ML20116N804

From kanterella
Jump to navigation Jump to search
Forwards Addl Safety Issues Requiring Resolution Prior to TMI-1 Restart.More Items Requiring Resolution Prior to Commission Vote on Restart Exist than Identified in 850417 Presentation.Issues Purportedly Settled Unclear
ML20116N804
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 05/03/1985
From: Pollard R, Weiss E
UNION OF CONCERNED SCIENTISTS
To: Asselstine J, Palladino N, Roberts T
NRC COMMISSION (OCM)
References
CON-#285-871, RTR-NUREG-0737, RTR-NUREG-737, TASK-2.D.1, TASK-TM SP, NUDOCS 8505070356
Download: ML20116N804 (16)


Text

sal ,

DOCKET NUMBER x. g g -

UNION OF "" " " " ' ~=

CONCERNED .. ..

SCIENTISTS me ce..mie.t i. ..e. s.w. . s. >>oi . wa.si..te . Dc 20o36. <2o2> 296-seoo DCLKETED USNRC May 3, 1985

'85 MM-6 All :53 Nunzio J. Palladino, Chairman Thomas M. Roberts, Comissioner GFflCE OF SEtat I;J r James K. Asselstine, Comissioner Frederick M. Bernthal, Comissioner 00CKEi g EPv!Ci Lando W. Zech, Comissioner U. S. Nuclear Regulatory Comission Washington, D. C. 20555 Gentlemen: ~

On April 17, 1985, the NRC staff briefed the Comission on the status of Three Mile Island Unit 1 (1MI-1) in preparation for a restart vote. UCS's coments the following day on the staff's presentation were limited to the subject of the steam generators. We are writing now to address other subjects because the staff's presentation was not complete.

Specifically, the staff's presentation failed to inform you of the following:

~

1. Some " lessons learned" items (NUREG-0737 items) previously certified by the staff to be complete are, due to new information, no longer complete;
2. Some conditions of the 1MI-1 plant do not conform with the conditions described in sworn testimony during the restart proceeding which were relied upon by the Licensing Board and Appeal Board in deciding contested issues in favor of restart; and
3. Many of the new 1MI-1 technical specifications proposed by GPU and  !

approved by the staff effectively reverse Licensing Board and Appeal Board  !

findings that certain equipment is necessary to protect public health and i safety by permitting ope ation of IMI-1 with that equipment inoperable.

Specific examples of each of these safety deficiencies are described in detail in the attachment to this letter. A brief starnary of thwse examples follows.

1.a. A lessons learned requirement was that the pressurizer safety valves be tested to demonstrate acceptable performance under accident conditions.

Aftee tests were brought to the Appeal Board's attention showing tha", incor-rect valve adjustments caused valve damage and inadequate relief capacity, GPU comitted to specific valve settings that had been shown to produce acceptable valve performance. The issue was largely resolved on this basis.

However, GPU later chavd the settings, as discoverd by an NRC inspector. Doctanenta-tion that purportedly supports the new settings is dated in early 1984 but was not scheduled to be submitted by GPU until March 31, 1985. UCS has not received that information or the staff's evaluation of it.

B505070356 850503 -

! PDR ADOCK 05000289 '

( O PDR '

I Mai. Office: 26 Church Street . Cambridge Massachusetts 02238 . (617) 547 5552  ;

i

.- . _ , -. ---- O

}

' 1 1.b. Se MI-2 accident demonstrated that additional instrumentation to ,

detect inadequate core cooling was required. he incore thermocouples are '

part of that instrumentation and a lessons learned requirement was that the incore thermocouple instrumentation must be environmentally qualified. GPU informed the staff that environmental qualification has not been established,

' testing -is underway, efforts to procure replacement equipment are being pur-sued concurrently, and if replacement is necessary, procurement and installa-tion will take 40 weeks. On March 29, 1985, the staff approved GPU's request for extension of the March 31, 1985 environmental qualification deadline on the basis that the hot leg. temperature detectors (which provide . an input signal to the subcooling margin meters) are an adequate substitute for the incore thermocouples. However, it was apparently overlooked that the hot leg temperature instrtments can not be used unless the reactor coolant pumps are running, which they will not be in certain accident conditions. In addition, the TMI-1 technical specifications permit plant operation with the subcooling margin instrtmentation inoperable on the basis that the incore thermocouples are an adequate substitute.

