Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005)
ML17242A207
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 08/28/2017
From: Nick Taylor
NRC/RGN-IV/DRP/RPB-B
To: Heflin A
Wolf Creek
NICK TAYLOR
References
IR 2017005
Download: ML17242A207 (5)


Text

August 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2017005)

Dear Mr. Heflin:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for Wolf Creek Generating Station. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. This inspection will be conducted at Wolf Creek Generating Station to confirm the stations full implementation of Commission Orders EA-12-049 and EA-12-051.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511

A. Helflin

public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (817) 200-1141 with any questions you have regarding this letter.

Sincerely,

/RA D. Proulx for/

Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 05000482 License No. NPF-42 Enclosure:

Wolf Creek Generating Station Inspection Plan

SUNSI Review ADAMS:

Non-Publicly Available Non-Sensitive Keyword-NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE

/RA/

/RA DProulx for/

DATE 8/28/17 8/28/17

Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Wolf Creek Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 1 of 2 08/25/2017 08:25:55 INIT EXA

- INITIAL EXAM

1 INITIAL EXAM WOLF CREEK (11/2017)

X02597 10/16/2017 10/20/2017

INITIAL EXAM WOLF CREEK (11/2017)

X02597 11/06/2017 11/10/2017 EB1-21N

- WC DESIGN BASIS INSPECTION PROGRAMS

1 IP Design Bases Assurance Inspection (Programs)

7111121N 05/08/2017 07/13/2017 PI&R

- PI&R FOCUSED SAMPLE - SCWE

1 IP In-depth Reviews 71152-Reviews 08/29/2017 08/30/2017 EB2-05T

- TRIENNIAL FIRE PROTECTION INSPECTION

1 IP Fire Protection [Triennial]

7111105T 10/02/2017 10/06/2017

IP Fire Protection [Triennial]

7111105T 10/16/2017 10/20/2017 EP-2

- BIENNIAL EP EXERCISE INSPECTION

1 IP Exercise Evaluation 7111401 11/13/2017 11/17/2017

IP Emergency Action Level and Emergency Plan Changes 7111404 11/13/2017 11/17/2017 EP-3

- EP PERFORMANCE INDICATOR VERIFICATION

1 IP Drill/Exercise Performance 71151-EP01 11/13/2017 11/17/2017

IP ERO Readiness 71151-EP02 11/13/2017 11/17/2017

IP Alert & Notification System Reliability 71151-EP03 11/13/2017 11/17/2017 TI191

- MITIGATING STRATEGIES/SFP INST FOR BDBEE

1 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 01/22/2018 01/26/2018 7111108

- INSERVICE INSPECTION

1 IP Inservice Inspection Activities - PWR 7111108P 04/02/2018 04/13/2018 RS 12PI

- RAD SAFETY

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/09/2018 04/13/2018

IP Occupational ALARA Planning and Controls 71124.02 04/09/2018 04/13/2018

IP Occupational Exposure Control Effectiveness 71151-OR01 04/09/2018 04/13/2018

IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 04/09/2018 04/13/2018 INSP

- BRQ INSPECTION

1 IP Licensed Operator Requalification Program 7111111B 06/04/2018 06/08/2018 PI&R

- BIENNIAL PI&R INSPECTION

1 IP Problem Identification and Resolution 71152B 06/11/2018 06/15/2018

IP Problem Identification and Resolution 71152B 06/25/2018 06/29/2018 EB1-21M

- WC DESIGN BASES INSPECTION TEAMS

1 IP Design Bases Assurance Inspection (Teams)

7111121M 07/16/2018 08/03/2018 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Wolf Creek Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 2 of 2 08/25/2017 08:25:55 RS 5678

- RAD SAFETY

1 IP Radiation Monitoring Instrumentation 71124.05 08/20/2018 08/24/2018

IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 08/20/2018 08/24/2018

IP Radiological Environmental Monitoring Program 71124.07 08/20/2018 08/24/2018

IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 08/20/2018 08/24/2018 EP-1

- EP PROGRAM INSPECTION

1 IP Alert and Notification System Testing 7111402 09/17/2018 09/21/2018

IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 09/17/2018 09/21/2018

IP Emergency Action Level and Emergency Plan Changes 7111404 09/17/2018 09/21/2018

IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 09/17/2018 09/21/2018

IP Drill/Exercise Performance 71151-EP01 09/17/2018 09/21/2018

IP ERO Readiness 71151-EP02 09/17/2018 09/21/2018

IP Alert & Notification System Reliability 71151-EP03 09/17/2018 09/21/2018 EB1-17T

- WOLF CREEK 10CFR50.59 INSPECTION

1 IP Evaluations of Changes, Tests, and Experiments 7111117T 04/29/2019 05/03/2019 RS 24

- RP INSPECTION

1 IP Occupational ALARA Planning and Controls 71124.02 05/06/2019 05/10/2019

IP Occupational Dose Assessment 71124.04 05/06/2019 05/10/2019 EP-2

- EP EXERCISE INSPECTION

1 IP Exercise Evaluation 7111401 06/03/2019 06/07/2019

IP Emergency Action Level and Emergency Plan Changes 7111404 06/03/2019 06/07/2019

IP Drill/Exercise Performance 71151-EP01 06/03/2019 06/07/2019

IP ERO Readiness 71151-EP02 06/03/2019 06/07/2019

IP Alert & Notification System Reliability 71151-EP03 06/03/2019 06/07/2019 EP2

- EP EXERCISE AND PI INSPECTION

1 IP Exercise Evaluation 7111401 06/03/2019 06/07/2019

IP Emergency Action Level and Emergency Plan Changes 7111404 06/03/2019 06/07/2019

IP Drill/Exercise Performance 71151-EP01 06/03/2019 06/07/2019

IP ERO Readiness 71151-EP02 06/03/2019 06/07/2019

IP Alert & Notification System Reliability 71151-EP03 06/03/2019 06/07/2019 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.