Mr. Cleve Reasoner, Chief Executive Officer
and Chief Nuclear Officer
Wolf Creek Nuclear Operating Corp
P.O. Box 411
Burlington, KS 66839
SUBJECT:
WOLF CREEK GENERATING STATION - REQUEST FOR INFORMATION
FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE
RENEWAL 05000482/2022012
Dear Mr. Reasoner:
On October 17, 2022, the Nuclear Regulatory Commission (NRC) will begin a Post-Approval
Site Inspection for License Renewal for your facility. Two inspectors will perform this one-week
inspection in accordance with NRC Inspection Procedure 71003. This Phase 1 inspection
focuses on reviewing the facility material condition, outage related activities to verify that license
conditions added as part of your renewed license, and a sample of license renewal
commitments have been implemented.
To minimize the inspection impact on the site and to ensure a productive inspection for both
parties, we have enclosed a request for information needed for the inspection. It is important
that all these documents are up to date and complete to minimize the number of additional
documents requested during the preparation and/or the on-site portions of the inspection.
Please provide this information electronically to the lead inspector. The information request has
two groups:
The first group lists information necessary for our initial inspection scoping and in-office
preparation activities. During the in-office preparation activities, the team will identify as
much as possible the information and activities to be reviewed during the inspection.
This information should be provided to the lead inspector by August 22, 2022.
The second group includes additional information required for the team to review the
selected activities. This information should be available to the team on October 17, 2022. It
is also requested that corrective action documents and/or questions developed during the
inspection be provided to the lead inspector as the documents are generated.
PAPERWORK REDUCTION ACT STATEMENT
This letter contains mandatory information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). Send comments
regarding this information collection to the Information Services Branch, Office of the Chief
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
June 29, 2022
C. Reasoner
2
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
Budget, Washington, DC 20503.
PUBLIC PROTECTION NOTIFICATION
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
for information or an information collection requirement unless the requesting document
displays a currently valid OMB control number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding. Your cooperation and support during this
inspection will be appreciated.
The lead inspector for this inspection is Greg Pick. If there are any questions about the
inspection or the material requested in the enclosure, please contact the lead inspector at
(817) 200-1270 (w), (817) 504-2105 (m) or via e-mail at greg.pick@nrc.gov .
Sincerely,
Greg Pick, Senior Reactor Inspector
Engineering Branch 2
Division of Operating Reactor Safety
Docket No. 50-482
License No. NPF-42
Enclosure:
Phase 1 Document Request
cc w/encl: Distribution via Listserv
Signed by Pick, Gregory
on 06/29/22
X SUNSI Review
ADAMS:
Non-Publicly Available
X Non-Sensitive
Keyword:
By: GAP
X Yes No
X Publicly Available
Sensitive
OFFICE
DORS/EB2/SRI:
NAME
GPick
SIGNATURE
gap
DATE
6/28/2022
1
Post-Approval Site Inspection for License Renewal Request for Information
I.
Information Requested Prior to the On-site Inspection - required by
August 22, 2022
If you have any questions regarding this information request, please call the team leader
as soon as possible. If a secure document management service is utilized, it is
recommended that a separate folder be used corresponding to each item listed below. It
is recommended that multiple documents within each folder be individually entered and
also combined into a ZIP file uploaded into the same folder. Documents should be
identified by both document number and noun name. Electronic media on compact disc
or paper records (hard copy) are also acceptable.
Please provide the information electronically in pdf files, Excel, or other searchable
formats, preferably on some portable electronic media (e.g., CDROM, DVD, flash drive,
etc.). The portable electronic media should contain descriptive names and be indexed
and hyperlinked to facilitate ease of use. Information in lists should contain enough
information to be easily understood by someone who has knowledge of light water
reactor technology.
1.
Provide a list of your license renewal commitments associated with appropriate
aging management programs. Include the completion status of each. For those
not yet complete, please provide an estimated completion date.
2.
Provide a list of your aging management programs, copies of the program basis
document for each and/or any associated plant program. Please include a listing
of the action tracking items for each.
3.
For aging management programs that are one-time inspection programs, provide
a list of completed work order numbers for inspections that have been
completed. This should include identification of the inspected component.
4.
Provide a listing of planned inspections that will be conducted during the onsite
week, credited for license renewal, that provide observations of areas that are
generally inaccessible at power (e.g., containment liner and containment coating
inspections). If there are no inspections planned, the inspectors will select areas
normally inaccessible that will need to be reviewed.
5.
Provide current management and license renewal organizational charts,
electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, Technical Specifications Bases, and Technical Requirements
Manual.
6.
Provide copies of any internal/external self-assessments and associated
corrective action documents generated in preparation for the inspection.
2
II.
Information Requested to be Available When the Inspectors Arrive On-site on
October 17, 2022
1.
Copies of the work orders requested during the preparation week related to the
selected commitments/aging management programs. This will include work
orders of inspections to be observed and completed work orders to be reviewed
by the team.
2.
Contact information to facilitate inspector observation of the selected work
activities or evaluation of inaccessible areas.
3.
Documentation demonstrating completion of license renewal commitments
considered completed as of the inspection date. For example, this may be in the
form of a binder for each commitment that includes the implementing
documentation and references.
III. Information Requested to be Provided Throughout the Inspection
1.
Copies of any corrective action documents generated because of the teams
questions or queries during this inspection.
2.
Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the inspection
to each team member).
If you have questions regarding the information requested, please contact the lead inspector.