MONTHYEARML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24018A1382024-01-18018 January 2024 Inservice Inspection Request for Information IR 05000482/20230052023-08-23023 August 2023 Updated Inspection Plan for Wolf Creek Nuclear Operating Corporation, Unit 1 (Report 05000482/2023005) - Mid-Cycle Letter 2023 IR 05000482/20220062023-03-0101 March 2023 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2022006) ML22321A2662022-11-16016 November 2022 January 2023 Emergency Preparedness Program Inspection - Request for Information IR 05000482/20220052022-08-23023 August 2022 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2022005) ML22215A2742022-08-0202 August 2022 Inservice Inspection Request for Information ML22249A2552022-06-29029 June 2022 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000482/2022012 ML22130A7662022-05-10010 May 2022 Notification of Inspection (NRC Inspection Report 05000482/2022003) and Request for Information IR 05000482/20224012022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 ML22123A2702022-05-0303 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000482/2022401 IR 05000482/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000482/2021006) ML22025A3612022-01-21021 January 2022 PI&R RFI Final ML22019A0932022-01-19019 January 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000482/2022002) and Request for Information ML21322A2952021-11-19019 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000482/2022001 and Request for Information ML21237A5212021-09-0101 September 2021 Wc Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21132A1032021-05-12012 May 2021 Document Request List, Paperwork Reduction Act Statement ML21123A0412021-05-0505 May 2021 Notification of NRC Design Bases Assurance Inspection (Teams) (05000482/2021010) and Initial Request for Information IR 05000482/20190062021-03-0303 March 2021 Annual Assessment Letter (Report 05000482/2019006) ML21061A3412021-02-25025 February 2021 Request for Information: Wolf Creek Nuclear Station, Dated February 11, 2021, Inspection Report 05000482/2021002 Occupational Radiation Safety Inspection-1, 2, PI ML21026A1982021-01-26026 January 2021 Inservice Inspection Request for Information ML20104C1472020-04-13013 April 2020 Notification of Inspection (NRC Inspection Report 05000482/2020003) and Request for Information ML20099G9422020-04-0808 April 2020 Notification of NRC Biennial Problem Identification and Resolution Inspection (05000482/2020010) and Initial Request for Information ML20055E1132020-03-0303 March 2020 WC2019006 Annual Assessment Letter ML20024D7072020-01-24024 January 2020 Notification of NRC Design Bases Assurance Inspection (Programs) (05000482/2020011) and Initial Request for Information IR 05000482/20190052019-08-30030 August 2019 Updated Inspection Plan for Wolf Creek Generating Station, Report 05000482/2019005 ML19158A0782019-06-0505 June 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2019003) and Request for Information IR 05000482/20180062019-03-0404 March 2019 Annual Assessment Letter for Wolf Creek Report 05000482/2018006) ML19043A9462019-02-12012 February 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000482/2019002) and Request for Information IR 05000482/20180052018-08-31031 August 2018 Updated Inspection Plan for Wolf Creek Generating Station, Unit 1, (Inspection Report 05000482/2018005) IR 05000482/20170062018-03-0101 March 2018 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006) ML17311A5182017-11-0101 November 2017 Notification of NRC Inspection of Implementation of Mitigation Strategies Assessment Plans (05000482/2018008) and Request for Information IR 05000482/20170052017-08-28028 August 2017 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) IR 05000482/20160062017-03-0101 March 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016006) IR 05000482/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) ML16237A0732016-08-31031 August 2016 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2016005) IR 05000482/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Reports Number 05000482/2016401) ML16085A0532016-03-25025 March 2016 Operating Corp - Notification of NRC