MONTHYEARIR 05000261/20240032024-10-30030 October 2024 Integrated Inspection Report 05000261/2024003 ML24297A2182024-10-28028 October 2024 – NRC Operator License IR 05000261/20244022024-10-16016 October 2024 – Security Target Set Baseline Inspection Report 05000261/2024402 IR 05000261/20244012024-09-11011 September 2024 Security Baseline Inspection Report 05000261/2024401 IR 05000261/20240052024-08-22022 August 2024 Updated Inspection Plan for H.B. Robinson Steam Electric Plant - Report 05000261/2024005 ML24169A2712024-08-14014 August 2024 – Issuance of Amendment No. 280 to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification 5.7, High Radiation Area IR 05000261/20240022024-08-0101 August 2024 Integrated Inspection Report 05000261/2024002 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000261/20240112024-06-0303 June 2024 Focused Engineering Inspection- Commercial Grade Dedication Report 05000261/2024011 ML24114A0152024-06-0303 June 2024 Unit 2 – Issuance of Amendment No. 279 Regarding Application of Leak-Before-Break Methodology for Auxiliary Reactor Coolant System Piping IR 05000261/20240012024-05-0909 May 2024 Integrated Inspection Report 05000261/2024001 IR 05000261/20240102024-04-30030 April 2024 Biennial Problem Identification and Resolution Inspection Report 05000261/2024010 IR 05000261/20230062024-02-28028 February 2024 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 - Report 05000261-2023006 IR 05000261/20243012024-02-0606 February 2024 – Notification of Licensed Operator Initial Examination 05000261/2024301 ML24033A0592024-02-0202 February 2024 Response to Request for Additional Information License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology IR 05000261/20230042024-01-31031 January 2024 Integrated Inspection Report 05000261/2023004 ML24009A2432024-01-25025 January 2024 Unit, No. 2 - Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0047 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24009A2712024-01-24024 January 2024 Revision to Reactor Vessel Material Surveillance Capsule Withdrawal Schedule ML23354A0052024-01-0808 January 2024 Request for Withholding Information from Public Disclosure, H. B. Robinson Steam Electric Plant, Unit No. 2 ML23342A0902023-12-0808 December 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000261/20234202023-11-30030 November 2023 Security Baseline Inspection Report 05000261/2023420 (Cover Letter with Report) IR 05000261/20230102023-11-28028 November 2023 Fire Protection Team Inspection Report 05000261/2023010 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000261/20230032023-11-0707 November 2023 – Integrated Inspection Report 05000261 2023003 and 07200060 2023001 ML23226A0862023-10-12012 October 2023 Issuance of Amendment No. 277 Regarding Revision of TSs to Add High-High Steam Generator Level Function to Table 3.3.2-1 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23235A0552023-08-23023 August 2023 – Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) IR 05000261/20230052023-08-21021 August 2023 Updated Inspection Plan for H.B. Robinson Steam Electric Plant (Report 05000261/2023005) 05000261/LER-2023-002, Plant Trip During Reactor Protection System Testing2023-08-17017 August 2023 Plant Trip During Reactor Protection System Testing 05000261/LER-2023-001, Condition Prohibited by Technical Specification Due to Missed Entry Into Limiting Condition for Operation2023-08-10010 August 2023 Condition Prohibited by Technical Specification Due to Missed Entry Into Limiting Condition for Operation IR 05000261/20230022023-08-0707 August 2023 – Integrated Inspection Report 05000261/2023002 IR 05000261/20234022023-05-30030 May 2023 – Cyber Security Inspection Report 05000261/2023402 ML23145A1602023-05-25025 May 2023 Submittal of Updated Final Safety Analysis Report (Revision No. 30), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 28), Technical Specifications Bases Revisions, Quality IR 05000261/20230012023-05-0202 May 2023 Integrated Inspection Report 05000261/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000261/20220062023-03-0101 March 2023 Annual Assessment Letter for H.B. Robinson Steam Electric Plant, Unit 2 (Report 05000261/2022006) ML23047A4512023-02-21021 February 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000261/2023402 ML23041A2272023-02-13013 February 2023 2022 Q4 Robinson_Workflow Final ML22329A2982023-01-19019 January 2023 Issuance of Amendment No. 274 Regarding Revision of Technical Specification 3.8.1 Surveillance Requirement 3.8.1.16 ML22294A0922022-12-15015 December 2022 Issuance of Amendment No. 273 Regarding Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML22339A1362022-12-0101 December 2022 2023 Requalification Program Inspection - H.B. Robinson Nuclear Plant ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22322A1322022-11-18018 November 2022 301, NRC Operator License Examination Report & Cover Letter Merged ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000261/20220032022-11-0303 November 2022 – Integrated Inspection Report 05000261 2022003 IR 05000261/20224022022-10-19019 October 2022 Security Baseline Inspection Report 05000261/2022402 IR 05000261/20220102022-09-26026 September 2022 – Design Basis Assurance Inspection (Teams) Inspection Report 05000261/2022010 2024-09-11
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 February 6, 2017 EA-16-227 Mr. Ernest J. Kapopoulos, Jr.
