IR 05000354/1986025

From kanterella
Jump to navigation Jump to search
Initial OL Review Rept 50-354/86-25
ML20203P510
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 04/28/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20203P509 List:
References
50-354-86-25, NUDOCS 8605070378
Download: ML20203P510 (66)


Text

_

-

_

_

_

l

-

.

.

-

.

s..

,

'

L, it N

'

.*

,

.s;y

~

-.

,.:N

_~

.,

- -

..

,

.

.

.

.

+g

.

,,

s..

?

A

, :-

-

s E

_

._,

m

,

-

w

.

,

-

.

,.

..

. %

r

-

.

r

,

.

,

-

.

,

x.

,,

3.,

'

,%

t, N*

N

.s

.

-

HOPE CREE'K GENERATIflG STATION INITIALOPERAftNdLICENSEREVIEWREPORT

'.

(50-354/8,6-25).

e

,

%

,

.,'

.

.'

.;,.

'

'

'

N,

..

i

,

N/

s

'

,

'

.

%

-

r,

.

,'

,

,

-

k

.

8605070378 860428 PDR ADOCK 05000354 G

PDR

!

' '

.

--

- - _. _ _ _ _ _ _ _ _. - - - _ _ - _ _ _ _ _ _ _. - - - - _ _ _ - - -

. _ _ -

.

.-

SUMMARY FOR HOPE CREEK Inspection Date/No. of No.

Inspectors Areas Findings 73-05 11/27-20/73 Meeting to outline NRC inspec-Several

tion functions and review of storage de-storage procedures and their ficiencies implementation, were identi-fied both with records and equipments.

74-02 6/19/74 QA program implementation

75-01 2/4-6/75 Long term storage.

Storage Vio-

lations of:

10 CFR 50, Appendix Criterion XVI Criterion XVIII.

75-02 8/12-14/75 Long term storage and site QA

activities.

75-03 11/25-26-75 Determination of status of site None I

construction and staffing and resolution of open items.

76-01 1/15-16 Review of receipt inspection and None 1/22/76 handling procedures for reactor

pressure vessel.

76-02 2/24-25/76 Environmental.

None

76-03 3/5/76 Reactor vessel handling and None

related procedures.

76-04 8/19-20/76 Dewatering, excavation, ground None

water control, and foundation requirement.

.

Enclosure 4

76-05 9/22-24/76 QA manuals reviewed to determine None

the basic requirements of the QA program and consistency with PSAR commitments.

76-06 11/18-19/76 Reactor vessel handling activi-None

ties.

76-07 12/8-10/76 Dewatering, excavation, speci-None 12/13/76 fications for concrete batch I

plant and test lab.

77-01 2/8-9/77 Document control and groundwater None

control procedures and site preparation work activities and quality rccords.

77-02 2/22-25/77 Inspection of the quality aspects None 3/7/77 of the excavation and dewatering I

work, work activities as related to foundations, concrete batch plant activities, and civil /

structural lab activities.

77-03 3/15-16/77 Environmental monitoring.

None

77-04 4/20-22/77 Dewatering, foundations, soils None

testing, backfill records, batch plant and solid test lab certi-fications, concrete specs, and civil QC inspection plans.

77-05 5/5-6/77 Implementation of contractor's None

and subcontractor's QA manuals.

77-06 7/13-15/77 Reactor vessel storage and None

related records, implementation of concrete OA procedures.

77-07 7/27-29/77 Onsite and offsite equipment None

storage, Bechtel and PSE&G QA audits.

77-08 8/2-5/77 Installation of rebar and cad-None

weld splices for reactor basemat, review of cadwelder qualifications

'

and cadweld inspection requirements, l

backfill records.

l

.

-

-

- -

-

.

. - -

- - - -

-

- - - - - - -

-

-

-

-

-

-

- -

- - -

.

,,

Enclosure 4

,.

77-09 8/9-11/77 QA program for primary containment None

_77-10 9/6-7/77 Concrete placement of basemat 1 Violation 9/12-14/77 section of power block.

Failure to

follow proce-dures during concrete placement 77-11 9/27-28/77 Bulletin and Circular Review.

None

77-12 10/19-21/77 Storage and maintenance procedure None

reviews, installation of structural steel, storage of steel and equip-rrent, applicant's audit program.

77-13 11/7-10/77 Concrete placement, cadwelding, None-11/14/77 removal of defective concrete,

review of concrete records.

77-14'

12/14/77 Status review of construction None

and schedule.

78-01 1/31/78 Concrete activities, rebar None 2/1-1/78 installation, ground water control I

records, batch plant audits.

