05000254/LER-1998-024, Forwards LER 98-024-00 Per 10CFR50.73(a)(2)(i)(B).List of Commitments Made by Util,Provided

From kanterella
(Redirected from 05000254/LER-1998-024)
Jump to navigation Jump to search
Forwards LER 98-024-00 Per 10CFR50.73(a)(2)(i)(B).List of Commitments Made by Util,Provided
ML20196C311
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 11/20/1998
From: Dimmette J
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20196C315 List:
References
SVP-98-349, NUDOCS 9812020029
Download: ML20196C311 (2)


LER-2098-024, Forwards LER 98-024-00 Per 10CFR50.73(a)(2)(i)(B).List of Commitments Made by Util,Provided
Event date:
Report date:
2542098024R00 - NRC Website

text

. - .

g- .

Commonu calth I.dNin ( hmpJn)

, Quad ( itich 6cncrJling 5tation 22710 20Mb Avenue North Orrdova. II. 6121247 40 Tel 3(DM F22ii SVP-98-349 November 20,1998 United States Nuclear Regulatory Commission ATTN: Document Control Desk Washington,DC 20555 Quad Cities Nuclear Power Station, Unit One Facility Operating License No. DPR 29 NRC Docket No. 50-254 Enclosed is Licensee Event Report (LER) 254/98-024, Revision 00, for Quad Citics Nuclear Power Station.

This report is submitted in accordance with the requirements of the Code of Federal  ;

Regulations, Title 10, Part 50.73(a)(2)(i)(B). The licensee shall report any operation or condition prohibited by the Plant's Technical Specifications. j We are committing to the following actions:

1. QCAP 2200-03, Attachment A." Daily Work Addition / Work Carryover  ;

Sheet," will be revised by January 8,1999, to facilitate the Senior Reactor Operator (SRO) review of work additions. This will ensure /  :

appropriate limiting condition for operation (LCO) entries are identified /

and will require the Work Week Manager to review the work additions with the work package in hand.

l 2. A process will be proceduralized by January 29,1999, w ensure the

./ b 1 impact of the work on the plant will be adequately addressed in all work packages.

i l 3. Training will be completed by March 1,1999, for licensed operators on p4

-% the lessons learned fmm this event, including the need to validate verbal information.

Any other actions described in the submittal represent intended or planned actions by Commonwealth Edison (Comed) Company. They are described for the NRC's information and are not regulatory commitments.

9812020029 981120 PDR ADOCK 05000254-

S , , . , ,

,,,, , ,,, ,,,, P DR c

5- ,

4 November 20,1998 U. S. Nuclear Regulatory Commission

. . Page 2 Should you have any questions concerning this letter, please contact Mr. C. Peterson, Regulatory Assurance Manager, at 309-654-2241, ext. 3609.  ;

i Resp etfully,  ;

A i sk JZMF_ '

Joel P. Dimmette, Jr. I Site Vice President I Quad Cities Nuclear Power Station JPD/CP/ea Enclosure cc: Regional Administrator-NRC Region 111 R.. Pulsifer, Project Manager, NRR C. Miller, Senior Resident Inspector, Quad Cities W. Leech, MidAmerican Energy Company D. Tubbs, MidAmerican Energy Company B. Ganser, IDNS, Quad Cities i S. Focht, American Nuclear Insurers  !

! INPO Records Center i Office of Nuclear Facility Safety, IDNS I