2. Another lesson learned requirement was that provisions to supply emergency electr.ical power to the presurizer heaters must be made without degrading the capacity, capability or reliablility of the onsite emergency power supply. The boards found the 1NI-1 provisions to be acceptable in large part on the basis that two conditions would be satisfied: a) the heaters would not be connected until the load on the emergency power supply was stabilized; and b) that the undervoltage trip used to disconnect the heaters to protect

! the power supply from a failure in the heater circuits would be set at a I

specified voltage and time delay. GPU has since changed the setpoints for both the voltage and time delay on the basis that starting of motors on the emergency power supply would result in tripping the heaters. Bis indicates that the heaters .will be connected without first stabilizing the load on the power supply. The staff is aware of this situation but has taken no action other than to classify it as a " closed item."

3. A principal purpose of the restart proceeding was to decide, in view of the TMI-2 accident, what new safety equipment was necessary and sufficient to protect the health and safety of the public during operation of TMI-1.

hat process has been completely frustrated by the approval of technical specifications that permit operation of MI-1 with equipment inoperable which the boards found was necessary to protect the public. For example, the-following new safety equipment falls in this category: subcooling margin instrumentation, position indication for the pressurizer PORV and safety ,

valves, emergency feedwater system flow instruments, and reactor coolant system high point vents.

UCS believes that the Comnission should take the following actions:

1-

1. Direct the staff to identify any additional " lessons learned" require-ments or other items that the staff has certified to the Conenssion as complete but which are no longer complete.

' 2. Direct the staff to identify any additional instances where the present status of TMI-1 does not conform with the GPU commitment and/or board-imposed license condition that .was relied upon in the adjudicatory decisions favorable to restart.

I - .

3-For items 1. and 2. above, the staff should also be directed to propose a method and schedule for resolving each safety issue identified, giving due consideration to the rights of the other parties.

3. Direct the staff to review the MI-1 technical specifications and amend them as necessary to require, as " limiting conditions for operation,"

the operability of all equipment relied upon by the boards as a basis for decision that TMI-1 can be operated without endangering the health and safety of the public. In addition, the staff should be directed to serve the parties with a complete set of the amended technical specifications and solicit the I parties' coments on whether the amended technical specifications contain all such required limiting conditions for operation.

In sum, UCS believes that there are more items requiring resolution prior to a Commission vote on restart than were identified by the staff in its April 17, 1985 presentation to the Comission. We anticipate the charge that these questions are being raised at the last minute. On the contrary, these are not new questions. They are issues which were purportedly settled during the restart proceedings. but which have became unraveled by either inadvertent or intentional lack of attention to the conditions of restart imposed by or implicit.in the ASLB and Appeal Board decisions.

Sincerely, Robert D. Pollard Nuclear Safety Engineer s

J Ellyn . Weiss General Counsel encl: Additional Safety Issues Requiring i

Resolution Prior To TMI-1 Restart ec: 1NI-1 Service List l

k

+ w

  • _,--.-,-%,. -_,.p.-e,-. , w. -my. ,v-. ,, 1-,,#-,.- ,,-.-rm -

-- ,----__.,m .

~d~ f ADDITIONAL SAFETY ISSUES REQUIRING RESOLUTION PRIOR TO TMI-1 RESTART -

Union of Concerned Scientists DOCKSTE1D USNRC May 3, 1985

'85 MAY-6 Aji:53

1. " Lessons Learned" Requirements That Are Incomplete 0FF;CE CF SECREi ry
a. NUREG-0737. Item II.D.1, Performance Testing of Boiling-WaYe^r Ya'68![<jEf'" 15 Pressurized-Water Reactor Relief and Safety Valves ( NUREdf0'578, Section 2.1.2)

One of the lessons learned requirements was that reactor coolant system safety valves had to be tested under the full range of expected operating con-ditions for design basis transients and accidents, which would include solid-water and two-phase flow conditions. [Ref. 1.] As discussed below, data from testing Dresser Industry safety valves, including the specific model used as pressurizer safety valves at IMI-1, showed that certain plant modifications and adjustments 1/ to the safety valves were necessary to prevent valve chatter that could reduce relief capacity and damage the valve internals. GPU commit-ted to these changes, which were relied upon by the Appeal Board to resolve the issue. Recent information indicates that GPU will not utilize the valve settings relied on by the Board.

