ust 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR DIABLO CANYON POWER PLANT, UNITS 1 AND 2 (REPORT 05000275/2017005 AND 05000323/2017005)

Dear Mr. Halpin:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019 for Diablo Canyon Power Plant, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/

Staffing/Multi-Unit Dose Assessment Plans. This inspection will be conducted at Diablo Canyon Power Plant, Units 1 and 2, to confirm the stations full implementation of Commission Orders EA-12-049 and EA-12-051.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (817) 200-1148 with any questions you have regarding this letter.

Sincerely,

/RA/

Mark S. Haire, Chief Division of Reactor Projects Docket Nos. 50-275; 50-323 License Nos. DPR-80, DPR-82 Enclosure: Diablo Canyon Power Plant Inspection Plan

ML17242A165 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002 By: MSH/dll Yes No Publicly Available Sensitive OFFICE SPE:DRP/A BC:DRP/A NAME RAlexander MHaire SIGNATURE /RA/ /RA/

DATE 8/28/17 8/28/17

Page 1 of 2 Diablo Canyon 08/25/2017 08:21:16 Inspection / Activity Plan Report 22 07/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RS 24 - RADIATION SAFETY 2 1, 2 07/31/2017 08/04/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 07/31/2017 08/04/2017 IP 71124.04 Occupational Dose Assessment EXAM - INITIAL EXAM 6 1 12/11/2017 12/15/2017 X02595 INITIAL EXAM DC U1 (10/2017)

2 12/11/2017 12/15/2017 X02596 INITIAL EXAM DC U2 (10/2017)

1 01/22/2018 02/05/2018 X02595 INITIAL EXAM DC U1 (10/2017)

2 01/22/2018 02/05/2018 X02596 INITIAL EXAM DC U2 (10/2017)

TI-191 - MITIGATING STRATEGIES/SFP INST FOR BDBEE 4 1, 2 11/13/2017 11/17/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 EP-1 - BIENNIAL EP PROGRAM INSPECTION 1 1, 2 10/30/2017 11/03/2017 IP 7111402 Alert and Notification System Testing 1, 2 10/30/2017 11/03/2017 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 10/30/2017 11/03/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 10/30/2017 11/03/2017 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies EP-2 - EP PERFORMANCE INDICATOR VERIFICATION 1 1, 2 10/30/2017 11/03/2017 IP 71151-EP01 Drill/Exercise Performance 1, 2 10/30/2017 11/03/2017 IP 71151-EP02 ERO Readiness 1, 2 10/30/2017 11/03/2017 IP 71151-EP03 Alert & Notification System Reliability 7111108 - INSERVICE INSPECTION 2R20 1 2 02/19/2018 03/02/2018 IP 7111108P Inservice Inspection Activities - PWR RS 12PI - RAD SAFETY 2 1, 2 02/26/2018 03/02/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 02/26/2018 03/02/2018 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 02/26/2018 03/02/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 02/26/2018 03/02/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences PI&R - BIENNIAL PI&R INSPECTION 4 1, 2 04/16/2018 04/20/2018 IP 71152B Problem Identification and Resolution 1, 2 04/30/2018 05/04/2018 IP 71152B Problem Identification and Resolution EB1-21N - DC DESIGN BASES INSPECTION PROGRAMS 3 1, 2 06/11/2018 06/29/2018 IP 7111121N Design Bases Assurance Inspection (Programs)

RS 5678 - RAD SAFETY 4 1, 2 07/09/2018 07/13/2018 IP 71124.05 Radiation Monitoring Instrumentation This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 Diablo Canyon 08/25/2017 08:21:16 Inspection / Activity Plan Report 22 07/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RS 5678 - RAD SAFETY 4 1, 2 07/09/2018 07/13/2018 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/09/2018 07/13/2018 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 07/09/2018 07/13/2018 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EB2-05XT - TRIENNIAL FIRE PROTECTION INSPECTION 4 1, 2 10/15/2018 10/19/2018 IP 7111105X Fire Protection - NFPA 805 (Triennial)

1, 2 10/29/2018 11/02/2018 IP 7111105X Fire Protection - NFPA 805 (Triennial)

EP-1 - EP EXERCISE INSPECTION 4 1, 2 10/22/2018 10/26/2018 IP 7111401 Exercise Evaluation 1, 2 10/22/2018 10/26/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 10/22/2018 10/26/2018 IP 71151-EP01 Drill/Exercise Performance 1, 2 10/22/2018 10/26/2018 IP 71151-EP02 ERO Readiness 1, 2 10/22/2018 10/26/2018 IP 71151-EP03 Alert & Notification System Reliability RS 13 PI - RP INSPECTION 2 1, 2 02/11/2019 02/15/2019 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 02/11/2019 02/15/2019 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 02/11/2019 02/15/2019 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 02/11/2019 02/15/2019 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 7111108 - INSERVICE INSPECTION 1 2 02/11/2019 02/22/2019 IP 7111108P Inservice Inspection Activities - PWR BRQ - BRQ INSPECTION 2 1, 2 04/08/2019 04/12/2019 IP 7111111B Licensed Operator Requalification Program EB1-07T - DIABLO CANYON HEAT SINK INSPECTION 2 1, 2 04/22/2019 04/26/2019 IP 7111107A Heat Sink Performance EB1-21M - DIABLO CANYON DBA TEAM INSPECTION 6 1, 2 06/10/2019 06/28/2019 IP 7111121M Design Bases Assurance Inspection (Teams)

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.