|
---|
Category:Inspection Plan
MONTHYEARML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22249A2552022-06-29029 June 2022 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000482/2022012 ML22130A7662022-05-10010 May 2022 Notification of Inspection (NRC Inspection Report 05000482/2022003) and Request for Information IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML22019A0932022-01-19019 January 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000482/2022002) and Request for Information ML21322A2952021-11-19019 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000482/2022001 and Request for Information ML21237A5212021-09-0101 September 2021 Wc Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21132A1032021-05-12012 May 2021 Document Request List, Paperwork Reduction Act Statement ML21123A0412021-05-0505 May 2021 Notification of NRC Design Bases Assurance Inspection (Teams) (05000482/2021010) and Initial Request for Information IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) ML21061A3412021-02-25025 February 2021 Request for Information: Wolf Creek Nuclear Station, Dated February 11, 2021, Inspection Report 05000482/2021002 Occupational Radiation Safety Inspection-1, 2, PI ML21026A1982021-01-26026 January 2021 Inservice Inspection Request for Information ML20104C1472020-04-13013 April 2020 Notification of Inspection (NRC Inspection Report 05000482/2020003) and Request for Information ML20099G9422020-04-0808 April 2020 Notification of NRC Biennial Problem Identification and Resolution Inspection (05000482/2020010) and Initial Request for Information ML20055E1132020-03-0303 March 2020 WC2019006 Annual Assessment Letter ML20024D7072020-01-24024 January 2020 Notification of NRC Design Bases Assurance Inspection (Programs) (05000482/2020011) and Initial Request for Information IR 05000482/20190052019-08-30030 August 2019 Updated Inspection Plan for Wolf Creek Generating Station, Report 05000482/2019005 ML19158A0782019-06-0505 June 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2019003) and Request for Information IR 05000482/20180062019-03-0404 March 2019 Annual Assessment Letter for Wolf Creek Report 05000482/2018006) ML19043A9462019-02-12012 February 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000482/2019002) and Request for Information IR 05000482/20180052018-08-31031 August 2018 Updated Inspection Plan for Wolf Creek Generating Station, Unit 1, (Inspection Report 05000482/2018005) IR 05000482/20170062018-03-0101 March 2018 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006) ML17311A5182017-11-0101 November 2017 Notification of NRC Inspection of Implementation of Mitigation Strategies Assessment Plans (05000482/2018008) and Request for Information IR 05000482/20170052017-08-28028 August 2017 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) IR 05000482/20160062017-03-0101 March 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016006) IR 05000482/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) ML16237A0732016-08-31031 August 2016 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) IR 05000482/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Reports Number 05000482/2016401) ML16085A0532016-03-25025 March 2016 Operating Corp - Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2016002) and Request for Information IR 05000482/20150062016-03-0202 March 2016 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015006) IR 05000482/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015005) ML15015A1712015-01-0808 January 2015 Focused Baseline Inspection at the Wolf Creek Site for a Major Essential Service Water Modification IR 05000482/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Report Number 05000482/2014402) IR 05000482/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2014006) ML14231A0682014-08-19019 August 2014 Notification of Inspection (NRC Inspection Report 05000482-14-005) and Request for Information ML14063A6282014-03-0404 March 2014 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2013001) ML13246A2992013-09-0303 September 2013 Midcycle Assessment Letter 2013 IR 05000482/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station (05000482/2012006) 2024-08-14
[Table view] Category:Letter
MONTHYEARIR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 ML24050A0012024-02-19019 February 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) 2024-09-06
[Table view] |
Text
September 1, 2021
Mr. Cleve Reasoner, Chief Executive Officer and Chief Nuclear Officer Wolf Creek Nuclear Operating Corp.
