ML14231A068
ML14231A068 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 08/19/2014 |
From: | Vincent Gaddy Division of Reactor Safety IV |
To: | Heflin A Wolf Creek |
References | |
IR-14-005 | |
Download: ML14231A068 (9) | |
See also: IR 05000482/2014005
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD.
ARLINGTON, TX 76011-4511
August 19, 2014
Adam C. Heflin, President and
Chief Executive Officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF INSPECTION
(NRC INSPECTION REPORT 05000482/2014005) AND REQUEST FOR
INFORMATION
Dear Mr. Heflin:
From October 6 through October 10, 2014, inspectors from the Nuclear Regulatory
Commissions (NRC) Region IV office will perform the baseline biennial requalification program
inspection at Wolf Creek Generating Station, using NRC Inspection Procedure 71111.11B,
Licensed Operator Requalification Program. Experience has shown that this inspection is a
resource intensive inspection both for the NRC inspectors and your staff. In order to minimize
the impact to your on-site resources and to ensure a productive inspection, we have enclosed a
request for documents needed for this inspection. These documents have been divided into
three groups. The first group (Section A of the enclosure) identifies information to be provided
prior to the inspection to ensure that the inspectors are adequately prepared. The second group
(Section B of the enclosure) identifies the information the inspectors will need upon arrival at the
site. The third group (Section C of this enclosure) identifies the items which are necessary to
close out the inspection and are usually sent a few weeks after the team has left the site. It is
important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the on-site portions of
the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Ms. Lucille Rockers of your licensing
organization. Our inspection dates are subject to change based on your updated schedule of
examination activities. If there are any questions about this inspection or the material
requested, please contact the lead inspector Mr. Sean Hedger at (817) 200-1556
(Sean.Hedger@nrc.gov), Mr. Michael Kennard at (817) 200-1244 (Michael.Kennard@nrc.gov),
or Mr. Gabriel Apger (Gabriel.Apger@nrc.gov).
A. Heflin -2-
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0018. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter
and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRCs
document system (ADAMS). ADAMS is accessible from the NRC web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Vincent G. Gaddy, Chief
Operations Branch
Division of Reactor Safety
Docket: 50-482
License: NPF-42
Enclosure:
Biennial Requalification Program Inspection Document Request
cc w/enclosure:
Electronic Distribution for Wolf Creek Generating Station
SUNSI Review ADAMS Publicly Available Non-Sensitive Keyword:
By: SHedger Yes No Non-Publicly Available Sensitive RGN-002
OFFICE OE:OB C:OB
NAME SHedger/dch VGaddy
SIGNATURE Email /RA/
DATE 8/15/2014 8/19/2014
Letter to Adam C. Heflin from Vincent G. Gaddy, dated August 19, 2014
SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF INSPECTION
(NRC INSPECTION REPORT 05000482/2014005) AND REQUEST FOR
INFORMATION
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
Acting DRP Director (Troy.Pruett@nrc.gov)
Acting DRP Deputy Director (Michael.Hay@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Charles.Peabody@nrc.gov)
Resident Inspector (Raja.Stroble@nrc.gov)
WC Administrative Assistant (Carey.Spoon@nrc.gov)
Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Project Engineer, DRP/B (Fabian.Thomas@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Fred.Lyon@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Anthony.Bowers@nrc.gov)
BIENNIAL REQUALIFICATION PROGRAM INSPECTION DOCUMENT REQUEST
FROM: Mr. Sean Hedger
Operations Engineer, NRC RIV
817-200-1556
TO: Mr. Brendan Ryan
Licensed Supervising Instructor, Operations Training -
Simulator and NRC Exams
Wolf Creek Generating Station
620-364-8831, ext. 5058
SUBJECT: INFORMATION REQUEST TO SUPPORT OCTOBER 6-10, 2014, LICENSED
OPERATOR REQUALIFICATION PROGRAM INSPECTION (IP 71111.11B)
A. The following information is requested in order to support inspection preparation
activities. These items are listed by section as they appear in the inspection module
(i.e., 2.02, 2.04, etc.). Requested materials should be sent either electronically or
hardcopy in order to arrive at the Region IV office no later than September 26, 2014.