Triennial Heat Sink Performance Inspection (05000482/2016002) and Request for Information IR 05000482/20150062016-03-0202 March 2016 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015006) IR 05000482/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2015005) ML15015A1712015-01-0808 January 2015 Focused Baseline Inspection at the Wolf Creek Site for a Major Essential Service Water Modification IR 05000482/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Wolf Creek Generating Station (NRC Physical Security Inspection Report Number 05000482/2014402) IR 05000482/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Wolf Creek Generating Station (Report 05000482/2014006) ML14231A0682014-08-19019 August 2014 Notification of Inspection (NRC Inspection Report 05000482-14-005) and Request for Information ML14063A6282014-03-0404 March 2014 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2013001) ML13246A2992013-09-0303 September 2013 Midcycle Assessment Letter 2013 2024-08-14
[Table view] Category:Letter
MONTHYEARML24306A2192024-11-0101 November 2024 Results of the Steam Generator Tube Inservice Inspection During the 26th Refueling Outage to Reflect TSTF-577 Reporting Requirements IR 05000482/20244202024-10-31031 October 2024 Security Baseline Inspection Report 05000482/2024420 ML24296B1902024-10-22022 October 2024 10 CFR 50.55a Requests for the Fifth Ten-Year Interval Inservice Testing Program 05000482/LER-2024-001-01, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-10-22022 October 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing 05000482/LER-2024-002, Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve2024-10-21021 October 2024 Technical Specification Required Shutdown Due to Inoperable Auxiliary Feedwater Discharge Valve ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24283A0752024-10-0909 October 2024 Notification of Commercial Grade Dedication Inspection (05000482/2025012) and Request for Information ML24199A1712024-09-17017 September 2024 Issuance of Amendment No. 241 Revise Ventilation Filter Testing Program Criteria and Administrative Correction of Absorber in Technical Specification 5.5.11 ML24260A0712024-09-12012 September 2024 License Amendment Request for a Risk-Informed Resolution to GSI-191 IR 05000482/20240102024-09-10010 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000482/2024010 (Public) ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24248A2492024-09-0404 September 2024 Inservice Inspection Program Fourth Interval, Third Period, Refueling Outage 26 Owner’S Activity Report ML24248A0762024-09-0404 September 2024 Containment Inservice Inspection Program Third Interval, Second Period, Refueling Outage 26 Owner’S Activity Report ML24241A2212024-08-29029 August 2024 Notice of Enforcement Discretion for Wolf Creek Generating Station ML24240A2642024-08-27027 August 2024 Corporation - Request for Notice of Enforcement Discretion Regarding Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24227A5562024-08-14014 August 2024 Application to Revise Technical Specifications to Adopt TSTF-569-A, Revision 2, Revision of Response Time Testing Definitions ML24213A3352024-07-31031 July 2024 License Amendment Request to Revise Technical Specification 3.2.1, Heat Flux Hot Channel Factor (Fq(Z)) (Fq Methodology), to Implement the Methodology from WCAP-17661-P-A, Revision 1. ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) IR 05000482/20240022024-07-18018 July 2024 Integrated Inspection Report 05000482/2024002 05000482/LER-2024-001, Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing2024-07-0202 July 2024 Mode 3 Entry with One Auxiliary Feedwater Pump Train Inoperable Due to Missed Post-Maintenance Testing IR 05000482/20244012024-07-0202 July 2024 Security Baseline Inspection Report 05000482/2024401 ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24162A1632024-06-11011 June 2024 Operating Corporation – Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000482/2024010) ML24150A0562024-05-29029 May 2024 Foreign Ownership, Control or Influence (FOCI) Information – Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML23345A1602024-05-0909 May 2024 Revision of Safety Evaluation