1/ These adjustments are called ring settings. Although there is some inter-action between the three separate ring ~ settings, the principal effect of each ring setting 'is as follows: the lower ring setting affects the rate at which the valve opens and adjusts " accumulation," the pressure above the preset opening pressure at which the valve is fully open; the middle ring adjusts " blowdown," the pressure below the opening pressure, at which the valve is fully reclosed; the upper ring setting is used to compensate for the effects of backpressure downstream of the valve. Accumulation and blowdown are generally expressed as a percentage of the pressure setpoint.

For example, a safety valve ' set to open at 2500 psi with 3% accumulation I

and 105 blowdown should open at 2500 psi, be fully open at 2575 psi and reclose at 2250 psi. [Ref. 2.]

i l

l k.

p 9

'B&W provided the following evaluation of the results from the testing performed on the safety valves:

Recent review of the EPRI test data indicate that for certain combinations of lower and middle ring settings the safety valves could chatter (rapid cycle valve opening and closing).

Two consequences of valve chattering have been noted during valve testing: a reduction in safety valve capability to relieve pressure while chattering and subsequent damage to valve internals. During the EPRI tests, this chattering phenomenon was noted only with valves with long inlet piping configurations. However, present understanding of the effect of ring settings on valve operation indicates that even with the valves mounted directly on the pressurizer nozzles, valve chatter could' be postulated for a combination of ring settings significantly different from those.used during the EPRI tests.

[Ref. 3.]

During the restart hearings conducted by the Licensing Board, UCS assert-ed, inter alia, that appropriate qualification testing of the safety valves had not been performed to ve*ify the capability of these valves to function during normal, transient, and accident conditions. [Ref. 4.] In resolving this question, the Licensing Board found that a valve testing program being conducted by the Electric Power Research Institute (EPRI) was adequate to reveal any design deficiencies in the safety ~ valves used at THI-1. [Ref. 5.]

This subject was revisited during the reopened hearings held by the ,

Appeal Board in March 1983. GPU testified that as a result of the EPRI tests

"[t]he safety valves were shown to be acceptable under all modes of operation after certain modifications were made." [Ref. 6.] The modifications which GPU testified were necessary in order to assure acceptable safety valve perform-ance were to change "the safety valve inlet piping from a. long inlet to a short inlet arrangement" [Ref. 7.], and to readjust the safety valve ring set-tings to "the final EPRI ring settings which we used in the last five tests."

[Ref. 8.] GPU's commitment to the latter modification has been abandoned.

. o During an NRC inspection of INI-1 conducted on January 21-24, 1985 (but not reported until March 18, 1985), the inspector noted that GPU had changed the safety valve ring settings. CPU furnished the inspector with documenta-tion from B&W dated in February and May of 1984 that purportedly supports the revised ring settings. However, the inspector concluded that since the staff's safety evaluation report had been based on the earlier ring settings, 4 there was a need to inform the Office of Nuclear Reactor Regulation (NRR) of the details. GPU representatives agreed "and committed to furnish the ring setting information to NRR by 3/31/85." [Ref. 9.] To date, UCS has not received that information or any staff evaluation of it.

UCS believes that this safety issue must be resolved before restart. The safety significance of the ring settings for the pressurizer safety valves is

} illustrated by the fact that after reviewing their safety valve ring settings 4 against the EPRI test results, Duke Power Company declared the safety valves inoperable and shut down Oconee Unit 2. [Ref. 10.] The Oconee plants and IMI-1 utilize the same model of Dresser safety valves. [Ref. 11.] Further-more, as discussed above, incorrect ring settings can result in ina(>quate relief capacity and damage to the safety valves. Since the staff claims that the " limiting transient" for THI-1 is a subcritical rod withdrawal [Ref. 12.]

and such an accident could occur early in the restart process, resolution of this safety issue can not be postponed until after restart.

b. NUREG-0737, Item II.F.2, Attachment 1, Design and Qualification

! Criteria for Pressurized-Water Reactor Incore Thermocouples.

