05000254/LER-1998-005, Forwards LER 98-005-00 Re Event Which Occurred at Quad Cities Nuclear Power Station.Commitments Made within Ltr, Listed

From kanterella
Jump to navigation Jump to search
Forwards LER 98-005-00 Re Event Which Occurred at Quad Cities Nuclear Power Station.Commitments Made within Ltr, Listed
ML20216C329
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 03/06/1998
From: Kraft E
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20216C336 List:
References
SVP-98-084, SVP-98-84, NUDOCS 9803130371
Download: ML20216C329 (2)


LER-2098-005, Forwards LER 98-005-00 Re Event Which Occurred at Quad Cities Nuclear Power Station.Commitments Made within Ltr, Listed
Event date:
Report date:
2542098005R00 - NRC Website

text

,e Camimonw cahh I Ahwn Lomp.m)

Quad Citics (.cncrating %tation 22*l0 2f Kith Anenue North g

Cordina. II.612 ain 40 ten 9w s 22 n s SVP-98-084 March 6,1998 United States Nuclear Regulatory Commission Washington, DC 20555 Attention: Document Control Desk

Reference:

Quad Cities Nuclear Power Station Docket Number SC-254, DPR-29, Unit One Enclosed is Licensee Event Report (LER)98-005, Revision 00, for Quad Cities Nuclear Power Station.

This report is submitted in accordance with the requirements of the Code of Federal Regulations, Title 10, Part 50.73(a)(1)(i)(B). The licensee shall report any operation or condition prohibited by the Plant's Technical Specifications.

The following commitments are being made by this letter:

j

1. Engineering Department will assign an owner to oversee the Leak Reduction Program to meet TS requirement 6.8.D.I. Due date 041598.

2.

QTP 0500-14 (and associated QCTP 0820-08) will be revised to better

)

encompass the program requirements, re-evaluate specific system operating '

procedures and existing station programs which meet periodic inspection requirements, address periodic inspections outside the normal annual periodicity (i.e. when systems are not operated or pressurized during the normal operating cycle) and will refer to TS section 6.8.D.1. Due date 071598.

3.

The remaining system visual leak inspections required to be completed and documented per QTP 0500-14 will be completed as soon as practicable based on system availability. Due date 063098. )

6 l

s 9803130371 980306 PDR ADOCK 05000254 S PDR

@!El4NMqip A 1 nkom ( omp.m3

USNRC

. SVP-98-084 2 March 6,1998 If there are any questions or comments concerning this letter, please refer them to Charles Peterson, Regulatory Affairs Manager at 309-654-2241, ext. 3609.

Respe tfully,

, .to ' A bbh

, S. Kran, Jr.

Site Vice President Quad Cities Station ESK/CP/pim Enclosure cc: A. B. Beach, Regional Administrator, Region III R. M. Pulsifer, Project Manager, NRR C. G. Miller, Senior Resident Inspector, Quad Cities W. D. Leech, MidAmerican Energy Company I D. C. Tubbs, MidAmerican Energy Company M. E. Wagner, Licensing, Comed f I