat it instead of me.

MITMESS TAYLOR
A somewhat inexperienced l

eingineering staff.

JUDGE MC COLLOM
What does that mean? i WITNESS TAYLOR: It means that all engincors ,

i '

23 4

are not necessarily created equal, sir.

'a j JUDGE MC COLLO!1: Is that right?

25 WITMCSS TAYLOR: Not all equally competent.

) s

i r

l

}

.. *.. +

28-al 6406 N

I i

(7%

4 1

JUDGE BLOCH: Are these somewhat still un-

) 2 experienced engineers still involved in design work at l

the j 3 plant?

4 WITNESS TAYLOR: Yes. Much of the oricinal design 5

you have to understand, is really taking our theoretical or i o  !

hypothetical wall and a hypothetical pipe and trying to 7

a Connect the two, and that takes a lot of peoplc in the field t 11 of doing this.

  • l i

JUDGE BLOCll:

4 These are the peopic who are making  ;

to the field modifications'in order to got around interferences?

j 11 WITNESS TAYLOR: Yes, sir. I t

'?

J JUDGE BLOCH: Was this inexperience uniformly i 13 distributed  !

among the group, or was it particularly

'a l characteristic of some members?

I i

t5 WITNESS TAYLOR: I really can't an.swer that

- question, sir.

'7 The organization at my last knowledge was somewhere' a 18 around 225 or 250 people, and I really can't say

, D) what percentage of them are inexperienced or what percentage v

.of them might be relatively less competent.

! -, I-I would tend to believe that probably a very 22 small percentage.

23

-  !!aw do I arrive at that next conclusion, is the 2d 'next question.

25 JUDGE BLOCH:

l I No, it wasn't. '

~l e /

! p f

l i

, -. ,- - , _ . - . . . . . - - , _ - - - . , - , - . - ,- . . . . - - . , , , , _