78-02 2/15/78 In process work and records review None

of containment erection, st; rage, receiving.

78-03 3/8-10/78 Environmental 1 Violation

Discharging motor oil to

.

the river 78-04 3/15-17/78 M&TE program, QC and audit Improper

'

personnel qualification records, issuance of QC subcontractor surveillance, material supports.

instruction 78-05-3/21-23/78 Concrete activities, concrete /

None I

soils test l'

78-06 4/11-14/78 QC program for reactor vessel None

storage,10 CFR 21 program,

vendor documentation for

'

structural embedments, sub-contractors' QA/QC procedures.

-

.

Endlosure4~

.

-78-07 5/2-4/78 Containment erection, concrete None

placement, backfill.

78-08 5/24-25/78 Applicant's audit program, None Bulletin and Circular review, Dames & Moore QA program, and

,10 CFR 21 conformance program.

78-09 6/6-9/78 QC program.for concrete place-None

ment, cement storage, equipment stora5e, structural steel documentation, CDR reporting 78-10 7/11-14/78 QC program for mechanical None

equipment, spacer material for structural joints.

78-11 7/31-8/3/78 Concrete placement activities, None I

qualification and training of QC personnel, inspection of honeycomb voids in concrete partition wall.

78-12 8/21-23/78 QC program for concrete place-None

ment, storage and maintenance of reactor vessel and reactor internals.

78-13 10/16-18/78 Fabrication and installation None

of torus.

78-14-11/18-30/78 QC programs for piping and None

structural steel, weld material control, examination of radio-graphs, soils, concrete lab QA program and its implementation.

79-01 1/30-2/1/79 QC program for structural steel None

79-02 2/27-3/1/79 QC program for installation of None

pipe hangers and supports, containment fabrication and i

erection.

i 79-03 4/16-19/79 QC program for fabrication and 1 Viol.

installation of containment Inadequate penetrations, structural steel storage of

equipment supports, containment penetra--

welding.

tion pipes l

!

-

.

-

... ~

.

a

..

Enclosure 4 5-

. 2 79-04-9/12-14/79 Receipt, installation, and 1 Viol.

I welding of safety-related piping.. Failure to perform required surface examina-tion 79-05 6/18-21/79 QC program for structural welding; None 4'

pipe welding; receipt and storage of equipment.

79-06 7/31-8/2/79 QC program for installation and-None

welding of piping 79-07 8/25-27/79 Bulletin and Circular review, ifViol.

review of ASME Certificates of.

Inade-Authorization.

quate correc-tive actions in response-to non-confor-mances 79-08 10/30-11/2/79 Structural integrity test None

79-09 11/26-30/79 Concrete placements and records, 1 Viol.

subcontractor QA program, Inadequate storage and storage records of concrete repair /-

poor records reactor vessel and internals.

79-10 12/19/79 Inspection of onsite facilities None

.

for Resident Inspector's Office.

.

,

-

i.

'

=

.

Enclosure 4_

.

80-01 1/14-17/80 Concrete placements, hanger and 1 Viol.

small bore pipe fabrication shop,- Inadequate subcontractor QA program, documen-dewatering settlement studies, tation of condi-tions adverse to quality 80-02 2/4-29/80 Concrete related activities, 1 Viol.

I reactor pressure vessel cleaning Improper activities, sandblasting and storage-painting inside the drywell, of storage and maintenance, welding, materials rebar fabrication, pipe joint f.itup, hanger installations, storage of radioactive sources.

80-03 3/3-28/80 Weld rod control, equipment None

maintenance and construction, structural. steel welding and bolting, reactor vessel nozzle-modification, pipe welding,. status of electrical work.

80-04 3/31-4/30/80 Reactor vessel nozzle modifica-1 Viol.

I tion, pipe welding, equipment Failure supports, hanger and restrains, of QC bolting, torus vent line bellows program repairs, maintenance of installed execution equipment, concrete activities for

,

'

cadwelding, pipe specs, PQR's, preventing allegation investigation involving segregation painting.

of concrete 80-05 4/21-25/80 Reactor vessel nozzle safe end None I

replacement, safety related pipe

.

welding.

L'

80-06 4/23-25/80 Nonconformance control, trend None 4/29/80 analysis, and control of field i-I change requests.

i

!

,

t.

.

-Enclosure 4

80-07 5/5-30/80 RPV nozzle modifications, vent 3 Viol.

