Letter Sequence Draft Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
Results
Other: DCL-26-006, License Renewal Application, Amendment 8 Regarding the Coastal Zone Management Act Consistency Certification, ML24003A890, ML24109A029, ML24117A013, ML24187A135, ML24240A022, ML24240A023, ML25148A196, ML26054A069
|
MONTHYEARML24003A8892024-01-19019 January 2024 FRN - Diablo Canyon, Units 1 and 2, Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement Project stage: Request ML24003A8882024-01-19019 January 2024, 24 January 2024 Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement Project stage: Request PMNS20240065, Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application2024-01-22022 January 2024 Environmental Scoping Public Meeting for the Diablo Canyon License Renewal Application Project stage: Meeting ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement Project stage: Other ML24030A0372024-01-26026 January 2024 Comment (1) of Richard Spotts on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Request ML24030A4672024-01-30030 January 2024 Environmental Scoping Meeting for the Diablo Canyon License Renewal Application - February 1 Meeting Slides Project stage: Meeting PMNS20240064, Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application2024-01-30030 January 2024 Environmental Scoping Virtual Public Meeting for the Diablo Canyon License Renewal Application Project stage: Meeting ML24108A1462024-02-0101 February 2024 Environmental Scoping Meeting - February 1 Transcript Project stage: Request ML24036A3382024-02-0505 February 2024 Environmental Scoping Meeting for the Diablo Canyon License Renewal Application - February 8 Meeting Slides Project stage: Meeting ML24108A1452024-02-0808 February 2024 Environmental Scoping - February 8 Meeting Transcript Project stage: Request ML24046A0792024-02-14014 February 2024 Comment (2) of Anonymous on Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Request ML24053A1432024-02-21021 February 2024 Comment (3) of Mila Vujovich-LaBarre on Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Request ML24109A0292024-02-22022 February 2024 Scoping Comments of the Yak Tityu Tityu Yak Ti?Hini Northern Chumash Tribe Diablo Canyon License Renewal Project stage: Other ML24058A0062024-02-23023 February 2024 Comment (6) of Nelson Chloe on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Request ML24058A0072024-02-23023 February 2024 Comment (7) of Kermit Kubitz on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 and 2 Project stage: Request ML24058A0052024-02-23023 February 2024 Comment (5) of Tony Brown on Behalf of Nuclear Energy Institute (NEI) on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Pacific Gas and Electric Company; Diablo Canyon Nuclear Power Plant, Units 1 an Project stage: Request DCL-2024-507, 2023 Annual Report on Discharge Self-Monitoring2024-02-27027 February 2024 2023 Annual Report on Discharge Self-Monitoring Project stage: Request ML24056A0022024-02-27027 February 2024 – License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application Project stage: Approval ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application Project stage: Approval ML24108A1472024-05-0707 May 2024 February 2024 Diablo Canyon Public Scoping Meetings - Summary Project stage: Request ML24108A1482024-05-0707 May 2024 February 2024 Environmental Scoping Meetings Related to the Diablo Canyon LRA - Memo Project stage: Meeting ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application Project stage: Other ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review Project stage: Other ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 Project stage: Other ML24240A0232024-09-20020 September 2024 Environmental Scoping Summary Report for Diablo Canyon License Renewal Project stage: Other ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants Project stage: Draft Other ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants Project stage: Draft Other ML25148A1962025-06-25025 June 2025 Ltr to P Gerfen - Diablo Canyon Nuclear Power Plants, Units 1 and 2 - Notice of Availability of Final Supplement 62 to the GEIS for License Renewal of Nuclear Plants Project stage: Other DCL-26-006, License Renewal Application, Amendment 8 Regarding the Coastal Zone Management Act Consistency Certification2026-02-11011 February 2026 License Renewal Application, Amendment 8 Regarding the Coastal Zone Management Act Consistency Certification Project stage: Other ML26054A0692026-02-26026 February 2026 Letter to P. Gerfen, Acknowledgement of Receipt of Supplement 5 to the Diablo Canyon License Renewal Application Regarding CZMA Consistency Certification Project stage: Other 2024-02-23
[Table View] |
Text
.
Po-Chieh Ting U.S. Environmental Protection Agency Region IX 75 Hawthorne St.
San Francisco, CA 94105
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 - NOTICE OF AVAILABILITY OF DRAFT SUPPLEMENT 62 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS (EPID NUMBER: L-2023-LNE-0004) (DOCKET NUMBERS:
50-275, 50-323)
Dear Po-Chieh Ting:
The U.S. Nuclear Regulatory Commission (NRC) staff has prepared an environmental impact statement (EIS), Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 62, Regarding License Renewal of Diablo Canyon Nuclear Power Plant, Units 1 and 2, Draft Report for Comment (NUREG-1437) (DSEIS). The period to provide comments on this document will end 45 days after the Federal Register Notice of Availability is published, which is expected to be November 1, 2024.
Based on its evaluation in the DSEIS, the NRC staffs preliminary recommendation is that the adverse environmental impacts of license renewal for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon) are not so great that preserving the option of license renewal for energy-planning decisionmakers would be unreasonable. This preliminary recommendation is based on: (1) the analysis and findings in NUREG-1437; (2) Pacific Gas and Electric Companys environmental report; (3) the NRC staffs consultation with Federal, State, Tribal, and local governmental agencies; (4) the NRC staffs independent environmental review; and (5) the NRC staffs consideration of public comments received during the scoping process.
The DSEIS was submitted to the U.S. Environmental Protection Agency via e-NEPA and copies are also being distributed to interested Federal, State, Tribal, and local agencies, industry organizations, interest groups, and members of the public. The DSEIS will also be available for public review near Diablo Canyon at the San Luis Obispo Library, 995 Palm St, San Luis Obispo, CA 93403, and in the NRCs Agencywide Documents Access and Management System (ADAMS) at https://www.nrc.gov/reading-rm/adams.html. The ADAMS Accession No. for the DSEIS is ML24299A167.
October 28, 2024
P. Ting 2
If further information is required, please contact NRC Senior Environmental Project Manager Kim Conway via email at Kimberly.Conway@nrc.gov.
Sincerely, Stephen S. Koenick, Chief Environmental Project Management Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. 50-275, 50-323 cc: Listserv Signed by Koenick, Stephen on 10/28/24
P. Ting 3
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 - NOTICE OF AVAILABILITY OF DRAFT SUPPLEMENT 62 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS (EPID NUMBER: L-2023-LNE-0004) (DOCKET NUMBERS: 50-275, 50-323)
DATED:
DISTRIBUTION:
PUBLIC RidsNrrDnrl Resource RidsNrrPMDiabloCanyonResource BHarris, NRR/DNRL LGibson, NRR/DNRL SKoenick, NMSS/REFS MSampson, NRR/DNRL SLee, NRR/DNRL SLee NRR/DORL DRoth, OGC SBurnell, HQ/OPA AMoreno, OCA DMcIntyre, HQ/OPA VDricks, RIV/OPA RAlexander, RIV/SLO MHayes, RIV, SRI PVossmar, RIV/DRP TDR5@pge.com ADAMS Package Accession No.: ML24284A300; Letter: ML24284A812 OFFICE NMSS/REFS NMSS/REFS:LA OGC NMSS/REFS:BC NAME KConway AWalker-Smith JWachutka SKoenick DATE 10/11/2024 10/11/2024 10/22/2024 10/28/2024 OFFICIAL RECORD COPY October 28, 2024