ML20102B617

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Rept 50-305/84-21.Corrective Actions:Surveillance Procedures Which Provide Exercise Timing Tests Being Reviewed & Revised to Require Timing from Initiation of Actuating Signal
ML20102B617
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 02/14/1985
From: Hintz D
WISCONSIN PUBLIC SERVICE CORP.
To: Little W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
CON-NRC-85-23 NUDOCS 8503040199
Download: ML20102B617 (4)


Text

-

NRC-85-23 WISCONSIN PUBLIC SERVICE CORPORATION P.O. Box 1200, Green Bay, WI 54305 February 14, 1985 Mr. William S. Little Chief, Operations Branch Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Little:

Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant Inspection Report 84-21

Reference:

Letter from W. S. Little (NRC) to D. C. Hintz (WPSC) dated January 15, 1985, transmitting Inspection Report 50-305/84-21 The attachment to this letter details our response to the items of non-compliance identified in inspection report 50-305/84-21(DRS).

Very truly yours,

{&<u Seu i

D. C. Hintz [

Manager - Nuclear Power OSN/jks Attach, cc - Mr. S. A. Varga, US NRC Mr. Robert Nelson, US NRC Og3040199850214 G ADOCK 05000305 PDR gg95 iPn\\

Mr. W. S. Litt10 N1-57.2 February 14, 1985 Page 1 Attachment Response to Items of Noncompliance Inspection Report 84-21 -

Items of Noncompliance

1. Kewaunee Technical Specification 4.2, ASME Code Class In-Service Inspection and Testing, states that the inservice testing of pumps and valves shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code except where relief is granted by the Commission.

Contrary to the above, the licenseo failed to request relief from Code testing requirements prior to implementing testing that was at variance with the Code in three areas:

a. Stroke timing of valves did not include the elapsed time from initiation of the actuating signal to the end of the actuating cycle as required by Subsection IWV-3413 of Section XI.
b. Pump suction pressure was not measured with the pump idle as required by Subsection IWP-3100.
c. Valve leak testing and corrective action was implemented per the method described in 10 CFR 50, Appendix J, in lieu of that described in Subsection IWV-3420 through IWV-3427.

This is a Severity Level V violation (Supplement I).

Response

a. The surveillance procedures which provide the exercise timing tests are being reviewed and revised to require timing from initiation of the actuating signal to the end of the actuating cycle. The operations personnel will time the valve travel by starting the stopwatch when the control switch in the control room is actuated and stop the watch upon illumination of the position (open/close) indicating light.

Previous timing tests were performed from light to light (limit switch indicators). We expect the valve timing test procedures to be revised by August 1, 1985.

.=

Mr. W. S. Little February 14, 1985 Page 2

b. The pump test procedures are being revised to require measurement of suction pressure with the pump idle in addition to the already measured suction pressure during pump operation. The idle pump suction pressure will be measured for those pumps for which previous relief requests have not been requested. If relief has previously been requested for measurement of the suction pressure it is to be understood that the relief applies to both the operating and idle pump conditions. The procedure revisions to incorporate this measurement will be completed by August 1, 1985.
c. A relief request describing our intent to perform containment isolation valve leakage testing and corrective actions in accordance with 10 CFR 50, Appendix J in lieu of that described in Subsections IWV-3420 through IWV-3427, has been generated and will be submitted by March 1, 1985.

Item of Noncompliance

2. Criterion XII of 10 CFR 50, Appendix B, as implemented by Wisconsin Public Service Corporation, " Operational Quality Assurance Program Manual," Section 10, requires the use of calibrated equipment in " activities affecting quality."

Contrary to the above, the licensee failed to require the use of calibrated tachometers or stopwatches in their surveillance testing procedures.

This is a Severity Level V violation (Supplement I).

Response

We are currently reviewing our inservice testing surveillance procedures to .

identify the measuring and testing devices used to implement the inservice testing program. We will verify that the testing devices identified receive periodic calibration.

. . . Mr. W. S. Little February 14, 1985 Page 3 In an effort to assure that calibrated equipment is used during testing we will also revise the inservice testing surveillance procedures to require iden-

~

tification of the instrument used. ,

We expect this effort to be completed by August 1, 1985.

Other Items Unresolved 1, tem 84-21-02 regarding remote position indicator verification has been evaluated. We are implementing a program which will verify that the limit switches for the valves included in the inservice testing program are set such that the remote position indicators (lights) in the control room are accurately indicative of actual valve position. We will keep the NRC inspector Mr. P. R.

Wohld informed of our progress on this project.