I line bellows repairs, equipment Welds made maintenance, structural steel without a welding, piping erection and procedure storage, backfill, cadwelds, bioshield welding, NDE records, Failure to containment penetrations, meet storage painting.

allegation.

requirements for RHR and core spray pumps Failure to identify

.

weld defects and missing records for bioshield 80-08 5/12-16'80 Weld material control, RPV safe None I

end welding, pipe welding.

80-09 6/2-27/80 RPV nozzle mods, vent line None

bellows repair, backfill and compaction, in place storage and maintenance, installation of torus

.

piping, structural steel installa-

'

tion, containment welding.

.

80-10 6/30-8/1/80 Backfill, pipe fitup, torus None

welding, NDE of bioshield,

'

storage of materials and equip-ment, vent line bellows repair,

drywell penetrations, structural

steel installation and welding,

!

core. boring, control rod drive housing restraint beam installa-i:

l tion, concrete repairs.

80-11 8/5/80 Information management meeting None

80-12 8/6-9/1/80 Backfill, storage, vent line None

repairs, concrete repairs, control rod drive housing support beam c

installation, containment spray header installation, pneumatic

'

testing of drywell penetrations, cadwelding, repair of defective

'

bioshield welds, concrete placement.

i L.

w,,

"

l o

Enclosure 4

.

80-13 8/26-29/80 Concrete placement for lower None 9/2,3,9/80 bioshield wall, heave / settlement

'

program, cadweld spliced rebar test program, and dewatering activities.

80-14 9/2-10/5/80 Vent line bellows repair, struc-3 Violations

tural steel installation, back-Failure to fill operations, pipe welding, establish equipment storage, drywell code basis penetration testing, drawing for installa-

.

drawing control, weld filler tion of CRDM material control, rebar housing sup-installation, and equipment port brackets lifting and handling.

Failure to establish controls over welding preheat Failure to follow bolt tensioning procedures 1 Deficiency Failure to follow procedures for issuing weld filler material 80-15 9/9/80 Cable tray installation and QA None 80-16 10/6-11/2/80 Vent line bellows repair, struc-3 Violations

tural steel installation, back-Failure to fill operations, pipe welding, correctly in-equipment storage, rebar stall SRV installation, biological shield piping installation, reactor vessel supports placement preparations, pipe support installation, NDE, and Failure to rebar splicing.

cap pipe spools Failure to identify and correct deficiencies

.

Enclosure 4

.

80-17 11/4-7/80 Structural steel erection and None

handling and installation of major components.

80-18 11/12-14/80 Receiving, storage, and mainten-None

ance of equipment, including associated QA records.

80-19 11/3-30/80 Valve internals inspection, 1 Violation structural steel welding inside Failure to containment, structural steel follow pro-erection, containment upper spray cedures when header pipe support welding, making bolted storage, of piping, hangers, and connections equipment; pipe installation including rigging and welding, rebar installation including mechanical splicing, concrete pre-placement, placement and curing; load testing of reactor pressure vessel (RPV) lifting rig, upper bioshield welding and painting, and concrete test lab activities.

80-20 12/2-5/80 Concrete construction and inspec-1 Violation

tor certification Improperly certified personnel 80-21 12/1/80 -

Bioshield rework, bioshield and 1 Violation 1/4/81 reactor vessel placement, vent Failure to

line bellows repair weld testing, maintain structural steel welding inside internal containment upper spray header piping pipe support welding, storage of cleanliness piping, hangers, and equipment; pipe installation, and concrete batch plant activities.

80-22 12/4,13,22 QA and procedures for transport-None

&31/80 ing, lifting and setting the

reactor vessel.

81-01 1/5-2/1/81 Vent line bellows repair testing, None

pipe handling, fitup and welding, concrete placement, weld preheat in cold weather, structural steel erection, and equipment storag..

Enclosure 4

,

81-02 2/2-3/1/81 Structural steel erection, pipe None

installation and repair, equip-ment storage, mechanical splicing of rebar, concrete placement, and upper bioshield installation.

81-03 2/5/81 Enforcement conference piping

subcontractor performance and responses to notices of violations.

81-04 3/2-4/5/81 Reactor vessel internals instal-2 Violations

lation, pipe hanger installation, Incorrect structural steel erection, pipe thickness installation and repair, equip-qualification ment storage and concrete placement.

Failure to radiograph in accordance with procedure 81-05 4/6-5/3/81 Reactor vessel internals instal-1 Violation

lation, pipe hanger installation, Defects in structural steel erection and ACME Embed welding, pipe installation, material storage, concrete place-ment, and electrical installations.

81-06 4/30/81 SALP NA

81-07 5/4-31/81 Supplier QA program, safety None

relief valve piping, upper bio-shield welding, pipe whip restraint installation, house-keeping, equipment maintenance, and pipe hanger installation.