, One of the " lessons learned" requirements was that additional instrumen-tation was needed for detection of inadequate core cooling. One requirement ~

applicable to incore thermocouples that measure core exit temperatures was that "[t]he instrumentation should be. environmentally qualified . . . . " [Ref.

! 13.]

1 1

j A GPU submittal to the staff dated May 20, 1983 stated that no extension of the March 31, 1985 deadline in 10 CFR 50.59 for environmental qualification of electrical equipment would be needed. In a submittal dated December 11, l 1984, GPU " identified nine (9) items of equipment that w m not qualified,"

including-the incore thermocouple instrumentation.-[Ref. 14'] On February 12, 1985, GPU applied for an extension of the deadline for qualifying the thermo-l I

couples. GPU gave as its " reason for scheduler (sic] extension" the following:

. Qualification testing of the existing.. cables and connectors is planned to be complete in April 1985 based on vendor bids.

~The final report is due out in May 1985. Pending the outcome

! of the testing, replacement may be necessary.- GPUN is pro-

!' ceeding in a parallel path with the testing to procure -

environmentally qualified replacement cables . . . .

[Ref. 15.]

GPU offered as a "JIO" (Justification for Interim Operation)- the asser-i tion that "[t]he safety function (of the incore thermocsuple instrumentation]

can be accomplished by alternate' qualified instrumentation with existing 4 procedural guidance." -[Ref. 16.] GPU asserted that the hot leg resistance i temperature detectors (RTDs) are the " alternate qualified instrumentation" to be used in determining the' subcooling margin of the reactor coolant system.

l However, GPU also correctly informed the staff, albeit in a _ footnote, that

"[wlith reactor coolant pumps _ running, the ' subcooling . margin is calculated

. from the hot les RTDs. If the RCPs are off, the subcooling - margin is calcu--

i-lated from the incore thermocouples." [Ref.17.]

l 2/ Previously, such information has been ' termed a "JC0" (Justification for-Continued Operation). The criteria _ for an . acceptable justification for equipment not shown to be qualified require, inter alia, either a) the equipment would perform its function before failing or b) there is other

-redundant, qualified safety-grade equipment. avsilable to perform the same safety function.

. . . . . . - . . _ . - - . - . . . =- _ ..

2 . . .

. The staff appears to have overlooked GPU's footnote. In a letter to GPU t dated March 29, 1985,1 the staff stated that "[w]e have reviewed the JI0s and conclude that they are sufficient to support operation during the requested i

extension period," and granted GPU's requested extension of the March 31, 1965 environmental qualification deadline. [Ref. 18.]

However, even assuming, arguendo, that the instrumentation used to i

determine subcooling margin from the hot led RTDs is environmentally quali-fied, that .intrumentation can not substitute for the incore thermocouples because it can not be used unless the reactor coolant pumps are running.

Under design basis accident assumptions, the reactor coolant pumps will not be running. The Commission's regulations (GDC-17) require postulating the loss of offsite electrical power, which is the only source of power for the pumps.

Furthermore, even if offsite power is not lost, the TMI-1 reactor operators have been trained and instructed to shut off the reactor pumps in certain accident situations. Thus, UCS concludes that NUREG-0737 Item II.F.2 is not

! complete because the incore thermocouples are not environmentally qualified.

UCS also concludes, contrary to the staff, that GPU has not provided a valid justification for operation of INI-1 without environmentally-qualified incore thermocouple instrumentation. One or the other must be done before operation  !

I of THI-1 can go forward uunder the rules that apply to all plants.

i

2. GPU Commitments or License Conditions That Are Not Met One of the lessons learned requirements was that provisions to supply-
- emergency electrical power to the pressurizer + heaters must be made without degrading the capacity, capability or reliability of the onsite emergency 1

1/ UCS received a copy of this letter at 4:00 p.m., Friday, April 15, 1985.

, . - - -,,.,,..,--,.--,w a -n-,nc .--.---,n - -.r,.,. . - - - - - - , .a-- - - - - . . . . ~ - - . - -

power supply. During the restart proceeding, UCS contended that the provi-sions at INI-1 to protect against the loss of the emergency electrical power supply as a result of an electrical fault (e.g., short circuit) in the non-safety grade pressurizer heaters or their circuits were inadequate. [Ref. 19.]