P.O. Box 411 Burlington, KS 66839
SUBJECT:
UPDATED INSPECTION PLAN FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2021005)
Dear Mr. Reasoner:
The enclosed inspection plan lists the inspections scheduled through June 30, 2023, for the Wolf Creek Generating Station. The U.S. Nuclear Regulatory Commission ( NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspect ors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Inspection procedure (IP) 71111.21N.03 is included in the inspection plan as a placeholder for your next Design Basis Assurance Inspection (Programs). The NRC is still determining the specific technical area to replace the previously performed power-operated valves programs inspection, IP 71111.21N.02. Once the inspection area has been determined, an inspection procedure will be issued publicly at least six months prior to the start of this inspection.
In response to the COVID -19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the Reactor Oversight Process ( ROP). Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of C. Reasoner 2
both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
On July 18, 2019, the NRC issued a Confirmatory Order (EA 165) documenting the commitments made as part of a settlement agreement between Wolf Creek and the NRC. The settlement agreement relates to the apparent violation of NRC requirements as discussed in our letter dated April 2, 2019 (ADAMS Accession No. ML19092A335). That letter provided you with the results of an investigation conducted by the NRC's Office of Investigations at the Wolf Creek Generating Station to determine whether a maintenance worker and a supervisor willfully documented inaccurate information in a required record regarding the cleaning and inspection of control rod drive mechanisms on October 31, 2016. Therefore, the NRC plans to conduct Inspection Procedure 92702, Follow Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders to follow up on your actions to address these commitments. The schedule for this inspection will be decided at a later date since the Confirmatory Order contains actions that are due in 2023.
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections is being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.
Additionally, during this period the NRC will perform an additional inspection per a revised version of Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012- 01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (Accession No. ML19163A176),
which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition.
Licensees will be individually notified when the NRC schedules these inspections.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for
C. Reasoner 3
public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200- 1141 with any questions you have regarding this letter.
Sincerely,
Neil F. OKeefe, Chief Reactor Projects Branch B Division of Reactor Projects
Docket No. 05000482 License No. NPF-42
Enclosure:
Inspection Plan
cc w/ encl: Distribution via LISTSERV
ML 21237A521 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: Yes No Publicly Available Sensitive NRC-002 OFFICE PE:DRP/PBB SPE:DRP/PBB BC:DRP/PBB NAME JMelfi JM DProulx DLP NOKeefe nfo DATE 08/23/2021 08/23/2021 09/01/2021 IP 22b Site Inspection Activity Plan 07200079 - Wolf Creek
07/01/2021 - 06/30/2023
Unit Start End Activity CAC Title Staff Count
Wolf Creek ISFSI Programs 72.212 Inspection (1 week in August) 6
1 7/1/2021 9/30/2021 IP 60856 001003 Review of 10 CFR 72.212(b) Evaluations
Wolf Creek ISFSI Dry Runs and First Loading Inspection (May be 3 trips in July-Sep) 2
1 10/1/2021 12/31/2021 IP 60854 001000 Preoperational Testing Of An ISFSI
1 10/1/2021 12/31/2021 IP 60855 001001 Operation Of An ISFSI
ISFSI Initial Security Inspection, Pre-loading, IP 81311 1
1 10/4/2021 10/8/2021 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations
Prepared on 8/18/2021 2:01:18 PM 1 of 4 IP 22b Site Inspection Activity Plan Wolf Creek
07/01/2021 - 06/30/2023
Unit Start End Activity CAC Title Staff Count
