ML20195E407

From kanterella
Jump to navigation Jump to search

Discusses 970522 Request That NRC Reconsider Conclusions in SE ,on EP Change 28.001.95 for Plant,Unit 1.Board Affirmation of Findings of NRC SE in EP Change 28.001-95 Decreased Effectiveness of Plan
ML20195E407
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 11/16/1998
From: Donohew J
NRC (Affiliation Not Assigned)
To: Eaton W
ENTERGY OPERATIONS, INC.
References
TAC-M99124, NUDOCS 9811180334
Download: ML20195E407 (5)


Text

- . _ . _ . _ _ . . . _ _ _ _ _ .

a..g l t UNITED STATES s*  ; NUCLEAR REGULATORY COMMISSION

. WASHINGTON, D.C. ace 86 00M j g

          • November 16, 1998 Mr. William A. Eaton -

Vice President, Operations GGNS Entergy Operations, Inc.

! P. O. Box 756 Port Gibson, MS 39150

SUBJECT:

APPEAL MEETING FOR EMERGENCY PLAN CHANGE 28.001-95 FOR GRAND GULF NUCLEAR STATION, UNIT 1 (TAC NO. M99124)

Dear Mr. Eaton:

i i

! In a letter dated May 22,1997 (GNRO-97/00048), Entergy Operations, Incorporated (the l licensee) requested that the Nuclear Regulatory Commission (NRC) reconsider its conclusions l In its Safety Evaluation (SE), dated December 11,1996, on Emergency Plan (EP) change

28.001.95 for the Grand Gulf Nuclear Station, Unit 1, (GGNS). The NRC staff concluded in the SE that change 28.001.95 decreased the effectiveness of the GGNS Emergency Plan, and, in l- accordance with 10 CFR 50.54(q), should not have been implemented without prior staff review and approval. This SE was transmitted to GGNS in a letter dated April 24,1997. The licensee's May 22,1997, letter also contained information to justify its position.

L The' NRC convened an appeal board (the Board) on July 10,1997, to hear the licensee's position to determine whether reconsideration was warranted; a summary of the Board meeting was issued on July 17,1997. In letters dated September 5, and December 9,1997 (GNRO-97/00086 and GNRO-97/00118, respectively), the licensee provided additional information to address issues raised by the Board and, subsequently thereafter, in response to staff concems.

l This transmits the Board's affirmation of the findings of the NRC safety evaluation in that EP change 28.001-95 decreased the effectiveness of the plan. The bases and the events leading up to this conclusion are described below.

l The Board meeting with the licensee revealed certain ambiguities in the staffing of the EP that the licensee addressed in its letters of September 5 and December 9,1997. These ambiguities

prevented the resolution of the technicalissues raised by the licensee in its letter of May 22, l 1997, and during the meeting of July 10,1997, and these issues were discussed at a meeting of the Board with the staff when the staff reported back to the Board on the letters of September 5 and December 9,1997. This Board-staff meeting focused on the technicalissues involving the use of technology to replace two (2) 30-minute health physics (HP) technician responders as described in the emergency plan. At that meeting, the Board requested that a l survey be made of the radiation protection and emergency preparedness staffs in headquarters and the regions to establish a consensus to determine whether the replacement of HP technicians by the use of technology in the early phase of an accident is an adequate attemative approach. The Board sought to determine whether technological advances and experience in the use of the technology were sufficient to warrant a change to the NRC position. The conclusion derived from that sun /ey is that the use of electronic dosimeters (EDs) and area radiation monitors (ARMS) cannot replace the two 30-minute HP technician I l

' g responders. In providing its position to the Board, the staff also evaluated the information ,

n

, e s P [.*;

9811180334 981116

[. .No h

. -(

. William A. Eaton 2 presented by the licensee to assure that the rationale used by the licensee was considered before the staff finalized its recommendation to the Board.

In its May 22,1997, letter, the licensee identified the following reasons for eliminating the two 30-minute HP technician responders:

. Automated access control

. On-shift personnel provide HP coverage

. Minimal HP involvement required for personnel monitoring

. Dosimetry self-issued by workers

. - Additional on-shift staff available for HP support.

