MONTHYEARML20217G4151999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2 TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Cpses.With ML20210U4081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2 ML20209G0801999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Cpses,Units 1 & 2 ML20195G5141999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Comanche Peak Steam Electric Station,Units 1 & 2.With ML20196L2241999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Cpses,Units 1 & 2 ML20205N3101999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Cpses,Units 1 & 2 ML20205N1481999-02-28028 February 1999 Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2 ML20204H6371999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Comanche Peak Units 1 & 2 ML20199E9961998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Cpses,Units 1 & 2 ML20197K2371998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Cpses,Units 1 & 2 ML20195F3161998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Cpses,Units 1 & 2 ML20154M8841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Cpses,Units 1 & 2 ML20151W0361998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Cpses,Units 1 & 2. with ML20237C6721998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Cpses,Units 1 & 2 ML20236R0711998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Cpses,Units 1 & 2 ML20249B2581998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Cpses,Units 1 & 2 ML20247G3241998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Cpses,Units 1 & 2 ML20216J3061998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Cpses,Units 1 & 2 ML20216J1861998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Comanche Peak Steam Electric Station ML20202H0431998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Cpses,Units 1 & 2 ML20198N7141997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Cpses,Units 1 & 2 ML20197J0941997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for CPSES Units 1 & 2 ML20199D2261997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Cpses,Units 1 & 2 TXX-9721, Monthly Operating Repts for Sept 1997 for Comanche Peak Steam Electric Station1997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Comanche Peak Steam Electric Station ML20212C4851997-08-31031 August 1997 Revised Monthly Operating Rept for Aug 1997 for CPSES Unit 2 ML20210V2101997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for CPSES ML20141J3911997-07-31031 July 1997 Monthly Operating Repts for July 1997 for CPSES ML20149E2991997-06-30030 June 1997 Monthly Operating Repts for June 1997 for CPSES TXX-9713, Monthly Operating Repts for May 1997 for CPSES1997-05-31031 May 1997 Monthly Operating Repts for May 1997 for CPSES TXX-9710, Monthly Operating Repts for Apr 1997 for Comanche Peak Steam Electric Station1997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Comanche Peak Steam Electric Station TXX-9708, Monthly Operating Repts for Mar 1997 for CPSES Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for CPSES Units 1 & 2 ML20137B9781997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for CPSES Units 1 & 2 ML20134Q2521997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20137B9901997-01-31031 January 1997 Revised MOR for Jan 1997 CPSES Unit 2 ML20133M1971996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Comanche Peak Steam Electric Station Units 1 & 2 ML20132C1631996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Comanche Peak Steam Electric Station TXX-9650, Monthly Operating Repts for Oct 1996 for Comanche Peak Steam Electric Station1996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Comanche Peak Steam Electric Station ML20129F1601996-09-30030 September 1996 Revised Monthly Operating Repts for Sept 1996 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20129B2401996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Comanche Peak Steam Electric Station ML20117N5201996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Comanche Peak Steam Electric Station ML20116N6651996-07-31031 July 1996 Monthly Operating Rept for July 1996 for Comanche Peak Unit 1 & 2 TXX-9640, Monthly Operating Rept for June 1996 for Comanche Peak Electric Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Comanche Peak Electric Station TXX-9638, Monthly Operating Repts for May 1996 for Comanche Peak Steam Electric Station Units 1 & 21996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Comanche Peak Steam Electric Station Units 1 & 2 ML20112A1951996-04-30030 April 1996 Monthly Operating Repts for April 1996 for CPSES TXX-9610, Monthly Operating Repts for March 1996 for CPSES1996-03-31031 March 1996 Monthly Operating Repts for March 1996 for CPSES ML20101D0461996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Comanche Peak Steam Electric Station Units 1 & 2 TXX-9601, Monthly Operating Repts for Jan 1996 for Comanche Peak Steam Electric Station,Units 1 & 21996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20101D0511996-01-31031 January 1996 Revised Monthly Operating Rept for Jan 1996 for Comanche Peak Steam Electric Station Unit 1 ML20096E7381995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Comanche Peak Steam Electric Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217E8021999-10-0707 October 1999 CPSES Unit 1 Cycle 8 Colr ML20217G4151999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2 ML20212F7671999-09-24024 September 1999 SER Granting Relief Request C-4 Pursuant to 10CFR50.55a(g)(6)(i) for Unit 2,during First 10-year ISI Interval & Relief Requests B-15,B-16 & B-17 Pursuant to 10CFR50.55a(g)(6)(i) ML20216J5701999-09-16016 September 1999 Rev 2 to CPSES Unit 2 Cycle 5 Colr TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Cpses.With ML20211M2981999-08-0606 August 1999 Rev 1 to CPSES Fuel Storage Licensing Rept, CPSES Credit for Soluble Boron & Expansion of Spent Fuel Storage Capacity, Consisting of Revised Title Page and 4-1 ML20210U4081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2 ML20210D8321999-07-23023 July 1999 Safety