This safety issue was resolved by the Boards relying upon, inter alia, GPU's commitments that two conditions would be satisfied at IMI-1. First, the Boards relied upon GPU's testimony that "[t]he undervoltage relays will trip 1

open the (pressurizer heater circuit] breaker if the voltage on the ES

[ engineered safeguards] bus drops to 430v for 1.5 seconds." [Ref. 20.]

Second, the Boards relied upon GPU's testimony that the pressurizer heaters will not be connected to the emergency power supply unless " adequate diesel generator capacity is available and all systems have stabilized." [Ref. 21.]

GPU apparently has no intention of adhering to these two conditions.

During routine safety inspections of TMI-1 conducted on January 3 -

February 3, 1984, NRC inspectors noted that GPU had changed both the voltage and time delay setpoints for the undervoltage trip. The inspectors reported that the setpoints were changed from those relied upon by the Appeal Board to avoid tripping of the pressurizer heater circuit breakers "due to motors starting on the class 1E bus." (If motors are being started, then the load on the power supply has not been stabilized.) Although aware that the Appeal Board decision was based on different setpoints, the inspection report states

?

that "[t]his item is closed." The relevant portion of the inspection report follows:

The setting specified in the Licensee [ sic] Boar'd Hearing ALAB-729 was 430 volts at 1.5 seconds. The setting by the licensee is 420 volts at I second. '

The ALAB-729 relay setting of 430 volts would protect the j class 1E system.- However, the purpose of CLI-79-8 would not i i

be achieved due to undesired tripping. This setting is 90% of  ;

normal [ voltage] which would be reached due to motors starting

~ -- . - - - - _ - -. .- -- _ .. .. -. __

{ '

~

, on the class 1E bus. The setting of 420 volts is 85% of 3 normal which allows 80% for motor starter coil pickup plus 5%

i voltage drop through the control transformer and control wires. The time setting has been reduced from the ALAB-729 equirement of 1.5 seconds to .1 second. The 85% voltage setting at 1 second assures the primary objective of pro-tecting the class 1E system. This item is closed. [Ref. 22.]

! It is not clear what evaluation, if any, was done by the staff to support the conclusion that revised undervoltage trip setpoints achieve "the primary objective" of protecting the onsite emergency power supply. It is clear,

) however, that the revised setpoints are not equivalent to those relied upon by the Appeal Board. For example, an electrical fault that caused the voltage to drop to between 420 and 430 volts would not result in tripping of the circuit breakers no matter how long the ' fault persisted if the unauthorized setpoints f are used. In contrast, the same fault would result in tripping the breaker if i

{ the setpoints relied upon by the Appeal Board are used. Thus, to some degree, i

the revised setpoints degrade the capability and reliability of the emergency power supply. In any event, the staff and GPU can not unilaterally change commitments relied upon by the Boards.

UCS considers the abandonment of the commitment. not to connect the pres-surizer heaters to the emergency power supply unless the loads have stabilized l

to have even more safety significance because a failure of the emergency power ,

system at this stage could imperilall of the plant's safety systems. - Further- l

more,- if that commitment had not . been abandoned, there would apparently have l

, 'been no need to depart from the specific voltage and time delay setpoints for I

the undervoltage trip which were relied upon by:the Appeal, Board.

l t - .

3. TMI-1 Technical Specifications That Negate Board Decisions

( A principal- purpose' of the restart proceeding was to decide, in view of 1

the 1NI-2 accident, what new safety equipment was. necessary and sufficient to l

4 protect the health and safety of the public during operation of INI-1. That process has been completely frustrated by the approval of license technical specifications that permit operation of INI-1 with equipment inoperable, even though the Boards found that equipment to be necessary to protect the public.

Examples of instances where this has occurred are as follows:

a. Subcooling Margin Instrumentation. A lessons learned requirement was that primary coolant saturation meters should be installed to provide online indication of coolant saturation condition. [Ref. 23.] GPU testified that this requirement was met by the installation two "subcooling margin monitors,"

one for each loop. However, the technical specification permit unrestricted operation of TMI-1 with one subcooling meter inoperable all the time and permit operation for an additional week after failure of the second. [Ref. 24.]

