ML19343C290

From kanterella
Jump to navigation Jump to search
Informs of Status of Activities Initiated in Response to IE Bulletins 75-04 & 75-04A Re Cable Fire at Browns Ferry.Util Scheduling Implementation of Commitments & Developing Specs for Halon 1301 Suppression Sys for Cable Spreading Room
ML19343C290
Person / Time
Site: Oyster Creek
Issue date: 01/06/1977
From: Ross D
JERSEY CENTRAL POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-75-04, IEB-75-04A, IEB-75-4, IEB-75-4A, NUDOCS 8103060184
Download: ML19343C290 (1)


Text

- m n

e Jersey Central Power & Light =)' Company MADISON AVENUE AT PUNCH EOWL RO AD e MORRISTOWN, N.J. 07960

  • 201539-6111 nr. . o, r.,

General P ', PubHc utilitie$ Corporation y

EAGWB-10 January 6, 1977 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement Region I United States Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. O'Reilly:

Subject:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Status Report of IE Bulletins No. 75-04 and No.75-04A

Reference:

Our Monthly Status Letters to you since May, 1975 This reports the status of activities that were initiated in response to IE Bulletins No. 75-04 and 75-04A.

In early December, 1976, we submitted to the commission our comparison of.the Oyster Creek Fire Protection System with the Commission's Standard Revicw Plan 9.5.1, We have made extensive commitments toward fire protection which are itemi::ed in the comparison. We are now in the process of scheduling the implementation of these commitments and developing l the specifications for the Halon 1301 Suppression System for the cable spreading rooc,etc. as per previous correspondence. We will continue P.o submit monthly status letters pertaining to the implementation of the Oyster Creek Fire Protection commitments.

Ver truly yours, s /

D. A. Ross, Manager Generating Stations - Nuclear l- .