Category:Inspection Plan
MONTHYEARML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22249A2552022-06-29029 June 2022 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000482/2022012 ML22130A7662022-05-10010 May 2022 Notification of Inspection (NRC Inspection Report 05000482/2022003) and Request for Information IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML22019A0932022-01-19019 January 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000482/2022002) and Request for Information ML21322A2952021-11-19019 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000482/2022001 and Request for Information ML21237A5212021-09-0101 September 2021 Wc Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21132A1032021-05-12012 May 2021 Document Request List, Paperwork Reduction Act Statement ML21123A0412021-05-0505 May 2021 Notification of NRC Design Bases Assurance Inspection (Teams) (05000482/2021010) and Initial Request for Information IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) ML21061A3412021-02-25025 February 2021 Request for Information: Wolf Creek Nuclear Station, Dated February 11, 2021, Inspection Report 05000482/2021002 Occupational Radiation Safety Inspection-1, 2, PI ML21026A1982021-01-26026 January 2021 Inservice Inspection Request for Information ML20104C1472020-04-13013 April 2020 Notification of Inspection (NRC Inspection Report 05000482/2020003) and Request for Information ML20099G9422020-04-0808 April 2020 Notification of NRC Biennial Problem Identification and Resolution Inspection (05000482/2020010) and Initial Request for Information ML20055E1132020-03-0303 March 2020 WC2019006 Annual Assessment Letter ML20024D7072020-01-24024 January 2020 Notification of NRC Design Bases Assurance Inspection (Programs) (05000482/2020011) and Initial Request for Information IR 05000482/20190052019-08-30030 August 2019 Updated Inspection Plan for Wolf Creek Generating Station, Report 05000482/2019005 ML19158A0782019-06-0505 June 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2019003) and Request for Information IR 05000482/20180062019-03-0404 March 2019 Annual Assessment Letter for Wolf Creek Report 05000482/2018006) ML19043A9462019-02-12012 February 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000482/2019002) and Request for Information IR 05000482/20180052018-08-31031 August 2018 Updated Inspection Plan for Wolf Creek Generating Station, Unit 1, (Inspection Report 05000482/2018005) IR 05000482/20170062018-03-0101 March 2018 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006) ML17311A5182017-11-0101 November 2017 Notification of NRC Inspection of Implementation of Mitigation Strategies Assessment Plans (05000482/2018008) and Request for Information IR 05000482/20170052017-08-28028 August 2017 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) IR 05000482/20160062017-03-0101 March 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016006) IR 05000482/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) ML16237A0732016-08-31031 August 2016 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) IR 05000482/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Reports Number 05000482/2016401) ML16085A0532016-03-25025 March 2016 Operating Corp - Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2016002) and Request for Information IR 05000482/20150062016-03-0202 March 2016 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015006) IR 05000482/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015005) ML15015A1712015-01-0808 January 2015 Focused Baseline Inspection at the Wolf Creek Site for a Major Essential Service Water Modification IR 05000482/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Report Number 05000482/2014402) IR 05000482/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2014006) ML14231A0682014-08-19019 August 2014 Notification of Inspection (NRC Inspection Report 05000482-14-005) and Request for Information ML14063A6282014-03-0404 March 2014 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2013001) ML13246A2992013-09-0303 September 2013 Midcycle Assessment Letter 2013 IR 05000482/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station (05000482/2012006) 2024-08-14
[Table view] Category:Letter
MONTHYEARIR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 ML24050A0012024-02-19019 February 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) 2024-09-06
[Table view] |
Text
tember 2, 2014
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 0500482/2014006)
Dear Mr. Heflin:
On August 12, 2014, the NRC completed its mid-cycle performance review of Wolf Creek Generating Station. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2013, through June 30, 2014. This letter informs you of the NRCs assessment of Wolf Creek Generating Station during this period and its plans for future inspections at that facility.
The NRC determined that overall, Wolf Creek Generating Station was operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Wolf Creek Generating Station during the most recent quarter was within the Regulatory Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because of one Greater-than-Green Security Cornerstone input and one White finding in the Emergency Preparedness Cornerstone. The Security issue was described in Inspection Report 05000482/2014405 (ADAMS ML14069A025), and the White Emergency Preparedness finding, associated with a failure to maintain adequate methods for assessing the potential consequences of a radiological emergency condition, was described in Inspection Report 05000482/2014503 (ADAMS ML14182A628). The NRC issued a Follow-Up Assessment letter dated March 26, 2014, (ADAMS ML14085A376) to inform you of your movement from the Licensee Response Column to the Regulatory Response column of the NRCs Action Matrix.
In addition to ROP baseline inspections, the NRC plans to conduct supplemental inspections in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, when you inform us of your readiness for these inspections. The objectives of this inspection procedure are to provide assurance that, for risk-significant performance issues: (1) the root causes and contributing causes are understood; (2) the extent of condition and extent of cause are identified; and (3) the licensees corrective actions are sufficient to address the root and contributing causes and prevent recurrence. These supplemental inspections will separately review your actions to address the Greater-than-Green Security Cornerstone input and White finding in the Emergency Preparedness Cornerstone.