Site Vice President H. B. Robinson Steam Electric Plant Duke Energy 3581 West Entrance Road, RNPA01 Hartsville, SC 29550 SUBJECT: H.B. ROBINSON STEAM ELECTRIC PLANT - NOTICE OF VIOLATION; NRC INSPECTION REPORT NO. 05000261/2017405; AND INVESTIGATION REPORT NO. 2-2016-001
Dear Mr. Kapopoulos:
This refers to an investigation completed on September 30, 2016, by the Nuclear Regulatory Commissions (NRC) Office of Investigations (OI) concerning activities at Duke Energys H. B. Robinson Steam Electric Plant (Robinson). The purpose of the investigation was to review a security incident that was identified on September 23, 2015. The results of the investigation, including the identification of an apparent violation, were described in NRC Inspection Report (IR) 05000261/2016404 dated December 27, 2016.
In the letter transmitting the inspection report, we provided you with the opportunity to address the apparent violation identified in the report by either attending a pre-decisional enforcement conference or by providing a written response before we made our final enforcement decision.
In a letter dated January 24, 2017, you provided a response to the apparent violation.
As documented in your written response, you accepted the violation and facts as described in the inspection report, acknowledged the significance of the issue and the need for lasting and effective corrective actions, and provided details of your corrective actions to preclude recurrence.
Based on the information developed during the investigation and the information provided in your written response, the NRC has determined that a violation of NRC requirements occurred.
The violation is cited in the enclosed Notice of Violation (Notice, Enclosure 1), and the circumstances surrounding it are described in detail in the subject NRC Inspection Report.
Enclosure 2 to this letter describes the basis for determining the severity level of the violation and the basis for the NRCs conclusion that a civil penalty is not warranted. For administrative purposes, this letter is issued as NRC Inspection Report 05000261/2017405.
Accordingly, the AV documented in NRC Inspection Report 05000261/2016404 is designated as VIO 05000261/2017405-001.
The NRC has concluded that information regarding: (1) the reason for the violation; (2) the corrective actions that have been taken and the results achieved; and (3) the date when full compliance was achieved is already adequately addressed on the docket in Duke Energys written response dated January 24, 2017. Therefore, you are not required to respond to this letter unless the description therein does not accurately reflect your corrective actions or your position. In that case, or if you choose to provide additional information, you should follow the instructions specified in the enclosed Notice.
This cover letter will be made available for public inspection in the NRCs Agencywide Documents Access and Management System (ADAMS) at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
The material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs ADAMS, accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Should you have any questions concerning this letter, please contact me at 404-997-4600.
Sincerely,
/RA/
Catherine Haney Regional Administrator Docket No. 50-261 License No. DPR-23 Enclosures:
1. Notice of Violation 2. Severity Level and Civil Penalty Assessment cc: (See page 3) cc:
Jeffrey Remick, Director Nuclear Plant Security H.B. Robinson Steam Electric Plant 3581 West Entrance Road, RNPA02 Hartsville, South Carolina 29550 Edward T. ONeil, General Manager Nuclear Protective Services Duke Energy Corporation 526 South Church Street, Phase II, EC5ZD Charlotte, NC 28202 _________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS-PSB2 RII:DRS RII:EICS RII:EICS RII;DRS RII:ORA RII:ORA SIGNATURE JOB2 * BBD * MXK7 SAP1 VIA ATG * LXW1 CXH EMAIL *
NAME JBROWN BDESAI MKOWAL SPRICE AGODY LWERT CHANEY DATE 1/25/2017 1/27/2017 2/3/2017 1/26/2017 1/30/2017 2/6/2017 2/6/2017 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICE OE OGC NSIR NRR SIGNATURE DXF4 VIA DDS1 VIA AXR2 VIA LRC1 VIA EMAIL EMAIL EMAIL EMAIL NAME DFURST DSTRAUS ARICHARDSON LCASEY DATE 2/2/2017 2/1/2017 1/31/2017 2/1/2017 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO