UNITED STATES NUCLEAR REGULATORY COMMISSION ust 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR H. B. ROBINSON STEAM ELECTRIC PLANT - NRC INSPECTION REPORT 05000261/2017005

Dear Mr. Kapopoulos:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for H. B. Robinson Steam Electric Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4609 with any questions you have regarding this letter.

Sincerely,

/RA/

Steven D. Rose, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-261 License Nos.: DPR-23 Enclosure:

Robinson Inspection/Activity Plan (09/01/2017 - 06/30/2019)

cc Distribution via ListServ SUBJECT: UPDATED INSPECTION PLAN FOR H. B. ROBINSON STEAM ELECTRIC PLANT - NRC INSPECTION REPORT 05000261/2017005 August 28, 2017 DISTRIBUTION:

M. Kowal, RII S. Price, RII K. Sloan, RII OE MAIL RIDSNRRDIRS PUBLIC RIDSNrrPMRobinson Resource ROPassessment Resource ROPreports Resource Institute of Nuclear Power Operations (INPO)

ADAMS Accession No. ML17240A298 OFFICE RII: DRP RII: DRP RII: DRP NAME DJackson JDodson SRose DATE 8/15/2017 8/15/2017 8/28/2017 OFFICIAL AGENCY RECORD

Page 1 of 2 Robinson 08/23/2017 14:09:45 Inspection / Activity Plan Report 22 09/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site ASM EP - 2017 EP ASM & RES BASELINE 2 2 01/01/2017 12/31/2017 IP 7111406 Drill Evaluation OL EXAM - INITIAL LICENSE EXAM PREP 3 2 08/28/2017 09/01/2017 V23500 ROBINSON/SEPTEMBER 2017 INITIAL EXAM AT POWER FACILITIES EQI - DESIGN BASES ASSURANCE INSPECTION (PROGR 3 2 09/11/2017 09/15/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

2 10/02/2017 10/06/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

2 10/16/2017 10/20/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

OL EXAM - INITIAL LICENSE EXAM 3 2 09/25/2017 10/06/2017 V23500 ROBINSON/SEPTEMBER 2017 INITIAL EXAM AT POWER FACILITIES TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 5 2 11/27/2017 12/01/2017 IP 7111105T Fire Protection [Triennial]

2 12/11/2017 12/15/2017 IP 7111105T Fire Protection [Triennial]

MODS - PERMENANT PLANT MODIFICATION 3 2 02/26/2018 03/02/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 4 2 03/05/2018 03/09/2018 IP 71152B Problem Identification and Resolution 2 03/19/2018 03/23/2018 IP 71152 Problem Identification and Resolution EP - EP PROGRAM INSPECTION 3 2 03/12/2018 03/16/2018 IP 7111402 Alert and Notification System Testing 2 03/12/2018 03/16/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 2 03/12/2018 03/16/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 2 03/12/2018 03/16/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 2 03/12/2018 03/16/2018 IP 71151 Performance Indicator Verification RP - RP PUBLIC INSPECTION 2 2 06/11/2018 06/15/2018 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 2 06/11/2018 06/15/2018 IP 71124.07 Radiological Environmental Monitoring Program 2 06/11/2018 06/15/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 2 06/11/2018 06/15/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences HS - TRIENNIAL HEAT SINK PERFORMANCE 1 2 06/18/2018 06/22/2018 IP 7111107T Heat Sink Performance ISI - UNIT 2 IN-SERVICE INSPECTION & RVH EXAM 2 2 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Robinson 08/23/2017 14:09:45 Inspection / Activity Plan Report 22 09/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RP - RAD HAZARD AND TRANSPORTATION 2 2 09/24/2018 09/28/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 2 09/24/2018 09/28/2018 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation LR - POST-APPROVAL LR PHASE 4 2 2 12/03/2018 12/07/2018 IP 71003 Post-Approval Site Inspection for License Renewal DBAI - DESIGN BASES ASSURANCE INSPECTION (TEAMS 6 2 04/08/2019 04/12/2019 IP 7111121M Design Bases Assurance Inspection (Teams)

2 04/29/2019 05/03/2019 IP 7111121M Design Bases Assurance Inspection (Teams)

2 05/13/2019 05/17/2019 IP 7111121M Design Bases Assurance Inspection (Teams)

EP - EP EXERCISE INSPECTION 6 2 05/20/2019 05/24/2019 IP 7111401 Exercise Evaluation 2 05/20/2019 05/24/2019 IP 7111404 Emergency Action Level and Emergency Plan Changes 2 05/20/2019 05/24/2019 IP 7111408 Exercise Evaluation - Scenario Review 2 05/20/2019 05/24/2019 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.