The NRC also issued a Chilling Effect Letter (CEL) (ADAMS ML13233A208) to Wolf Creek Nuclear Operating Corporation on August 19, 2013. The CEL was issued because the Occupational Safety and Health Administration (OSHA) had issued a finding of discrimination for raising safety concerns against a former employee of an engineering contractor employed by Wolf Creek Nuclear Operating Corporation, and due to the NRC identifying that a chilled work environment existed within your facilitys Quality Assurance Group. Issuance of a CEL meets the NRC criteria in Inspection Manual Chapter (IMC) 0305, Operating Reactor Assessment Program, for the identification of a cross-cutting theme in the area of safety conscious work environment (SCWE). The NRC has assessed your 30-day and 6-month responses to the CEL, and conducted a public meeting in the Region IV office on January 22, 2014, to discuss the actions that you are taking to address the working environment at your facility. The NRC has decided not to open a substantive cross-cutting issue in the area of SCWE at this time because the NRC staff does not have a concern with your actions. This theme will continue to be reviewed during the next performance assessment as we continue to monitor your staffs actions to ensure Wolf Creek Generating Station is a workplace that fosters an environment where employees feel free, and are encouraged, to raise safety concerns. The NRC will conduct a follow-up inspection to review your actions to address the CEL when you inform us of your readiness for inspection.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310.
Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections scheduled to be conducted during the last nine months are tentative and may be revised based on the results of the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact your staff as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Neil F. OKeefe at 817-200-1141 with any questions you may have regarding this letter.
Sincerely,
/RA/
Troy W. Pruett, Acting Director Division of Reactor Projects Docket No.: 50-482 License No.: NPF-42 Enclosure: Wolf Creek Generating Station Inspection/Activity Plan
ML14239A622 SUNSI Review ADAMS Publicly Available Non-Sensitive By: NOKeefe Yes No Non-Publicly Available Sensitive OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME OKeefe/dll AVegel TPruett SIGNATURE /RA/ /RA/VGaddy /RA/
for DATE 8/21/14 8/25/14 8/25/14
Letter to Adam from Troy W. Pruett dated September 2, 2014 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2014006)
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
Acting DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Michael.Hay@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Charles.Peabody@nrc.gov)
Resident Inspector (Raja.Stroble@nrc.gov)
Administrative Assistant (Carey.Spoon@nrc.gov)
Branch Chief (Neil.OKeefe@nrc.gov)
Senior Project Engineer (David.Proulx@nrc.gov)
Project Engineer, (Fabian.Thomas@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
RIV State Liaison Officer (Bill.Maier@nrc.gov)
Project Manager (Fred.Lyon@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
R4DRPBC@nrc.gov R4DRSBC@nrc.gov Director, DIRS, NRR (Scott.Morris@nrc.gov)
Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)
Acting Director, DORL, NRR (Louise.Lund@nrc.gov)
Acting Deputy Director, DORL (Michael.Markley@nrc.gov)
Director, NSIR/DPR (Rob.Lewis@nrc.gov)
Chief, PLB IV, DORL, NRR (Eric.Oesterle@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Anthony.Bowers@nrc.gov)
ROPassessment Resource@nrc.gov ROPreports@nrc.gov OEMail Resource@nrc.gov Electronic Distribution for Wolf Creek Generating Station
Page 1 of 2 Wolf Creek 08/22/2014 14:03:38 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EXAM - INITIAL OPERATOR EXAM 5 1 10/19/2015 10/23/2015 X02549 INITIAL EXAM WC(11/2015)
1 11/16/2015 11/20/2015 X02549 INITIAL EXAM WC(11/2015)
INSP - BIENNIAL REQUAL INSPECTION 3 1 10/06/2014 10/10/2014 IP 7111111B Licensed Operator Requalification Program EB2-05T - TRIENNIAL FIRE PROTECTION INSPECTION 4 1 10/20/2014 10/24/2014 IP 7111105T Fire Protection [Triennial]
1 11/03/2014 11/07/2014 IP 7111105T Fire Protection [Triennial]
EP-1 - EP PERFORMANCE INDICATORS 1 1 11/17/2014 11/21/2014 IP 71151-EP01 1 11/17/2014 11/21/2014 IP 71151-EP02 1 11/17/2014 11/21/2014 IP 71151-EP03 EP-2 - EP PROGRAM INSPECTION 1 1 11/17/2014 11/21/2014 IP 7111402 Alert and Notification System Testing 1 11/17/2014 11/21/2014 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/17/2014 11/21/2014 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/17/2014 11/21/2014 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies RS 13 PI - RADIATION SAFETY 2 1 03/02/2015 03/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/02/2015 03/06/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 03/02/2015 03/06/2015 IP 71151-OR01 1 03/02/2015 03/06/2015 IP 71151-PR01 71111.08 - INSERVICE INSPECTION 1 1 03/09/2015 03/20/2015 IP 7111108P Inservice Inspection Activities - PWR RS 24 - RADIATION SAFETY 2 1 06/22/2015 06/26/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 06/22/2015 06/26/2015 IP 71124.04 Occupational Dose Assessment EB1-17T - WC PERMANENT PLANT MODS & 50.59 1 1 07/06/2015 07/17/2015 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications EP-2 - HAB EXERCISE INSPECTION 5 1 11/16/2015 11/20/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 11/16/2015 11/20/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event EP-3 - EP PERFORMANCE INDICATORS 2 1 11/16/2015 11/20/2015 IP 71151-EP01 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Wolf Creek 08/22/2014 14:03:38 Inspection / Activity Plan Report 22 09/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP-3 - EP PERFORMANCE INDICATORS 2 1 11/16/2015 11/20/2015 IP 71151-EP02 1 11/16/2015 11/20/2015 IP 71151-EP03 This report does not include INPO and OUTAGE activities.