Network of area radiation monitors Access control involves safety decisions to permit personnel into radiological areas, managing the activities of personnel in radiological areas, establishing control areas to prevent the spread of contamination, and providing appropriate dosimetry for personnel. Under normal plant operating conditions, access control may be automated because radiological conditicas are established before permitting personnel into a hazardous environment and conditions are monitored before releasing personnel. Issuing radiation work permits, establist ing barriers, step off pads, etc. are essential to an effective access control program; these s etivities require personnel even during normal operating conditions. Under accident conditions, where conditions may not be well established, HP staff are required to ensure that persannel are not subject to undue risk. Access controlis substantively more than just logging persennelinto radiological areas and providing dosimetrv Staffing was discussed in great depth with the licensee at the Board meeting and in subsequent phone calls; the licensee stated that the contingent of on-shift personnel exceeded minimum requirements. Nevertheless, the staff identified discrepancies in the emergency organization described in the GGNS EP. The staff determhed that a number of emergency workers were double-counted and given collateral responsibilities for handling several assignments simultaneously. The staffing scheme outlined in the emergency plan was confusing and ambiguous regarding the number of emergency responders; the licensee did not resolve this issue at the Board meeting. In subsequent discussions and in the submittals of September 5 and December 9,1997, the proposed licensee staffing-level changes were implemented and the staffing issues were resolved for the GGNS EP. The EP staffing levels in Table 5-1, EP shift staffing and augmentation capabilities, dated October 20,1997, that was submitted in the

~ December 9,1997, letter removed the double counting of emergency workers that had been incorporated in earlier versions of Table 5-1, and thus was an augmentation of previous staffing levels.

ARMS have been part of radiation protection programs for a long time and their use was

' considered when the minimum HP emergency organization staffing standard was developed initially. Recognition of the presence of these monitors does not provide a sufficient basis to

. Justify the reduction in the number of 30 minute HP technician responders. Unlike normal operations, where there is likely to be good correlation between ARMS and radiological conditions there may be an inappropriate reliance on ARMS under accidert conditions because

Wdliam A. Eaton 3 the magnitude and mix of radionuclides may be unknown and the spatial distribution of radioactive material may be highly variable.

The underlying principles associated with as low as is reasonably achievable (ALARA) for occupational exposure, even under accident conditions, would not permit workers to enter into a hazardous environment without recognition of the risk and an appropriate justification for worker exposure. The use of EDs to monitor and control radiation exposure provides additional advantages over thermoluminescent dosimeters and pocket dosimeters, however, EDs cannot 1 replace appropriate HP coverage where judgement is required for personnel safety. Only j recently have licensees relied on EDs as the primary dosimeter. Notwithstading improvements in the design, performance and fabrication of these devices, EDs have limitations. Reliance on EDs as the primary information source to preclude unnecessary worker exposure under accident conditions is not consistent with ALARA.

The licensee expected that there would be a human resource savings provided by workers obtaining their own dosimetry and performing their own monitoring as is evidenced under the current practice for normal operations. In addition to the foregoing discussion as the bases for the denial of reconsideration of the staff's conclusion in its SE dated December 11,1996, the licensee's practice in this specific area is a problem area. For example, in the letter dated October 9,1997, the Plant Support area of the latest SALP Report found a decrease in the SALP score from a "1" to a "2." The NRC noted that problems were identified in the radiation protection area: radiation workers were not wearing EDs and were not following established radiation protection procedures. These inspection findings alone do not advance the licensee's position that HPs are not needed because radiation workers can use electronic dosimeters and are trained in their use.

The Board affirms the findings of the NRC safety evaluation, issued to the licensee in the NRC letter dated April 24,1997, that EP change 28.001-95 decreased the effectiveness of the plan.

The Board considered the licensee's position outlined in its May 22,1997, letter and the representations made at the Board meeting on July 10,1997. The summary of the Board meeting dated July 17,1997, indicated that a limited number of issues required clarification to i be acceptable; the summary did not reflect the concern of the Board regarding the ambiguity in the emergency organization described in the cmergency plan and the assignment of collateral l duties. Nevertheless, in letters dated September 5, and December 9,1997, the licensee provided additional information to respond to the isst es covered in the summary of the meeting l and, subsequently thereafter, in response to staff cornerns. While the Board finds that i reconsideration of the staff's conclusion in its SE dateJ December 11,1996, is not warranted, it i is apparent to the Board that the licensee attempted to resolve the issues promptly and in good  !

faith. The Board has directed the staff to proceed with closure of this proceeding and '

disposition of findings; however, the Board is receptive to the reconsidernon by the licensee of l its EP staffing commitments in its correspondence dated September 5, and December 9,1997, l had the staffing commitments been made under the presumption that the licensee would have prevailed on its position or that the licensee would have prevailed on appeal.

