ML17354A514

From kanterella
Jump to navigation Jump to search
LER 97-002-00:on 970423,automatic Reactor Tripped.Caused by Actuation of Turbine Overspeed Protection Circuit. Administrative Procedures Governing Inadequate Work Controls Will Be Revised to Capture Lessons learned.W/970522 Ltr
ML17354A514
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 05/22/1997
From: Hovey R, Mowrey C
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-97-128, LER-97-002-02, LER-97-2-2, NUDOCS 9706030019
Download: ML17354A514 (16)


Text

~ CATEGORY ~

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCEGSION'BR:9706030019 DOC.DATE: 97/05/22 NOTARIZED: NO DOCKET ¹ FACIL:50-251 Turkey Point Plant, Unit 4, Florida Power and Light C 05000251 AUTH. NAME AUTHOR AFFILIATION MOWREY,C.L. Florida Power & Light Co.

HOVEY.,R.J. Florida Power & Light Co.

'RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

LER .97-002-00:on 970423,automatic, reactor tripped. Caused by actuation of turbine overspeed protection circuit.

Administrative procedures governing inadequate cwork controls will be revised to capture lessons learned.W/970522 ltr.

DISTRIBUTION 'CODE: IE22T COPIES RECEIVED:LTR 3 ENCL SIZE:

TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt, etc. E NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-3 PD 1 1 CROTEAU,R 1 1 INTERNAL'~QRAB 2 2 AEOD/SPD/RRAB 1 1 1

1 1 NRR/DE/ECGB 1 1 1 NRR/DE/EMEB 1 1 NRR/DE/EELB'RR/DRCH/HHFB 1 1 NRR/DRCH/HICB 1 1 NRR/DRCH/HOLB 1 1 NRR/DRCH/HQMB 1 1 NRR/DRPM/PECB 1 1 NRR/DSSA/SPLB 1 1 NRR/DSSA/SRXB 1 1 RES/DET/EIB 1 1 RGN2 FILE 01 1 1 D EXTERNAL: L ST LOBBY WARD 1 '1 LITCO BRYCE,J H 1 1 NOAC POOREgW. 1 1 NOAC QUEENER,DS 1 1 NRC PDR 1 1 NUDOCS 'FULL 'TXT 1 1 E

N NOTE TO ALL "RZDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 FUL'L TEXT'ONV"RSION REQUIRED TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24

I x/

NAY 28 1997 L-97-128'0 CFR 50..73 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C, 20555 Re: Turkey Point Unit 4 Docket No. 50-251 Reportable Event: 97-002-00 Automatic Reactor Tri Due to Loss of External Load The attached Licensee Event Report 251/97-002-00 is being provided in accordance with 10 CFR 50.73(a) (2) (iv) ..

If there are any questions, please contact us.

Very truly yours, R. J. Ho ey Vice President Turkey Point Plant attachment cc: Luis A. Reyes, Regional Administrator, Region II, USNRC Thomas P. Johnson, Senior Resident Inspector, Turkey Point Plant, USNRC 9706030019 970522 PDR ADOCK 05000251 PDR II!IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII an FPL Group company

I i5

LICENSEE EVENT REPORT (LER)

FACILITY NAME t 1) DOCKET NUMBER (2) PAGE (3)

TURKEY POINT UNIT 4 05000251 OF

'TITLE Automatic Reactor Trip Due to Loss of External Load EVENT DATE <S) LER NUMBER(6) RPT DATE (7) OTHER FACILITIES INV. ts)

MON DAY YR SEQ ¹, R¹ MON DAY YR FACILITY NAMES DOCKET ¹ (S) 4 23 97 97 002 00 5 22 97 OPERATING MODE (9)

POWER LEVEL {10) 100%

LICENSEE CONTACT FOR THIS LER (12)

TELEPHONE NUMBER C. L. Mowrey, Compliance Specialist 305-246-6204 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (13)

CAUSE SYSTEM NPRDS7 CAUSE COMPONENT MANUFACTURER NPRDS7 SUPPLEMENTAL REPORT EXPECTED (14) NO YES 0 EXPECIED SUBMISSION MONTH DAY DATE tlS)

(If yes, caepleee EXPECTED SUBMISSION DATE)

ABSTRACT (16)

On April 23, 1997, Unit 4 tripped from 100% power. An Z6C Specialist, working inside the back of the Main Control Board, apparently bumped a relay, causing a false Turbine Overspeed Protection signal. The signal caused turbine control valves to close (loss of load), and the reactor tripped on Over Temperature Delta-T.

The root cause of the event was inadequate physical protection.

The contact arm on this relay is not enclosed, and can be actuated with very slight force. Contributors were inadequate work controls and a loss of lighting inside the panel during the work.