for Amendment No. 237 Request for Deviation from Fire Protection Requirements ML24089A2622024-04-29029 April 2024 Financial Protection Levels ML24118A0022024-04-27027 April 2024 Wolf Generating Nuclear Station - 2023 Annual Radiological Environmental Operating Report ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24113A1882024-04-19019 April 2024 Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment ML24109A1212024-04-18018 April 2024 (WCGS) Form 5 Exposure Report for Calendar Year 2023 ML24109A1842024-04-18018 April 2024 Cycle 27 Core Operating Limits Report IR 05000482/20240012024-04-17017 April 2024 Integrated Inspection Report 05000482/2024001 ML24114A1442024-04-15015 April 2024 Redacted Updated Safety Analysis Report (WCGS Usar), Revision 37 ML24106A1482024-04-15015 April 2024 Notification of Inspection (NRC Inspection Report 05000482/2024003) and Request for Information ML24098A0052024-04-0707 April 2024 2023 Annual Environmental Operating Report ML24089A1352024-03-29029 March 2024 10 CFR 50.46 Annual Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML24089A0972024-03-29029 March 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24074A3312024-03-14014 March 2024 Missed Quarterly Inspection Per 40 CFR 266 Subpart N IR 05000482/20240122024-03-11011 March 2024 Fire Protection Team Inspection Report 05000482/2024012 ML24080A3452024-03-11011 March 2024 7 of the Wolf Creek Generating Station Updated Safety Analysis Report ML24016A0702024-03-0808 March 2024 Issuance of Amendment No. 240 Removal of the Power Range Neutron Flux Rate - High Negative Rate Trip Function from Technical Specifications ML24068A1992024-03-0707 March 2024 Changes to Technical Specification Bases - Revisions 93 and 94 ML24066A0672024-03-0505 March 2024 4-2022-024 Letter - OI Closure to Licensee ML24061A2642024-03-0101 March 2024 Revision of Two Procedures That Implement the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) Commissioners IR 05000482/20230062024-02-28028 February 2024 Annual Assessment Letter for Wolf Creek Generating Station Report 05000482/2023006 ML24059A1702024-02-28028 February 2024 Annual Fitness for Duty Program Performance Report, and Annual Fatigue Report for 2023 ML24026A0212024-02-27027 February 2024 Issuance of Amendment No. 239 Modified Implementation Date of License Amendment No. 238 2024-09-06
[Table view] |
Text
arch 2, 2016
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2015006)
Dear Mr. Heflin:
On February 16, 2016, the Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Wolf Creek Generating Station. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1 through December 31, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Wolf Creek Generating Station operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Wolf Creek Generating Station during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP)
Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e.,
green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2017.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the second half of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event.
Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of a Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations. Following the audit, and after the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191:
Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1141 with any questions you have regarding this letter.
Sincerely,
/RA/
Nick Taylor, Chief Project Branch B Division of Reactor Projects Docket No: 50-482 License No: NPF-42 Enclosure:
Wolf Creek Generating Station Inspection/Activity Plan
ML16061A402 SUNSI Review ADAMS: Sensitive Non-Publicly Available Keyword By: NHT Yes No Non-Sensitive Publicly Available NRC-002 OFFICE RIV/BC/DRP RIV/D/DRS RIV/D/DRP NAME NTaylor AVegel TPruett SIGNATURE /RA/ /RA/ /RA/RLantz, for DATE 2/25/16 2/25/16 2/26/16
Letter to Adam from Nick Taylor dated March 2, 2016 SUBJECT: ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2015005)
DISTRIBUTION:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Douglas.Dodson@nrc.gov)
Resident Inspector (Fabian.Thomas@nrc.gov)
WC Administrative Assistant (Vacant)