81-08 5/26-29/81 Structural steel erection, None

installation and documentation.

81-09 6/1-7/5/81 Upper bioshield welding, struc-None

tural steel erection, concrete placement, Cadweld program, hanger installation, batch plant material storage, cable tray and conduit installation, and pipe installation.

l

.-.

-

- -

-

-

-

- - -

-

-

.,

Enclosure 4

.

81-10 6/18,19,22-Structural-steel installation, 1 Viol.

26/81

- component maintenance and Failure to

storage, and reactor vessel document installation, maintenance inspections 81-11 7/6-8/2/81 Hydrostatic testing, piping None

installation, rebar installation, backfill activities, hanger installation, concrete-placement, equipment storage, electrical installation, diesel generator design, and batch plant operations.

81-12 8/3-31/81 Concrete placement, reactor vessel 1 Viol.

I hold-down bolt tcrouing, and Failure to pipe and hanger installation, adequately-train pipefitters 81-13-8/14-21/81 Concrete' placement and QA.

None

81-14 9/1-10/4/81 Structural steel installation, 1 Viol.

pipe and hanger installation,-

Failure to material storage, reactor vessel add filler installation, HVAC duct installa-while welding tion, service water intake structure excavation, concrete placement.

81-15 10/5-11/1/81 Pipe and hanger installation, None

material storage, housekeeping, service water pipe backfill, reactor vessel internals installation, service water intake structure excavation, fluid head penetration installation, and contractor QA.

81-16 11/2-30/81 Intake structure installation, None

rebar installation, equipment storage, housekeeping, testing of embedded piping, fire protec-tion, and radiograph ^

,

-..

' Enclosure 4

.

81-17 11/12/81 SALP NA 81-18 12/1/81-Rebar splicing, structural steel 2 Viol.

1/3/82 installation, pipe and hanger Failure to

installation, welder qualifica-implement tions, cable tray installation, corrective concrete placement, reactor action internals installation, material storage, fire protection, house-Failure to keeping, and wall pour operations, translate design basis into drawings /spe.

cifications 82-01 1/4-31/82 Intake structure foundation con-1 Violation

struction and design, PSAR Failure to commitment implementation, pipe implement and hanger installation, reactor procedures vessel internals installation, for M&TE control rod drive pipe installation, control concrete placement, and response to NRC Bulletins.

82-02 1/18-22/82 QA performance for ongoing work None

in the following areas: reactor internals, reactor controls supports, HVAC, and concrete placement; QA audits and surveillance.

82-03 2/1-28/82 Intake structure foundation None

cleanup, equipment storage and maintenance, structural steel installation, rebar installation, and valve installation, 82-04 3/1-4/4/82 Intake structure underwater con-1 Violation-

-2 crete placement, structural Failure to steel welding, reactor internal implement installation, electrical penetra-weld filler tion installation, pipe and hanger material con-installation, ductwork installa-trol proce-tion.

dure L

...

,

Enclosure 4

c

.

82-05 4/5-5/2/82 Upper bioshield placement pre-2 Violations

parations, intake structure Failure to dewatering and concrete place-

' indicate in-ment, structural steel welding, spection HVAC duct installation, anchor status of ex-bolt installation, and electrical pansion penetration installation.

anchor bolts Failure to initiate a design change

prior to modification 82-06 5/3-31/82 Cable tray supports, diesel None

generator installation, electrical penetrations, weld qualifications, and QC inspector qualifications.

82-07 6/1-7/3/82 Installation of reactor internals, 3 Violations

pipe and hangers, electrical Failure to

'

penetration, and HVAC ductwork, bend test anchor bolting,.NDE, housekeeping, Nelson studs-and QC inspector qualifications.

Failure to obtain excavation permit.

~82-08 7/6-8/1/82 Structural steel erection, con-None

crete placement, service water

-

pipe trench excavation, cable

,

tray and support installation, pipe whip restraints, and welding.

_82-09 8/2-9/6/82 Bicshield installation, concrete None

placement, filler metal control, hanger and pipe installation, housekeeping, polar crane assembly, diesel generator installation and structural steel erection.

-82-10 8/30-9/2/82 Electrical installation, instru-None

mentation, and field design control.

82-11 9/8-10/82 Welding on vessel internals and 1 Violation

reactor vessel cleanliness Failure to control.

follow clean-liness controls

-

'

,

-., ~

.

Enclosure 4

.