The work document did not indicate that the work had the potential to trip the unit.

This relay and others like it will be evaluated to determine they can be enclosed or relocated, to prevent inadvertent if actuation. Until the evaluation is complete, Nuclear Plant Supervisor (NPS) permission is required to work inside this panel, and the NPS will brief the workers. on the location and sensitivity of the relays. Administrative procedures governing the inadequate work controls will be revised to capture the lessons learned.

I LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME DOCKET NUMBER LER NUMBER PAGE NO TURKEY POINT UNIT 4 05000251 97-002-00 2 OF 6 I.. DESCRIPTION OF THE EVENT On April 23, 1997,, Florida Power & Light Company's Turkey Point Unit 4 was operating in Mode 1 at 1008 power. The following maintenance activities were in progress:

1. Periodic survei;llance testing on T-average and Delta-T

'Protection Channels [JC], requiring the condenser steam dump valves [JI:cv] to be in manual.

2. .Rescaling of Condensate Storage Tank (CST) level indicators [KA:li] on the control console. Train A had been completed; the train B. indicator was being changed.

~

3. Restoration of a Temporary System Alteration on Lighting Panel LP-50 [FF:pl], which rendered all turbine valve position indication [JJ:zi], and the digital generator load indicator [TB:ji],-, out of service.

At approximately 10:53 a..m , the first of three Turbine Overspeed Protection Circuit (OPC) signals was detected by the plant Digital Data Processing System (DDPS) [IQ] computer. The OPC circuit is normally actuated upon a turbine trip, or by an imbalance between steam pressure (>50%) and turbine load (<20%').

The circuit prevents turbine overspeed by dumping: turbine control oil pressure [TG], thereby causing the turbine control valves to close. The system takes about two seconds to completely drain the oil pressure, but it takes only a 20% decrease in oil pressure to:effectively close the turbine control, valves.

About ten seconds after the initial OPC alarm an automatic reactor trip occurred due to Over Temperature Delta-T (OTdT).

Due to the lost turbine valve position indication from the LP-50 work, operators could not verify the turbine valves closed after the trip. Therefore they manually closed the Main Steam Isolation Valves (MSIVs)[SB:iv] in accordance with the Response Not Obtained step of the Emergency Operating Procedure.

Review of the DDPS sequence of events showed that 'the event .was initiated at 10:53:57..13, when the OPC alarm was receivedand'hen by DDPS. During the next 3.33 seconds this alarm cleared, actuated and cleared two more times, .with a total time in alarm of 1.95 seconds; the last actuation lasted 1.5 seconds. About 7.8 seconds after the last actuation the reactor tripped.

Ib 1

LICENSEE EVENT REPORT (LER) 'TEXT CONTINUATION

'FACILITY NAME DOCKET NUMBER LER NUMBER PAGE NO.

TURKEY POINT UNIT 4 05000251 97-002-00 3 OF 6 Cl'osing the turbine control valves had the immediate effect of dropping Tf, which is developed from the turbine first stage pressure signal. Tf .is used as a setpoint input to the Hi Steam Flow comparators, which alarmed repeatedly during this time.

The secondary effect of closing, the turbine control valves was a diminished heat sink for the Reactor Coolant .System (RCS)[AB],

exacerbated by the unavailability of the condenser steam dump valves. As steam flow was cut off, cold leg RCS temperature increased rapidly, which in turn caused an increase in T,9.

T,9 is a parameter input to the OTdT setpoint. The difference between actual T 9 and nominal T,, (T,, at rated thermal power) is applied to a lead/lag element that has a large dynamic gain for 'a rapidly changing signal. The overall effect of the increasing T,9 was a large penalty on the OTdT setpoint, driving the setpoint down to meet actual Delta-T, causing a reactor trip.

The loss of external load and manual MSlV closure resulted in actuation of both pressurizer Power Operated. Relief Valves (PORVs) [AB:rv], and each of the 1085 psig Main Steam safety valves [SB:rv](one on each of the three steam generators) . All valves reseated properly upon pressure reduction. The PORVs, lifting at 2335 psig, prevented the pressurizer safety valves

[AB:,rv] from lifting. All control rods [AA] fully inserted on the reactor trip. The high RCS temperature resulting from the loss of external load kept pressurizer level above the programmed no-load value; a second charging pump was started manually to aid in maintaining pressurizer level. The high RCS temperature also prevented .an automa'tic feedwater isolation signal. Manual operator action was taken successfully, to maintain steam

- generator levels between 10% and 80% narrow range. level.

Therefore automatic Auxiliary Feedwater actuation did not occur, and'as not needed.

The NRC Operations Center was notified in accordance with 10 CFR 550. 72 (b) (2), (ii) .

