MONTHYEARML24128A2102024-05-0707 May 2024 Public Meeting Summary - 2023 Annual Assessment Meeting Regarding Saint Lucie ML22132A0032024-04-23023 April 2024 Summary of Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML23276A1852023-09-25025 September 2023 Subsequent License Renewal Draft EIS Public Meetings: Meeting Summary ML23221A3782023-08-16016 August 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23166A0042023-06-15015 June 2023 Summary of Meeting Concerning 2023 Annual Assessment of the Saint Lucie and the Turkey Point Nuclear Plants ML23087A0692023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23058A4262023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML23108A2752023-05-0202 May 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 ML23068A0712023-04-28028 April 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units Nos. 3 and 4 (EPID L-2022-LLA-0105) - Nonproprietary ML23107A2312023-04-18018 April 2023 Summary Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23081A5022023-03-28028 March 2023 Summary of Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Transition to a 24-Month Fuel Cycle ML23069A0282023-03-15015 March 2023 Summary of January 31, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23066A0872023-03-15015 March 2023 Summary of Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23044A4172023-03-0606 March 2023 Summary of January 17, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests ML23048A0492023-03-0303 March 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22357A0742023-01-19019 January 2023 Summary of December 1, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22349A0012023-01-0505 January 2023 Summary of Audit Meeting with Florida Power and Light Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Turkey Point, Units 3 and 4 ML22327A2402022-12-0808 December 2022 Summary of October 27, 2022, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Requests ML22276A2302022-10-0606 October 2022 Summary of September 13, 2022, Public Meeting with FPL Concerning Supplemental Information Needed for Acceptance of License Amendment Request to Replace Instrumentation with Digital Systems on Turkey Point, Units 3 and 4 ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22238A2762022-08-29029 August 2022 Summary of August 17, 2022, Meeting with Florida Power and Light/Nextera to Discuss a Turkey Point Planned License Amendment Request to Extend the Completion Time for an Inoperable Reactor Trip Breaker ML22229A5252022-08-24024 August 2022 Summary of August 11, 2022, Mtg. with Florida Power & Light/Nextera on St. Lucie and Turkey Point Improved Technical Specification Conversion License Amendment Request (EPIDs L-2021-LLI-0000 & -0002) ML22228A2352022-08-23023 August 2022 Summary of July 28, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22228A2032022-08-22022 August 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22195A1752022-07-27027 July 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22186A0812022-07-15015 July 2022 Summary of June 22, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Fire Protection Program Changes ML22167A1852022-06-30030 June 2022 Summary of June 6, 2022, Meeting with Duke Energy to Discuss Shearon Harris Nuclear Power Plant, Unit 1 Closeout of Generic Safety Issue (GSI) 191 ML22160A3792022-06-30030 June 2022 Summary of May 24, 2022, Closed Meeting with Florida Power and Light to Discuss Planned License Amendment Request Related to Reactor Coolant Pump Seal Replacements ML22154A5202022-06-0909 June 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22154A5112022-06-0707 June 2022 Summary of May 19, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22145A3932022-05-25025 May 2022 Public Meeting Summary 2021 Annual Assessment Meeting 20220434 ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 ML22118A3582022-05-10010 May 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22089A1382022-04-0505 April 2022 Summary of March 24, 2022, Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22066A7852022-03-23023 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22070A5632022-03-21021 March 2022 Summary of Meeting with Florida Power and Light/Nextera on Turkey Point Improved Technical Specification Conversion License Amendment Request ML22054A0082022-03-0303 March 2022 Summary of February 17, 2022, Partially Closed Meeting with Florida Power and Light to Discuss Intake Cooling Water Discharge Piping Proposed Alternative ML22020A4032022-02-0707 February 2022 Summary of November 17, 2021, Meeting with Florida Power