82-12 9/9-10/3/82 Polar crane rail installation, 2 Violations

conciete placement, pipe and Failure to QC support installation, HVAC duct to inspect installation, rebar installation, MCC's backfill and compaction Failure activities, welding and NDE.

to control weld activities 82-13 10/4-31/82 Cable tray installation, HVAC None

ductwork installation, pipe fit-up and welding, pipe support and pipe whip restraint welding, concrete curing, and structural steel welding.

82-14 10/25-12/1/82 Mobile Van (NDE) inspection None

involving independent measure-ments to verify adequacy of welding QC and NDE program.

82-15 11/1-12/5/82 Piping and support installation, 1 Violation

concrete curing, polar crane and Failure of QC reactor building dome installation, to identify housekeeping, HVAC ductwork pipe support installation, and QA audits.

deficiencies 82-16 12/6/82-Reactor internals installation, None 1/2/83 cold weather concreting, hydro-

static testing, measuring and test equipment, and expansion anchor bolt testing.

83-01 1/3-31/83 Cable tray installation, HVAC None

duct and support installation, materials storage, housekeeping, concrete activities, welding, and structural steel installation.

83-02 2/1-28/83 Reactor internals installation, 1 Violation

concrete curing, equipment Failure to storage, pipe and hanger follow proce-installation, and housekeeping.

dures for concrete curing 83-03 2/14-18/83 Design, procurement, receipt and None

installation of electrical component.

Enclosure 4

.

83-04 2/28-3/4/83 Soil compaction testing, equip-None

ment storage, and construction deficiency correction.

83-05 3/1-4/17/83 Electrical cable storage and 1 Violation

installation, water-tight door Failure of QC installation, structural steel to identify weld inspection, HVAC ductwork HVAC ductwork installation, and housekeeping, deficiencies 83-06 3/14-18/83 Electrical component procurement, None

receipt inspection, qualification and installation.

83-07 4/18-22/83 Installation of electrical race-None I

ways, cables, instruments, and valves.

83-08 4/18-6/5/83 Structural steel bolting and 1 Violation

welding, cable tray and conduit Failure of QC installation, reactor vessel to identify cleanliness, materials trace-weld and in-ability, and pipe supports.

stallation discrepancies 83-09 5/31-6/3/83 Electrical component and system None

installation and QA 83-10 6/6-7/4/83 Backfill activities, structural None

steel bolting and welding, housekeeping and concrete place-ment.

83-11 7/11-15,21/83 Pipe, pipe supports, and anchor None

bolts, QA/QC, and documentation of construction deficiencies.

83-12 7/5-31/83 Pipe and hanger installation, None I

housekeeping, response to NRC Bulletins and Circulars, and training.

83-13 8/18-10/16/83 Battery charging, backfill None

activities, pipe and hanger installation, materials storage, and housekeepin.

Enclosure 4

.

83-14 9/19-30/83 Regional Construction Team 1 Violation

Inspection of construction Failure of QC management, QA, design control, to identify electrical construction, welding raceway non-and piping, mechanical equipment, conformances procurement, and training.

83-15 9/19-23/83 Preservice inspection (PSI)

None

activities.

83-16 10/17-12/4/83 Torus modifications, installa-None I

tion of instrument tubing, electrical cable trays and conduits, piping, pipe supports, HVAC ductwork, housekeeping, and Construction Deficiency Reporting.

83-17 12/20-23/83 Welding and QA/QC for primary None

containment modifications.

83-18 12/4/83-HVAC ductwork and support 1 Violation 1/5/84 installation, rebar drawings, Failure of QC pipe and support installation, to identify torus modifications, and inadequate housekeeping.

weld prep 84-01 1/10-13/84 Procurement, installation, 1 Violation

inspection, and maintenance of Failure to electrical components and energize systems.

diesel alternator heaters 84-02 1/9-2/20/84 Pipe and support installation, None

NRC trending, torus mods, house-keeping, documentation reviews, CDR's, potentially generic issues.

84-03 1/20/84 Corrective action on discrepan-None

>

I cies identified in the original seismic analysis of the auxiliary building.

84-04 2/21-4/1/84 Torus mods, pipe and hanger None

installation, implementation of snubber protection program, cable pulling, housekeeping, potentially generic issues, Bulletin and Circular review.

_.

- _ _

_

_ _ _.

.

,

-o.-

/

Enclosure 4

.

84-05 5/14-6/24/84 Torus mods, raceway and cable 1 Violation

installation, seismic II/I 4 Examples program, HVAC ductwork supports, Failure to instrumentation, housekeeping, maintain ty-NCR and SDR trending, hydrostatic wrap spacing testing, electrical terminations, pipe and hanger installation, Failure to Startup and Test program manual, ty-wrap COR's.

cables to

'

tray Failure of QC

~

to identify shim installation deficiencies Failure to follow rework control procedures 84-06 4/30-5/4/84 Pipe and support installation and 2 Violations

related QA/QC activities.