Branch Chief, DRP/B (Nick.Taylor@nrc.gov)
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Project Engineer, DRP/B (Shawn.Money@nrc.gov)
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Project Manager (Fred.Lyon@nrc.gov)
Team Leader, DRS/TSS (Thomas.Hipschman@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Raj.Iyengar@nrc.gov)
Director, DIRS, NRR (Scott.Morris@nrc.gov)
Deputy Director, DIRS, NRR (Clay.Johnson@nrc.gov)
Director, DORL, NRR (Anne.Boland@nrc.gov)
Deputy Director, DORL, NRR (George.Wilson@nrc.gov)
Director, DPR (Lawrence.Kokajko@nrc.gov)
Director, NSIR (Brian.Holian@nrc.gov)
DRP Branch Chiefs (R4DRPBC@nrc.gov)
DRS Branch Chiefs (R4DRSBC@nrc.gov)
ROPreports.Resource@nrc.gov ROPassessment.Resource@nrc.gov
Page 1 of 2 Wolf Creek 02/29/2016 15:49:02 Inspection / Activity Plan Report 22 04/01/2016 - 12/31/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB1-21T - WC COMPONENT DESIGN BASIS INSPECTION 6 1 03/28/2016 04/29/2016 IP 7111121 Component Design Bases Inspection EB1-07T - WC HEAT SINK PERFORMANCE 2 1 05/23/2016 05/27/2016 IP 7111107T Heat Sink Performance RS 5678 - RADIATION SAFETY - TEAM 4 1 05/23/2016 05/27/2016 IP 71124.05 Radiation Monitoring Instrumentation 1 05/23/2016 05/27/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 05/23/2016 05/27/2016 IP 71124.07 Radiological Environmental Monitoring Program 1 05/23/2016 05/27/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation TSB 52B - BIENNIAL PI&R INSPECTION 4 1 06/13/2016 06/17/2016 IP 71152B Problem Identification and Resolution 1 06/27/2016 07/01/2016 IP 71152B Problem Identification and Resolution INSP - BIENNIAL REQUAL INSPECTION 2 1 06/27/2016 07/01/2016 IP 7111111B Licensed Operator Requalification Program EP-1 - EP PERFORMANCE INDICATORS 1 1 08/01/2016 08/05/2016 IP 71151-EP02 ERO Readiness 1 08/01/2016 08/05/2016 IP 71151-EP03 Alert & Notification System Reliability 1 08/01/2016 08/05/2016 IP 71151-IE01 Unplanned Scrams per 7000 Critical Hrs EP-2 - BIENNIAL EP PROGRAM INSPECTION 1 1 08/01/2016 08/05/2016 IP 7111402 Alert and Notification System Testing 1 08/01/2016 08/05/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 08/01/2016 08/05/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 08/01/2016 08/05/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies RS 12 PI - RADIATION SAFETY 2 1 10/03/2016 10/07/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/03/2016 10/07/2016 IP 71124.02 Occupational ALARA Planning and Controls 1 10/03/2016 10/07/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 10/03/2016 10/07/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71111.08 - INSERVICE INSPECTION 1 1 10/03/2016 10/14/2016 IP 7111108P Inservice Inspection Activities - PWR INIT EXA - INITIAL EXAM 7 1 10/16/2017 10/20/2017 X02597 INITIAL EXAM WOLF CREEK (11/2017)
1 11/13/2017 11/24/2017 X02597 INITIAL EXAM WOLF CREEK (11/2017)
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Wolf Creek 02/29/2016 15:49:02 Inspection / Activity Plan Report 22 04/01/2016 - 12/31/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RS 13 PI - RADIATION SAFETY 2 1 05/08/2017 05/12/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 05/08/2017 05/12/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 05/08/2017 05/12/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1 05/08/2017 05/12/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences RS 24 - RADIATION SAFETY 2 1 06/12/2017 06/16/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 06/12/2017 06/16/2017 IP 71124.04 Occupational Dose Assessment EB2-05T - TRIENNIAL FIRE PROTECTION INSPECTION 4 1 08/07/2017 08/11/2017 IP 7111105T Fire Protection [Triennia ]
1 08/21/2017 08/25/2017 IP 7111105T Fire Protection [Triennia ]
EP-2 - BIENNIAL EP EXERCISE INSPECTION 4 1 11/13/2017 11/17/2017 IP 7111401 Exercise Evaluation 1 11/13/2017 11/17/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes EP-3 - EP PERFORMANCE INDICATOR VERIFICATION 1 1 11/13/2017 11/17/2017 IP 71151-EP01 Drill/Exercise Performance 1 11/13/2017 11/17/2017 IP 71151-EP02 ERO Readiness 1 11/13/2017 11/17/2017 IP 71151-EP03 Alert & Notification System Reliability This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.