- Electronically: via IMS Certrec or email (to Sean.Hedger@nrc.gov,
Gabriel.Apger@nrc.gov, and Michael.Kennard@nrc.gov)
- Hardcopy to: U.S. Nuclear Regulatory Commission, Region IV
1600 E. Lamar Blvd
Arlington, TX 76011
ATTN: Sean D. Hedger
General Requests:
- List of licensed operators, both senior reactor operator (SRO) and reactor
operator (RO), by crew (operating and staff).
- Training and Operations Department organization charts [with qualified licensed
operator requalification (LOR) evaluators identified].
- Procedures that identify process for revising and maintaining licensed operator
continuing training program up-to-date.
- List of outstanding LOR program changes.
- List of plant events and industry operating experience incorporated into LOR
program since last biennial requalification (BRQ) inspection.
- Audits and/or self-assessment reports addressing the licensed operator
requalification training program.
- Last two years of simulator review committee (or equivalent) meeting minutes.
- Last two years of curriculum review committee (or equivalent) meeting minutes.
Enclosure
02.03: Biennial Requalification Written Examination Quality
- The current and approved biennial written examination schedule.
have already been administered up to the week prior to the inspection team arrival
on-site.
- All written examinations that have been approved for administration up to and
including the week before the inspection team is on-site. (This will need to have
adequate password protection if e-mailed or double envelope protection if mailed via
regular mail per NUREG-1021.)
- The current requalification cycle examination methodology (sample plan).
02.04: Annual Requalification Operating Test Quality
- The schedule for the operating tests [job performance measures (JPMs) & scenarios]
to be given the week of October 6, 2014 (week team is on-site).
- The operating tests (JPMs & scenarios) (password protected and provide separately
via telephone at later date) to be given the week of October 6, 2014 (week team is
on-site).
prior to the inspection team arrival on-site.
- All of the previous years NRC required annual operating tests.
- Current requalification cycle operating test methodology (sample plan).
- All portions of the Updated Final Safety Analysis Report that identify operator
response times for time critical operator actions.
02.05: Licensee Admin of Requalification Exams
- All procedures used to administer the annual operating test.
- All procedures used to assess operator performance.
- All procedures that describe conduct of simulator training.
- All procedures used to test, operate, and maintain the simulator.
02.06: Requalification Examination Security
- Submit any tracking tools that you use as a means to prevent excessive overlap on
the written examinations and also meet the intent of sampling all required topics on a
periodic basis.
- Submit any tracking tools that you use as a means to prevent excessive overlap on
the operating tests and also meet the intent of sampling all required malfunctions
(including major events, instrument/component malfunctions, technical specification
calls, etc.) on a periodic basis.
- All procedures that describe examination security, including procedures used to
develop the examinations that include guidelines on overlap between examinations
in current exam cycle tests and prior year examinations.
- List of all condition reports since the last biennial requalification inspection related to
examination security and overlap.
-2-
02.07: Licensee Remedial Training Program
- List of remedial training conducted or planned since last requalification exams
(includes training provided to operators to enable passing requalification exams and
training provided to correct generic or individual weaknesses observed during
previous requalification exam cycle).
- Remediation plans (lesson plans, reference materials, and attendance
documentation).
02.08: Conformance with Operator License Conditions
- All procedures and program documentation for maintaining active operator licenses,
tracking training attendance, and ensuring medical fitness of licensed operators.
- All procedures and associated documentation that supports reactivation of any
SRO/RO license (operating or staff crew) since the last biennial inspection.
02.09: Simulator Performance
- For the following cases, send the most recent transient test packages, which may
be electronic or in paper single test packages and shall be complete with test
procedures for each test, the acceptance criteria, and results. For each transient
test, the reference chart should be included or an equivalent subject matter expert
review versus the simulator results with a write-up for any differences beyond the
American National Standards Institute (ANSI) 3.5 standard requirements. Based
on the input that the licensee implements simulator testing standards per
ANSI 3.5-2009, provide this information for the following Transient and Steady
State tests:
o Transient test 2, Simultaneous trip of all feedwater pumps.
o Transient test 6, Main turbine trip from maximum power level which does not
result in immediate reactor trip.
o Transient test 10, Slow primary system depressurization to saturated condition
with pressurizer relief or safety valve stuck open (inhibit activation of high
pressure emergency core cooling system).
o Steady State tests for medium power test.