The purported basis for this technical specification is that "[allternate indications are available for Saturation Margin Monitors using hand calcula-tions." [Ref. 25.] However, the use of " hand calculations," which were avail-able during the TMI-2 accident, obviously does not meet the lessons learned requirement to install instrumentation "to provide on-line indication of coolant saturationcondition." [Ref. 26.] Furthermore, the only temperature indications available for such hand calculations, other than the hot leg resistance temperature detectors which provide the temperature input to the subcooling meters, are the incore thermocouples. As discussed above, the staff has proposed allowing TMI-1 to operate without environmentally qualified incore thermocouple instrumentation on the grounds that the incore thermocouples are backed up by the subcooling meters. In any event, the lessons learned requirements specified that both the incore thermocouples and saturation meters must be provided and GPU tesimony during the restart proceeding was that both would be.

b. Direct Indication of PORY and Safety Valve Position. A lessons learned requirement was that reactor system relief and safety valves shall be provided with reliable positive indication of their position in the control room. [Ref. 27.] GPU testified that this requirment had been met by the installation of redundant position indicators for the PORV and by a single position - indicator for each safety valve. Specifically, discharge flow from the two pressurizer code safety valves and the PORY is measured by differen-tial pressure transmitters connected across elbow taps downstream of each valve. In addition, an acoustic monitor is provided to detect flow in the PORV discharge line.

However, the technical specifications permit operation of THI-1 with either one of the PORV instruments continuously inoperable and permit con-tinued operation for a week following the failure of the other PORV instrument and both safety position indications. [Ref. 28.] The basis purported to justify this relaxation of the lesson learned requirements is that alternate indication of the position of the safety valves and the PORV is available from the thermocouples in the valves' discharge pipes. It is precisely these downstream thermocouples that proved . inadequate during the _ TMI-2 sccident and led to the requirement for reliable position indication.

c. Emergency Feedwater System Flow Indication. A l'e s sons learned requirement was that "[slafety-grade indication of auxiliary feedwater flow to each steam generator shall be provided in the control room." [Ref. 29.] GPU testified that this requirement was met by the installation of redundant EFW flow instruments for each steam generator.

However, the technical specifications permit operation of TMI-1 with one flow instrument for each steam generator inoperable all the time and permit continued operation for a week following failure of the other EFW flow instru-i

ments. [Ref. 30.] - Allowing operation with one flow instrument inoperable does not meet the requirement for sLfety-grade instrumentation because the single failure criterion is not met with only one flow indicator per steam generator.

l The availability of local EFW flow indication does not satisfy the requirement that the indication be in the control room,

d. Reactor Coolant System High Point Vents. A lessons learned require-ment was that high points vents be installed inorder to vent non-condensible

. gases from the reactor . coolant system which could otherwise block natural circulation cooling of the core. The lessons learned requirements applicable to the high point vents specified that although each vent path need not meet the single failure criterion, a " degree of redundancy should be provided by

. powering different vents from different emergency buses." [Ref. 31.]

The evidentiary record indicates that INI-1 complied with this require-ment by installing four vents - one on each loop, one on the pressurizer and one on the reactor vessel. The cesign is such that the vents on the vessel, pressurizer, and loop B are powered from one electric power supply and the vent on loop A is powered from a redundant power supply.

However, the technical specifications permit operation of TMI-1 wi,th one

loop vent inoperable all the time and permit continued operation for 30 days  !

following - failure of another vent. [Ref. 32.] Thus, if THI-1 is operating with the loop A vent inoperable, a single failure of the power supply for the i

pressurizer, vessel and loop B vents would render all high point vents inoper--

able. 'The technical specifications therefore violate the lesson learned l requirement that the vents collectively should meet the single failure criter-

ion. Furthermore, since ' the vents on the pressurizer and the vessel can not l

remove gas from the high point of the loops, the - same situation (i.e., the t

inability to restore natural-' circulation) would prevail if INI-1 were in oper-

'l

- - . _ . - -- . - . - . . . . - . -. - i

) .

ation with the loop B vent inoperable. That _ is, an accident accompanied by a

  1. single failure of the power supply for the loop A vent would leave THI-1 with no operable loop vent. The basis for this technical specification provides no j justication either for allowing operation with one loop vent continuously 1

inoperable, or for 30-days continued operation with both loop vents inoperable. I l

1 1

UCS concludes that the TMI-1 Technical specifications must be amended to require, as " limiting conditions for operation," the operability of all equip-ment relied upon by the Boards as a basis for the decision that TMI-1 can be operated without endangering the health and safety of the public. In addition, we believe that another requirement should be added to the technical specifications.