II. CAUSE OF THE EVENT The cause of the reactor trip was actuation of the Turbine Overspeed Protection Circuit(OPC) . The OPC circuit apparently was actuated when the R/OPC relay .was bumped.

0 V

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME DOCKET NUMBER LER'UMBER PAGE NO.

TURKEY POINT UNIT 4 05000251 97-002-00 4 OF 6 The root cause of the event was inadequate physical protection for the relay.

The R/OPC relay is a Westinghouse Model SG relay, located inside Main Control Board panel 4C02 [JL:cbd]. It is mounted on the rear panel which forms a stanchion between two access doors at the rear of the board." When gaining access to one of the panel's front mounted devices, such as the CST level indicator, one comes in close proximity to this relay without being aware of it. The relay is constructed so that its contact arm is not enclosed.

The force needed to actuate this arm was tested and found to be very slight.

A contributor was inadequate work controls. Turkey Point uses a plant operation (called "load threatening work, "'r "Red Sheet" to identify. work which could pose a risk to continued "sensitive work") . The Red Sheet completed for the work on the CST level indicators did not indicate that the work had the potential to trip the unit, i.e., close proximity to the R/OPC relay.

Another contributor was the outage on Lighting Panel LP-50.

LP-50 was de-energized just prior to completion of the work on the CST level indicators. With LP-50 out of service, the normal lighting inside control board 4C02 was lost, and the CST level indicator work was being finished by flashlight.

III. ANALYSIS OF THE EVENT The Turkey Point Units 3 and 4 Updated Final Safety Analysis Report (UFSAR) discusses. the expected plant response to a complete loss of generator load. The UFSAR assumes a complete loss of load'ithout a subsequent reactor trip, and shows the adequacy of the pressure relieving devices and that no core damage results. The UFSAR conclusion was that this event poses no hazard to the integrity of the reactor coolant system and steam system. In the:event reported herein the reactor trip occurred as designed. Therefore, the UFSAR analysis bounds the trip which occurred in this case. As a result of this analysis, plant procedures are developed to provide operator guidance in responding to these transient conditions and to assure that the plant is stabilized in a safe condition,. The unit was stabilized in Mode 3 in accordance with these approved plant procedures.

All safety related equipment operated per design. Therefore the health and safety of the public were not adversely affected.

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME DOCKET NUMBER LER NUMBER PAGE NO.

TURKEY POINT UNIT 4 05000251 97-002-00 5OF6 IV. CORRECTIVE ACTIONS A training brief will be issued to all plant departments detailing the lessons learned from this incident.. Each Maintenance discipline will receive additional training on the correct leveI of review detail for Red Sheets.

2) Engineering will investigate the possibility of installing. a relay cover or relocating the R/OPC relay for both Unit 3 and Unit 4.
3) Operations has hung a caution tag on the 3C02 and 4C02 access doors, requi'ring permission from the Nuclear Plant Supervisor to enter. Prior to granting access, the Nuclear Pl'ant Supervisor will provide a briefing regarding the location and sensitivity of the relays. These tags will remain until Corrective Action 82 is complete.
4) Procedure O-ADM-701, Control of Plant Work Activities, will be revised to require a job .walkdown prior to work inside control room consoles or vertical panels (if the unit is at power), and the Red Sheet will be revised to identify such work as sensitive work. These changes will improve the recognition of sensitive jobs, and also help prevent the scheduling of other work which might impact such sensitive jobs, e.g., lighting outages.
5) Engineering will inspect the Unit 3 and Unit 4 control consoles and vertical panels to identify those relays that are not enclosed, and may be inadvertently actuated; to determine the consequences of such actuation; and to determine any needed countermeasures.

V. ADDITIONAL INFORMATION Similar events: LER 250/91-002 reported a reactor trip signal generated (with the unit defueled) as a result of allowing work in both trains of reactor protection simultaneously. A contributor to that event was that one train of protection was activated when a technician bumped an unprotected'reaker inside a cabinet. Corrective actions for that event were directed at safety-related protection equipment, and did not include non-safety relays. LERs 251/94-004 and 250/96-006 reported events caused in,part by relays mounted on breaker cubicle doors, which

11 LICENSEE EVENT REPORT. (LER) TEXT CONTINUATION FACILITY NAME .DOCKET 'NUMBER LER NUMBER PAGE NO.

TURKEY POINT UNIT 4 05000251 97-002-00 6OF6 were jarred. In both cases, the jarring resulted from mechanical agitation by nearby components, not from bumping by personnel.

EIIS Codes are shown in the format,[EIIS SYSTEM: IEEE component function identifier, second .component function identifier (if appropriate)].

II 0 J

~ '