Design Bases Assurance (Team) 21M - Wolf Creek 6
1 7/19/2021 8/6/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - WC 6
1 8/30/2021 9/3/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
1 9/20/2021 9/24/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing
In-Office EP Exercise Scenario Review - WC 4
1 9/5/2021 10/17/2021 IP 71114.08 000723 Exercise Evaluation Scenario Review
Wolf Creek ISFSI Dry Run and 1st Loading Inspection (Part 50) Feeder to Residents 2
1 10/1/2021 10/31/2021 IP 60854 001000 Preoperational Testing Of An ISFSI
1 10/1/2021 10/31/2021 IP 60855 001001 Operation Of An ISFSI
RP 2,4 2
1 10/4/2021 10/8/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls
1 10/4/2021 10/8/2021 IP 71124.04 000728 Occupational Dose Assessment
TI 2515/194 - WC 2
1 10/18/2021 10/22/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
EP Biennial Exercise and PI Inspection - WC 4
1 11/15/2021 11/19/2021 IP 71114.01 000716 Exercise Evaluation
1 11/15/2021 11/19/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
1 11/15/2021 11/19/2021 IP 71151 001397 Performance Indicator Verification
Security Access Control.02 1
1 2/28/2022 3/4/2022 IP 71130.02 000734 Access Control
1 2/28/2022 3/4/2022 IP 71151 001338 Performance Indicator Verification
1 3/28/2022 4/1/2022 IP 71130.09 001656 Security Plan Changes
Heat Exchanger/Sink Performance Inspection - 07T - Wolf Creek 2
1 3/7/2022 3/11/2022 IP 71111.07T 000700 Heat Sink Performance
Wolf Creek Biennial PI&R 4
1 3/14/2022 3/18/2022 IP 71152B 000747 Problem Identification and Resolution
1 3/28/2022 4/1/2022 IP 71152B 000747 Problem Identification and Resolution
10 CFR 50.59 Inspection - 17T - Wolf Creek 3
1 4/11/2022 4/15/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments
Security Protective Strategy.05 2
Prepared on 8/18/2021 2:01:18 PM 2 of 4 IP 22b Site Inspection Activity Plan
1 6/20/2022 6/24/2022 IP 71130.05 000737 Protective Strategy Evaluation
RP 5,8 2
1 7/18/2022 7/22/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation
1 7/18/2022 7/22/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation
Security Training/Equip Maint.07 and.04 2
1 7/18/2022 7/22/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
1 7/18/2022 7/22/2022 IP 71130.07 000739 Security Training
MC&A 1
1 7/18/2022 7/22/2022 IP 71130.11 000742 Material Control and Accounting (MC&A)
WC 2022 BRQ 3
1 7/24/2022 7/30/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance
Cyber Security Inspection - WC 4
1 8/1/2022 8/5/2022 IP 71130.10P 000741 Cyber Security
EP Program & PI Inspection - WC 1
1 8/29/2022 9/2/2022 IP 71114.02 000717 Alert and Notification System Testing
1 8/29/2022 9/2/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
1 8/29/2022 9/2/2022 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
1 8/29/2022 9/2/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness
1 8/29/2022 9/2/2022 IP 71151 001397 Performance Indicator Verification
Inservice Inspection RF25 - WC 1
1 9/29/2022 10/14/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,2,PI 2
1 10/3/2022 10/7/2022 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
1 10/3/2022 10/7/2022 IP 71124.02 000726 Occupational ALARA Planning and Controls
Design Bases Assurance Inspection (Program) - 21N - Wolf Creek 3
1 1/1/2023 6/30/2023 IP 71111.21N.03 Design Bases Assurance Inspections (Programs) 2023
Security Access Authorization.01 and Access Control.02 + PIV + Plan Change.09 2
1 1/23/2023 1/27/2023 IP 71130.01 000733 Access Authorization
1 1/23/2023 1/27/2023 IP 71130.02 000734 Access Control
1 1/23/2023 1/27/2023 IP 71130.09 001656 Security Plan Changes
1 1/23/2023 1/27/2023 IP 71151 001338 Performance Indicator Verification
RP 2,4 2
1 3/13/2023 3/17/2023 IP 71124.02 000726 Occupational ALARA Planning and Controls
1 3/13/2023 3/17/2023 IP 71124.04 000728 Occupational Dose Assessment
Security FFD.08 1
Prepared on 8/18/2021 2:01:18 PM 3 of 4 IP 22b Site Inspection Activity Plan
1 5/22/20235/26/2023 IP 71130.08 000740 Fitness For Duty Program
Prepared on 8/18/2021 2:01:18 PM 4 of 4