The technical specifications permit continued - operation for some period of time following failure of safety equipment that is subject to a limiting (r condition for operation. If repairs can not be made with the specified time, the technical specification require that the plant be shut down.

f UCS believes

that GPU should be required to assess, within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after detecting the 1 failure, whether the equipment can be restored to an operable status within
the time continued operation is permitted ' without that - equipment. When-it is )

concluded that repairs can not be accomplished within the allowable time l period, the plant should be immediately shut down. There is no justification  !

l for continued operation, even for a limited time, if it is known that the l

, equipment can not be repaired prior- to the time the plant will be required to shut down. s 4

J

4. References. See next page.

i-l

- y-s

= 6 References

1. NUREG-0737, Item II.D.1. See also, NUREG-0578, Section 2.1.2.
2. Appeal Tr. pp. 151-152 (Lanese), March 7, 1983.
3. J. H. Taylor, Manager, _ Licensing Services, B&W, letter to R. C. DeYoung.

Director, IE, NRC, October 15, 1982, p. 1.

4 See LBP-81-59, 14 NRC 1211. 1375 (1981).

5. 14 NRC 1378-79.

6.. Jones and Lanese, fol. Appeal Tr. 111 at 3-4, March 7, 1983, emphasis added..

7. Id., at 4
8. Appeal Tr. 423 (Correa), March 16, 1983, emphasis added.
9. NRC Inspection _ Report No. 50-289/85-03, March 18, 1985, p. 3.

4

10. Frank Miraglia and Gus Lainas, Division of Licensing, NRC, memorandum to
James Knight, Division of Engineering, NRC, " Review of Licensee / Vendor Letter on Dresser Safety Valves," November 3, 1982.
11. Thomas Ippolito, Division of Licensing, NRC, memorandum to Dennis Crutchfield, Division of Licensing, NRC, " Review of Licensee / Vendor Letters on Dresser Safety Valves," December 30, 1982, enclosure, Table 1.
12. Id.
13. NUREG-0737, Item II.F.2, Attachment 1, p. 3-118..
14. Harold Denton, Director, NRR, NRC, letter to Henry Hukill, Vice President
and Director - TMI-1, GPUN, March 29, 1985, p. -1.
15. GPUN letter no. 5211-85-2018 to Harold Denton, NRC, February' 12, 1985, p.1, emphasis added.
16. . Id., enclosure, p. 6.
17. Id.', enclosure, p. 3, n. 1~.
18. Harold Denton, Directors NRR, NRC, letter. to Henry Hukill, Vice President and Director - TMI-1, GPUN, March 29,.1985, p. 2.
19. See, e.g. , ALAB-729, 17 NRC 814, 855-859 (1983) .
20. 17 NRC 858, footnote omitted.

.21. 17 NRC 860, footnote omitted, emphasis added.

l

-( #

[

22. NRC Inspection Report No. 50-289/84-01, March 17, 1984 (NRC transmittal letter dated April 9, 1984), p. 5.
23. NUREG-0578, pp. A-11, A-12.

24 Technical Specification 3.5.5 (Amendment No. 100) and Table 3.5-2 (Amendment No. 78).

25. Technical Specification 3.5.5, p. 3-40b (Amendment No. 100).
26. NUREG-0578, p. A-12.
27. NUREG-0578, pp. A-9, A-10.
28. Technical Specification 3.5.5 (Amendment No. 100) and Table 3.5-2 (Amendment No.-78).
29. NUREG-0578,'p. A-32.
30. Technical Specification 3.5.5 (Amendment No. 100) and Table'3.5 (Amendment No. 78).
31. NUREG-0737, Item II.B.1, Reactor Coolant System Vents.
32. Technical Specification 3.1.13 (Amendment No. 97).

I l

l

'