ML22258A030
| ML22258A030 | |
| Person / Time | |
|---|---|
| Site: | Oconee, Mcguire, Catawba, Brunswick, Robinson, McGuire |
| Issue date: | 09/15/2022 |
| From: | Ellis K Duke Energy Progress |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML22258A029 | List: |
| References | |
| RA-22-0262 | |
| Download: ML22258A030 (2) | |
Text
KEVIN M. ELLIS General Manager Nuclear Regulatory Affairs, Policy &
Emergency Preparedness 13225 Hagers Ferry Rd., MG011E Huntersville, NC 28078 704-382-8004 Kevin.Ellis@duke-energy.com Serial: RA-22-0262 10 CFR 50, Appendix E September 15, 2022 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Docket Nos. 50-325, 50-324 / Renewed License Nos. DPR-71 And DPR-62 Catawba Nuclear Station, Unit Nos. 1 and 2 Docket Nos. 50-413, 50-414 / Renewed License Nos. NPF-35 and NPF-52 McGuire Nuclear Station, Unit Nos. 1 and 2 Docket Nos. 50-369, 50-370 / Renewed License Nos. NPF-9 and NPF-17 Oconee Nuclear Station, Unit Nos. 1, 2, and 3 Docket Nos. 50-269, 50-270, and 50-287 / Renewed License Nos. DPR-38, DPR-47, and DPR-55 H. B. Robinson Steam Electric Plant, Unit No. 2 Docket No. 50-261 / Renewed License No. DPR-23
SUBJECT:
2022 Evacuation Time Estimate Reports for Brunswick, Catawba, McGuire, Oconee, and H.B. Robinson
U.S. Nuclear Regulatory Commission RA-22-0262 Page 2 Ladies and Gentlemen:
Pursuant to 10 CFR 50, Appendix E, Section IV, Paragraph 4, Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC (referred to collectively as Duke Energy) is providing the 2022 Evacuation Time Estimate (ETE) Reports for Brunswick Steam Electric Plant Units 1 and 2 (BNP), Catawba Nuclear Station Units 1 and 2 (CNS), McGuire Nuclear Station Units 1 and 2 (MNS), Oconee Nuclear Station Units 1, 2, and 3 (ONS), and H. B. Robinson Steam Electric Plant Unit 2 (RNP) to the Nuclear Regulatory Commission (NRC). The BNP, CNS, MNS, ONS, and RNP 2022 ETE Reports are provided in Enclosures 1, 2, 3, 4, and 5 respectively.
This submittal contains no new regulatory commitments.
Should you have any questions concerning this letter, or require additional information, please contact Ryan Treadway, Fleet Licensing Director, at (980) 373-5873.
Sincerely, Kevin M. Ellis General Manager, Nuclear Regulatory Affairs, Policy & Emergency Preparedness
Enclosures:
cc:
1.
Brunswick 2022 Evacuation Time Estimate Report 2.
Catawba 2022 Evacuation Time Estimate Report 3.
McGuire 2022 Evacuation Time Estimate Report 4.
Oconee 2022 Evacuation Time Estimate Report 5.
Robinson 2022 Evacuation Time Estimate Report L. Dudes, USNRC, Region II Regional Administrator L. Haeg, USN RC NRR Project Manager for BNP and RNP Z. Stone, USN RC NRR Project Manager for CNS J. Klos, USNRC NRR Project Manager for MNS S. Williams, USN RC NRR Project Manager for ONS G. Smith, USN RC Senior Resident Inspector for BNP J. Austin, USN RC Senior Resident Inspector for CNS A. Hutto, USN RC Senior Resident Inspector for MNS J. Nadel, USN RC Senior Resident Inspector for ONS M. Fannon, USNRC Senior Resident Inspector for RNP