March 4, 2015
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR H.B. ROBINSON STEAM ELECTRIC PLANT - NRC INSPECTION REPORT 05000261/2014001
Dear Mr. Glover:
On February 11, 2015, the NRC completed its end-of-cycle performance review of the H.B. Robinson Steam Electric Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, the H.B. Robinson Steam Electric Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at H.B. Robinson Steam Electric Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
We also plan on conducting the following infrequently performed inspections and temporary instructions: Operator Licensing Exams, and TI 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4645 with any questions you may have regarding this letter.
Sincerely,
/RA/
George T. Hopper, Chief
Reactor Projects Branch 4
Division of Reactor Projects
Docket No.:
50-261 License No.: DPR-23
Enclosure: Robinson Inspection/Activity Plan (03/01/2015 - 06/30/2016)
cc Distribution via ListServ
_________________________
SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE DRP:RII DRP:RII DRP:RII
SIGNATURE DXW4 JSD GTH
NAME D. Jackson J. Dodson G. Hopper
DATE 02/13/2015 03/04/2015 02/20/2015
E-MAIL COPY?
YES NO YES NO YES NO Letter to Richard Michael Glover from George T. Hopper dated March 4, 2015.
SUBJECT: ANNUAL ASSESSMENT LETTER FOR H.B. ROBINSON STEAM ELECTRIC PLANT - NRC INSPECTION REPORT 05000261/2014001
DISTRIBUTION:
D. Gamberoni, RII L. Gibson, RII OE MAIL RIDSNRRDIRS PUBLIC RidsNrrRobinson Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
Page 1 of 2 03/04/2015 12:10:24 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Robinson Inspection / Activity Plan 03/01/2015 - 06/30/2016 ASM EP
2 IP Drill Evaluation 7111406 01/01/2015 12/31/2015 OL RQ
- REQUAL INSP
2 IP Licensed Operator Requalification Program 7111111B 03/02/2015 03/06/2015 RP
- RP OCCUPATIONAL BASELINE WEEK 1
2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/11/2015 05/15/2015
IP Occupational ALARA Planning and Controls 71124.02 05/11/2015 05/15/2015
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/11/2015 05/15/2015
IP Occupational Dose Assessment 71124.04 05/11/2015 05/15/2015
IP Radiation Monitoring Instrumentation 71124.05 05/11/2015 05/15/2015
IP Performance Indicator Verification 71151 05/11/2015 05/15/2015 ISI
- UNIT 2 IN-SERVICE INSPECTION & RVH EXAM
2 IP Inservice Inspection Activities - PWR 7111108P 05/18/2015 05/22/2015 RP
- RP OCCUPATIONAL BASELINE WEEK 2
2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/18/2015 05/22/2015
IP Occupational ALARA Planning and Controls 71124.02 05/18/2015 05/22/2015
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/18/2015 05/22/2015
IP Occupational Dose Assessment 71124.04 05/18/2015 05/22/2015
IP Radiation Monitoring Instrumentation 71124.05 05/18/2015 05/22/2015
IP Performance Indicator Verification 71151 05/18/2015 05/22/2015 HS
- TRIENNIAL HEAT SINK PERFORMANCE
2 IP Heat Sink Performance 7111107T 07/06/2015 07/10/2015 EP
- EP EXERCISE
2 IP Exercise Evaluation 7111401 07/20/2015 07/24/2015
IP Emergency Action Level and Emergency Plan Changes 7111404 07/20/2015 07/24/2015
IP Performance Indicator Verification 71151 07/20/2015 07/24/2015 MODS
- PLANT MODIFICATIONS INSPECTION
2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 10/26/2015 10/30/2015
IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 11/16/2015 11/20/2015 ASM EP
2 IP Drill Evaluation 7111406 01/01/2016 12/31/2016 OL EXAM
- INITIAL LICENSE EXAM PREP
2 ROBINSON/SEPTEMBER 2015 INITIAL EXAM AT POWER FACILITIES V23459 01/04/2016 01/08/2016 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Page 2 of 2 03/04/2015 12:10:24 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Robinson Inspection / Activity Plan 03/01/2015 - 06/30/2016 RP
- RP PUBLIC RAD SAFETY BASELINE
2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 01/25/2016 01/29/2016
IP Radiological Environmental Monitoring Program 71124.07 01/25/2016 01/29/2016
IP Performance Indicator Verification 71151 01/25/2016 01/29/2016 OL EXAM
- INITIAL LICENSE EXAM
2 ROBINSON/SEPTEMBER 2015 INITIAL EXAM AT POWER FACILITIES V23459 02/01/2016 02/12/2016 PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION
2 IP Problem Identification and Resolution 71152B 03/07/2016 03/11/2016
IP Problem Identification and Resolution 71152B 03/21/2016 03/25/2016 EP
- EP PROGRAM INSPECTION
2 IP Alert and Notification System Testing 7111402 06/20/2016 06/24/2016
IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 06/20/2016 06/24/2016
IP Emergency Action Level and Emergency Plan Changes 7111404 06/20/2016 06/24/2016
IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 06/20/2016 06/24/2016
IP Performance Indicator Verification 71151 06/20/2016 06/24/2016 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.