QC acceptance of nonconforming -

snubber installation Failure to notify.QC of snubber removal 84-07 CANCELLED i

!

84-08 6/5-8/84 Heave / settlement measurement pro-None

gram records and actions taken

!

and records generated relating to the CDR of grout intrusion into

-

the drywell air gap.

84-09 6/11-15/84 Work observation and records None

associated with electrical cables

-

and terminations and HVAC.

84-10 6/25-8/5/84-Equipment maintenance, turnover None I

packages, seismic II/I program,

,

l instrumentation, proposed drywell l-mod to accommodate reactor water level sensing lines, housekeeping, CDR's, allegation investigation, t

-

.

...

~

Enclosure 4

.

.

84-11 CANCELLED

,

^

'84-12 8/6-9/16/84 Hydrostatic testing, pipe hanger i Violation,-

installation,' torus sand blasting, 3_ Examples core boring, startup group per-Failure of

,

sonnel qualifications, turnover startup pro-

,

1'.

packages, Bulletin and Circular gram to con-

'

'

review, trol action items

'

Failure to assure test author.

attendance at PORC Failure to

..

implement

'

adequate.PORC review 84-13 8/20-24/84 Safety-related equipment, vendor None l'

documentation and QC records of-piping and equipment, QA audit records.

-

84-14 CANCELLED'

84-15 9/19-21/84 Piping. system as-built turnover None 9/26-28/84 inspection, welding, PSI /ISI

program.

84-16~

9/24-28/84 QA program for turnover including None

,

'

QA/QC overview and interfacing

activities.

84-17 10/1-4/84-Preoperational environmental None

surveillance program, radio-logical environmental monitoring

,

program, meteorological program, facilities and equipment, documentation, quality assurance, and contractor programs.

84-18 9/17-11/4/84 Mechanical and piping system None

walkdowns, instrumentation, potentially generic issues,

,~,

falsification of records of soils test lab, QA audits of turnover packages, CDR's, SAFETEAM, piping system walkdowns.

.

.

-

-

- -

-

.

-

-

.

.

-

,

w

'-

,-

,

Enclosure 4-

[y

-

,

,

,

,w

-

-

~

,

84-19

'10/29-11/2/84 Preoperational OA including None

"

'2 surveillances and audits.

84-20

,10/30-11/1/84-This inspection opened the None '

,

preop tdst program.

84-21 11/5-9/84 Norkfobservation and quality

- 1 Violation,

recor_d review of the installa-2 Examples tidd'of cabling and instrumen-Unsupported tation' systems and components cable

'

in the areas of receipt inspec-tion,r6uti,qg, storage, termina-

' Bend, radius c

'

.ttons, and maintenance.

violation 84-22 L10/22/84 This'was a'second corpnrate NA management meeting to discuss

'

construction status and Region I

~

-

.

activities during the preop-and

-

start lap phases.

84-23.

'

10/23-10/26/-

Preo'p fostrumentation, manage-N_one

ment action to address;previously

-

identified problems in the

,

[

instrumentation area, CDR's.

84-24

-

11/5/84-12/ i Routine resident inspection of None-16/84L construction work in progress,

~

preoperational testing and

C

.freventative maintenance

,

84-25 11/14/84-,

Preservice Inspection Program None-11/29/84 activities, personnel qualifica-

'

V tion records and'QA_ surveillance i

reports

.

-

'

'84-26

_L SALP~

.

84-27 12/10/84-System turnover process and None 12/14/84 procedures s

2.

'

a

,

-84-28 12/17/84-Preoneration test prograte and None

'

12/20/84 procedures

.

3-84-29 12/17/84-Routine resident inspection of-1 Violation

'

- 1/27/85 preoperational test programs Faf,1ure to

'

'

and. ongoing construction

.

follow test

activit.ies equipment

,

control procedures

_~ - -

,'

s

., -

,

.

,,,,, -. -

,

,

Enclosure 4

.

85-01 1/1/85-Preventive maintenance and 1 Violation 1/10/85 preparations for reactor vessel Failure to

hydrostatic test.

maintain storage conditions for a heat exchanger.

85-02 1/8/85-Preoperational radiation protec-None 1/10/85 tion, chemistry, and radioactive waste programs.

85-03 1/14/85-Installation of safety-related 1 Violation 1/18/85 instrument components and 2 Examples of I

systems, failure to follow procedures.