In the absence of an action by the licensee to continue this matter, the Board plans to dissolve within 30 days of the date of this letter.

4

i e l William A. Eaton 4

, This closes out the appeal meeting and your appeal of the staff's decision in its letter of April 24,1997, on EP change 28.001-95. This also closes out TAC M99124 on the appeal l

meeting. If you have any questions, contact me at 301-415-1307, or by "JND@NRC. GOV" on l the intemet.

Sincerely, l

i 13 4 h id Jack N. Donohew, Senior Project Manager

! Project Directorate IV-1 Division of Reactor Projects lil/IV Office of Nuclear Reactor Regulation Docket No. 50-416 i

cc: See next page l

l l

4 l

William A. Eaton 4 This closes out the appeal meeting and your appeal of the staff's decision in its letter of April 24,1997, on EP change 28.001-95. This also closes out TAC M99124 on the appeal meeting. If you have any questions, contact me at 301-415-1307, or by "JND@NRC. GOV" on the internet.

Sincerely, 1

N ND Jack N. Donohew, Senior Project Manager Project Directorate IV-1 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation Docket No. 50-416 cc: See next page DISTRIBUTION:

DechetfUi] PUBLIC PD4-1 r/f E. Adensam (EGA1) J.Donohew T. Gwynn, RIV ACRS OGC (15B18) C.Hawes J.Hannon C. Miller B. Zaleman L. Cohen J. Roe B. Murray, RIV Document Name: GG99124. APP *SEE PREVIOUS CONQURRENCE OFC PM/kD4h LA/PD4-1' BC/PERB* RIV\PSB D/ OS[ DD/DRPM NAME JDdeN CHaN CMiller SkuNaf JHannon f Jh DATE 19Y/98 /0/ k /98 10/07/98 II 2/ /98 h/N/98 ) h /98 II/ /98 COPY YES/NO YES/NO YES/NO - YES/NON YES/NO YES/NO OFFICIAL RECORD COPY q e-ns 6h llf 2- fd N

1

, ,.7 __._ _ .

i .

I l- Mr.' William A. Eaton

! Entergy Operations, Inc. Grand Gulf Nuclear Station cc:

Executive Vice President General Manager, GGNS

& Chief Operating Officer Entergy Operations, Inc.

Entergy Operations, Inc. P. O. Box 756 -

P. O. Box 31995 Port Gibson, MS 39150
Jackson, MS 39286-1995 Attorney General L Wise, Carter, Child & Caraway Department of Justice L P. O. Box 651 State of Louisiana Jackson, MS 39205 P. O. Box 94005 Baton Rouge, LA 70804-9005 Winston & Strawn 1400 L Street, N.W. - 12th Floor State Health Officer  ;

l Washington, DC 20005-3502 State Board of Health P. O. Box 1700 Director Jackson, MS 39205 Division of Solid Waste Management Mississippi Department of Natural Office of the Govemor Resources State of Mississippi P. O. Box 10385 Jackson, MS 39201 Jackson, MS 39209 Attomey General l: Fresident, Asst. Attorney General l Claibome County Board of Supervisors State of Mississippi P. O. Box 339 P. O. Box 22947 Port Gibson, MS 39150 Jackson, MS 39225 Regional Administrator, Region IV Vice President, Operations Support l U.S. Nuclear Regulatory Commission Entergy Operations, Inc.

611 Ryan Plaza Drive, Suite 1000 P.O. Box 31995 Arlington,TX 76011 Jackson, MS 39286-1995 Senior Resident inspector Director, Nuclear Safety U. S. Nuclear Regulatory Commission and Regulatory Affairs l P. O. Box 399 Entergy Operations, Inc.

Port Gibson, MS 39150 P.O. Box 756 l- Port Gibson, MS 39150 i

l l

l i

i

. - -- . ..