and Light/Nextera on Improved Technical Specification Conversion License Amendment Requests (EPIDs L-2021-LLI-0000 and L-2021-LLI-0002) ML21342A3752022-01-0606 January 2022 Summary of Meeting with Florida Power and Light/Nextera on Proposed Improved Technical Specification Conversions ML21327A1802021-12-0707 December 2021 Summary of August 25, 2021 Observation Public Meeting with FPL to Discuss Proposed Alternative Report for the Intake Cooling Water System ML21246A0212021-11-23023 November 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 ML21279A0432021-10-15015 October 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 ML21285A0412021-10-13013 October 2021 Summary of September 29, 2021 Meeting with the U.S. Fish and Wildlife Service Regarding Crocodile Monitoring at Turkey Point ML21190A1862021-08-0202 August 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 ML21176A0102021-06-29029 June 2021 Summary of Drop-in Meeting with NextEra-Florida Power and Light to Discuss Pending Submittals Related to Digital Instrumentation and Controls and Improved Standard Technical Specifications for Turkey Point Nuclear Plant, Units 3 & 4 (EPID L ML21159A1352021-06-0808 June 2021 Public Meeting Summary Regarding the Saint Lucie Nuclear Plant, Units 1 and 2, Docket No. 50-335 and 389, and the Turkey Point Nuclear Generating Station Units 3 and 4, Docket No. 50-250 and 50-251; Meeting Number 20210505 ML21158A0572021-06-0707 June 2021 Summary of May 3, 2021, Teleconference with the U.S. Fish and Wildlife Service and Florida Power & Light Company Regarding Injured American Crocodile at Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML21158A0582021-06-0707 June 2021 Summary of May 20, 2021, Teleconference with the Florida Power & Light Company Regarding Endangered and Threatened Species Reporting at Turkey Point Nuclear Generating Unit Nos. 3 and 4 2024-05-07
[Table view] |
Text
March 3, 2022
LICENSEE: Florida Power and Light Company/NextEra
FACILITY: Turkey Point Nuclear Generating Unit No. 3
SUBJECT:
SUMMARY
OF FEBRUARY 17, 2022, PARTIALLY CLOSED MEETING WITH FLORIDA POWER AND LIGHT TO DISCUSS INTAKE COOLING WATER DISCHARGE PIPING PLANNED ALTERNATIVE (EPID L-2021-LLR-0078)
On February 17, 2022, the U.S. Nuclear Regulatory Commission (N RC) staff held a partially closed meeting with representatives of Florida Power and Light Company (FPL or the licensee) to discuss a planned alternative request for the Intake Cooling Water (ICW) discharge piping line for the Turkey Point Nuclear Generating Unit No. 3. The m eeting notice and agenda for this meeting, dated February 4, 2022, are available in the Agencywid e Documents Access and Management System (ADAMS) at A ccession No. ML22035A022. A list of attendees is enclosed. No regulatory decisions were made at this meeting.
During licensees public presentation (ADAMS Accession No. ML22046A046), it described the leak discovery and leak location, pipe characteristics and flaw size, flaw evaluation, American Society of Mechanical Engineers (ASME) Code repair hardship, ri sks and planned alternative request, ASME Code Case N-513, Revision 4 (N-513-4), Evaluatio n Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Sect ion XI, Division 1 extension, flaw size non-destructive examination (NDE) results and status update, and restoration hardware assembly proposed alternative.
Details of the restoration hardware assembly were discussed in detail during the closed portion of the meeting.
No members of public were in attendance.
Please direct any inquiries to me at 301-415-3867 or Michael.Mahoney@nrc.gov.
/RA/
Michael Mahoney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-250
Enclosure:
List of Attendees
cc: Listserv LIST OF ATTENDEES
FEBRUARY 17, 2022, PUBLIC PORTION OF PARTIALLY CLOSED MEETING W ITH
FLORIDA POWER AND LIGHT
REGARDING INTAKE COOLING WATER DISCHAGE
PIPING PROPOSED ALTERNATIVE
Name Organization Mike Mahoney U.S. Nuclear Regulatory Commission (NRC)
Matt Mitchell NRC John Honcharik NRC
Stavroula Mihalakea Florida Power and Light Company (FPL)
Tom Ruiz FPL Robert Hess FPL Michael Koberling FPL Chuck Zyne FPL Chris Webb FPL Gary Priolo FPL Steve Catron FPL Swadesh Ramdeen FPL Donna Slivon FPL
Ken Hudson PMC Engineering Solutions, Inc. (FPL Vendor)
Paul Manzon PMC Engineering Solutions, Inc. (FPL Vendor)
Stephen Parker Structural Integrity Associates, Inc. (third par ty reviewer)
Enclosure
ML22054A008 OFFICE NRR/DORL/LPL2-2/PM NRR/DORL/LPL2-2/LA NRR/DORL/LPL2-2/BC NRR/DORL/LPL2-2/PM NAME MMahoney RButler DWrona MMahoney DATE 02/22/2022 02/25/2022 03/02/2022 03/03/2022