85-04 Cancelled 85-05 1/28/85-Routine resident inspection 1 Violation 3/3/85 of preoperational test program Control of

and ongoing construction fluid and activities.

pipe temperatures during piping system flushes.

85-06 2/12/85-Preoperational tests and con-None 2/15/85 struction work in progress.

85-07 2/11/85 &

Management Meeting on system None 2/15/85 turnover and control room N/A design.

85-08 4/8/85-Independent measurements of None 5/3/85 safety-related piping.

85-09 Cancelled

'

..

.. -..-- -.-.,.

.. -. -. ~

. - - --

,

.

.-

-,

.,.

W o

,

- Enclosure 4

.

'

4'

85-10 3/4/85-Safety re:ated electrical 1 Violation

'

3/8/85 equipment Failure to

-

maintain safety.

related

- cables and

,

trays in a

.;

safe and

'

clean-condition.

85-11 4/8/85-Quality Assurance Program for None 4/12/85 Preoperational and Startup

'

Testing.

,

.

85-12 3/1/85-Reactor Vessel and Related None

!

- 3/5/85 Piping Hydrostatic Test.

j.

85-13 3/12/85-Preoperational test review and None

!

3/15/85 verification.

.

85-14 3/14/85-Routine resident inspection of None 4/14/85 work in progress and pre-

operational testing.

,

85-15.

3/18/85-Piping systems and supports, PSI

- None

,

-

3/22/85 I

f 85-16 3/19/85-Preoperational radiation pro-None

'

3/25/85 tection-program.

1-

85-17 4/15/85-Safety related electrical 1 Violation 4/18/85-systems.

Failure to

perform i

maintenanc e

in a L

timely

' '

manner.

85-18 4/16/85-Preoperational test procedure None 4/19/85 review and verification.

1.

-

!

O

,

,+<,n--

-r-

-,-,-.-...,-.wn.,

r-c.,

--

-

....v.,.

_--,, -,,--,-.-, -,~,.n,--,

-

,,-r-me

-

, -,, - -

---

--

-o Enclosure 4

.

85-19 4/15/85-Routine resident inspection of None 5/27/85 Preoperational testing, ongoing

construction work, and Emergency Planning program development.

85-20 4/22/85-Class 1 small pipe and pipe None 4/26/85 supports.

85-21 4/29/85-Maintenance, Surveillance, None 5/3/85 Document Control.

85-22 4/29/85-Reactor Pressure Vessel None 5/3/85 Internals Installation.

85-23 5/13/85-Preventive Maintenance Program None 5/17/85 and installation of safety-

related electrical equipment 85-24 5/20/85-Emergency Lighting and safe None 5/24/85 shutdown capability in the event

of a fire 85-25 5/14/85-Preoperational Security Program None 5/17/85 Review

85-26 6/10/85-Preoperational Testing None 6/14/85

85-27 5/28/85-Routine resident inspection of 1 Violation 7/7/85 preoperational testing and work Failure to

in progress follow procedures for implementing preoperation-al tests.

85-28 6/10/85-Pre-Service Inspection Program None 6/14/85

!

t.

,

- - -

_.

Enclosure 4

. 23 '

..

85-29 7/8/85-RO & SR0 Initial Cold License None 7/17/85 Examinations

85-30 6/24/85-Preoperational' Test Program None 6/28/85 Implementation

85-31 6/24/85-Soils and Foundations None 6/28/85

'85-32 5/8/85-Review of Independent Design 5/10/85 &

Verification Program 6/4/85-6/6/85

85-33 7/8/85-7/12/

Quality Assurance Program for None 85 & 7/15/85-Operations 7/18/85

85-34 7/8/85-Safety related electrical

.None 7/11/85 systems and equipment

85-35

.7/18/85-Routine resident inspection 1-Violation 8/11/85 of Preoperational testing and

ongoing construction work 85-36 7/22/85-Preoperational Testing Program'

None 7/26/85

85-37 7/30/85-Preservice Inspection Program None 7/26/85 3-85-38 7/30/85-Operations Quality Assurance None 8/2/85 Program

85-39-8/5/85-Instrumentation and controls None 8/9/85 support systems

85-40 8/12/85-Emergency Preparedness Program None 8/16/85 Appraisal

o Enclosure 4

.