- All simulator management and configuration procedures if not already provided for
Section 02.05 above.
- Simulator Discrepancy Report (DR) summary list for all open DRs. For closed DRs,
summary list for those items closed between October 2012 and October 2014.
- Malfunction tests for loss of condenser vacuum and loss of normal feedwater normal
feedwater system failure. If these are in a scenario based training package then the
review of that package would be acceptable.
- Primary parameters tested in order to verify core physics parameters [such as
moderator temperature coefficient (MTC), integral rod worth (IRW)]. The applicable
reference graphs from the Plant physics data book (electronic or other means as
available) should also be included as well as the test procedures used and the
acceptance criteria with results.
-3-
02.10: Problem Identification and Resolution
- A summary report of all condition reports related to operator actions/errors in the
control room.
- Any revised requalification training that was based on licensed operator performance
issues.
- Copies of Condition Reports 58233, 59491, 68711, 79701, 75336, 80353, and
82469.
- Copies of condition reports related to Licensee Event Reports (LERs) 2013-003-00,
2013-008-00, and 2014-001-00.
- Any causal analysis prepared to address the licensed operator performance issues
identified between 2012 and present, starting with the 2012 biennial requalification
exam failure rates Green finding.
B. The following information is requested in order to support the on-site inspection
activities. Requested materials should be available to the inspection team, either
electronically or hardcopy, upon site arrival on October 6, 2014.
02.02: Exam Results / 02.03 and 02.04: Written Exam and Op Test Quality
- All Operating tests (JPMs & scenarios) to be given in all subsequent weeks after
on-site week.
- All results up to the day the team leaves the site.
02.08: Conformance with Operator License Conditions
- Access to licensed operators records (operating and staff crews).
- Access to licensed operators training attendance records.
- Access to licensed operators medical records.
02.09: Simulator Performance
- Simulator discrepancies from October 2012 to October 2014. This should include all
open DRs and DRs that have been closed, including the documentation/justification
for closure.
- Acceptance test documentation, including hardware and software model revisions at
the time of acceptance (as available).
- Documentation that validates current models, including the thermal-hydraulics and
neutronics models, to the actual plant.
- All current model deficiencies, including Final Safety Analysis Report vs. Design
differences in the simulator (any documentation on this).
- Summary list of modifications from October 2012 to October 2014.
- Plant Modifications (both hardware and software) completed on the Simulator by due
date from October 2012 to October 2014.
- Simulator Differences Lesson plan used in training (current to October 6, 2014).
- The complete book of all Simulator annual performance test packages (usually in a
single book, but may be electronic or in single test packages), complete with all
transient tests, steady state tests, and malfunction tests. This should also include
the test procedures for each test, the acceptance criteria, and results. For each
transient test, the reference chart should be included or an equivalent subject matter
expert review versus the simulator results with a write-up for any differences beyond
the ANSI standard requirements.
-4-
- All test packages used to verify core physics parameters (such as MTC, IRW). The
applicable reference graphs from the Plant physics data book (electronic or other
means as available) should also be included as well as the test procedures used and
the acceptance criteria with results.
- All simulator test, configuration management, and related documents available in the
room for inspectors to review. This includes training needs analysis packages,
simulator review committee meeting minutes, etc.
- Current copy of ANSI 3.5 standard you are committed to for simulator testing.
02.10: Problem Identification and Resolution
- All condition reports related to operator actions/errors in the control room.
C. Wolf Creek Generating Station is required to send the final results summary and any
remaining exams and operating tests that have not been reviewed to the regional
office lead inspector for this inspection for final review and comparison against the
Significance Determination Tools in order to communicate the exit results for the
inspection.
-5-