85-41 8/19/85-Readiness inspection for new 8/30/85 fuel receipt

85-42 8/12/85-Routine resident inspection of 1 Violation 9/23/85 New Fuel Receipt Preoperational Inadequate

Testing, and ongoing construction design work control 85-43 8/1/85 Management Meeting on operator None N/A licensing examination results

<

85-44 9/10/85-Preoperational Radiation Pro-None 9/13/85 tection, Chemistry, and

Radioactive Waste Program 85-45 9/24/85-Routine resident inspection of 1 Violation 10/27/85 new fuel receipt, preoperational Excessive

testing, and ongoing construc-cable tion work restraint spacing 85-46 9/23/85-Preservice Inspection Program None 9/30/85

85-47 9/25/85 and Preoperational Test Program None 10/1/85-10/11/85

4 85-48 10/14/85-Operator Licensing Examinations None 10/23/85

85-49 Cancelled 85-50 Cancelled 85-51 10/21/85-Instrumentation systems, com-2 Violations 10/25/85 ponents, and control circuits Failure to

follow instructions, procedures, drawings; Inadequate design control 85-52 10/28/85-Preoperational Radiation Pro-None 11/15/85 tection and Radioactive Waste

programs

.- _ _ - _ _ __ - ___

_ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

o Enclosure 4

,

85-53 10/28/85-Observation of annual emergency None 10/30/85 exercise

85-54 9/30/85-Independent Design Verification None 10/3/85 Program Final Report

85-55 11/4/85-Preoperational Test Program and None 11/15/85 Startup Test Program

85-56 10/28/85-Routine Resident Inspection of None

12/1/85 Preoperational testing and

ongoing construction work 85-57 11/12/85-Preoperational Security Program None 11/15/85 Review l

I 85-58 12/2/85-As-Built Team Inspection None t

12/13/85

'

85-59 11/18/85-Chemical and Radiochemical None 11/22/85 Measurements Programs

85-60 11/18/85-Preservice Inspection Program None 11/22/85

..

_ _ -

Enclosure 4

_o.

85-61 12/1/85-Routine Resident Inspection of 2 Violations 1/12/86 Preoperational Test Program and Quality

ongoing construction activities Control witness points bypassed and procedure changed without proper controls; final QC inspection failed to identi fy substandard bolt installed in flange in safety-relat-ed system 85-62 9/9/85-Preoperational Testing and Local None 9/18/85 Leak-Rate Testing

85-63 12/16/85-Heave / Settlement Measurement None 12/19/85 and Program, HVAC Ductwork & Supports, 12/23/85 Pipe Support Designs

85-64 12/2/85-Technical Specification Review None 12/13/85 and As-built comparison

85-65 12/23/85-Integrated Leak-Rate Test 1 Violation 1/3/86 Review / witnessing Closure of

containment isolation valve by other than normal mode of motor operation i

i

( -

.

,

,

no-o-

Enclosure 4'

85-66 12/30/85-ATWS Event Followup Items, QA None 1/3/86 Records and Measuring and Test

Equipment 86-01.

1/7/86-Fire Detection and Prevention None

.1/24/86 Program

-86-02 1/27/86-Administrative, Operations, and None 1/31/86 and Maintenance Procedures Review 2/3/86-2/7/

86 & 2/14/86

86-03 1/7/86-Preoperational Test Program None 1/17/86 Review

86-04-1/7/86-Operations QA Program None 1/10/86 and 1/13/86-1/15/86

86-05 1/13/86-Water Chemistry Control Program None.

1/24/86 Review

86-06 1/13/86-Routine Resident Inspection of 1 Violation 2/9/86 Preoperational Testing Activities Failure to

fully demonstrate system functionality

!.

86-07 1/21/86-Health Physics

!.'

2/14/86 L

86-08-1/27/86-

.Preoperational Security Program None i

1/30/86 Review i-

l 86-09 2/3/86-Emergency Planning

2/7/86

<-

.

86-10 1/27/86-Pre-operational Testing

2/7/86 a

86-11 1/27/86-Preservice Inspection Program None 1/31/86 Review

'

i'

,

t.~

e a

Enclosure 4

.o 86-12 2/10/86-Start-up Program 2/21/86 86-13 2/10/86-Open Item Closecut and Snubber None 2/14/86 Activity Review

86-14 2/3/86-Safeteam

2/7/86 86-15 2/10/86-Routine Resident

3/16/86 86-16 2/24/86-Operator Licensing

4/24/86 86-17 2/24/86-Start-up Program

2/28/86 86-18 3/3/86-Start-up Program

3/14/86 86-19 3/3/86-Bulletin /Open Items Closecut

3/6/86 86-20 3/17/86-Routine Resident

4/30/86 86-21 3/12/86-Surveillance Testing /

3/21/86 Start-up Program

  • Report Not Issued