Evaluation Accepting Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20209H7661999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Comanche Peak Steam Electric Station,Units 1 & 2 ML20209H2721999-07-0909 July 1999 2RF04 Containment ISI Summary Rept First Interval,First Period,First Outage ML20209H2631999-07-0909 July 1999 2RF04 ISI Summary Rept First Interval,Second Period,Second Outage ML20209G7501999-07-0808 July 1999 SER Finding That Licensee Individual Plant Exam of External Events Complete with Regard to Info Requested by Suppl 4 to GL 88-20 & That IPEEE Results Reasonable Given Design, Operation & History of Comanche Peak Steam Electric Station ML20196L0191999-07-0808 July 1999 Safety Evaluation Granting Request Relief B-6 (Rev 2),B-7 (Rev2),B-12,B-13,B-14 & C-9,pursuant to 10CFR50.55a(g)(6)(i).Technical Ltr Rept Also Encl ML20210J9391999-06-30030 June 1999 CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20209G0801999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Cpses,Units 1 & 2 ML20196J0621999-06-29029 June 1999 Safety Evaluation Supporting Proposed Changes to Emergency Plan Re Licenses NPF-87 & NPF-89 Respectively ML20195G5141999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Comanche Peak Steam Electric Station,Units 1 & 2.With ML20216E0711999-05-21021 May 1999 1999 Graded Exercise - Comanche Peak Steam Electric Station ML20206Q0091999-05-14014 May 1999 Safety Evaluation Accepting GL 92-08, Thermo-Lag 330-1 Fire Barriers, Dtd 921217,for Comanche Peak Electric Station,Unit 1 ML20206H2061999-05-0606 May 1999 SER Accepting Exemption to App K Re Leading Edge Flowmeter for Plant,Units 1 & 2 ML20196L2241999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Cpses,Units 1 & 2 ML20205R5701999-04-14014 April 1999 Rev 6 to ER-ME-067, TU Electric Engineering Rept,Evaluation of Thermo-Lag Fire Barrier Sys ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20205J7831999-04-0101 April 1999 Rev 0 to ERX-99-001, CPSES Unit 2 Cycle 5 Colr ML20205N3101999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Cpses,Units 1 & 2 ML20204H6371999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Comanche Peak Units 1 & 2 ML20205N1481999-02-28028 February 1999 Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2 ML20203A4881999-02-0303 February 1999 Safety Evaluation Granting Requests for Relief B-3 - B-6,C-2 & C-3 for Plant,Unit 2 ML20210J9201999-02-0101 February 1999 CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802- 990201 ML20202D0101999-01-27027 January 1999 Safety Evaluation Supporting First 10-yr Interval ISI Program Plan Requests for Relief B-9,B-10 & B-11 for CPSES, Unit 1 ML20199E9961998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Cpses,Units 1 & 2 ML20207D6091998-12-31031 December 1998 1998 Annual Operating Rept for Cpses,Units 1 & 2. with ML20197K2371998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Cpses,Units 1 & 2 ML20195F3161998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Cpses,Units 1 & 2 ML20154M8841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Cpses,Units 1 & 2 ML20154B5741998-09-30030 September 1998 Safety Evaluation Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety- Related Motor-Operated Valves. Licensee Has Established Acceptable Program ML20151W0361998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Cpses,Units 1 & 2. with ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C4061998-08-14014 August 1998 Safety Evaluation Supporting Request to Implement Risk Informed IST Program ML20237C6721998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Cpses,Units 1 & 2 ML20236V3121998-07-29029 July 1998 Final Part 21 Rept Re Enterprise DSR-4 & DSRV-4 Edgs.Short Term Instability Was Found During post-installation Testing & Setup as Part of Design mod/post-work Testing Process. Different Methods Were Developed to Correct Problem ML20236R0711998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Cpses,Units 1 & 2 ML20249B2581998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Cpses,Units 1 & 2 ML20248A1671998-05-22022 May 1998 Interim Part 21 Re Enterprise DSR-4 & DSRV-4 Emergency diesel.Post-installation Testing Revealed,High Em/Rfi Levels Affected New Controllers,Whereas Original Controllers Were unaffected.Follow-up Will Be Provided No Later than 980731 ML20247G3241998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Cpses,Units 1 & 2 ML20216B8661998-04-0101 April 1998 Rev 0 to ERX-98-001, CPSES Unit 1 Cycle 7 Colr ML20216J3061998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Cpses,Units 1 & 2 ML20216J1861998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Comanche Peak Steam Electric Station ML20197A6951998-02-24024 February 1998 Inservice Insp Summary Rept,First Interval,Second Period, First Outage ML20199J5391998-02-0202 February 1998 CPSES Commitment Matl Change Evaluation Rept 0002 for 960202-970801 1999-09-30
[Table view] |
Text
. - - _ . _ _ ..
v MM (
{"
] Log # TXX 98201 File # 10010.2 l
l Ref. # 10CFR50.36 1UELECTRIC September 11, 1998 c.ame wrry Senior Mce President
& PrincipalNuclear oficer U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 !
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50 445 AND 50 446 MONTHLY OPERATING REPORT FOR AUGUST 1998
. Attached is the Monthly Operating Report for August,1998, prepared and submitted pursuant to Technical Specification 6.9.1.5 contained in Appendix A to the CPSES Units 1 and 2 Operating License Nos. NPF 87 and NPF-89, respectively. During this reporting period, there have been no failures or challenges to the Power Operated :
Relief Valves or Safety Valves for CPSES Unit 1 and Unit 2. t This communication contains no new licensing basis commitments regarding CPSES Unit I and Unit 2. Should you have any questions, please contact Douglas W. Snow at (254) 897 8448. .
1 Sincerely, h
C. L. Terry By: 844(
- R. D.%alker Regulatory Affairs Manager i DWS/dws
-Attachment c- Mr. E. W. Herschoff, Region IV Mr. J. I. Tapia. Region IV Mr. T. J. Polich NRR Resident Inspectors
~
4 $~*n. 4
., 9809150147 980831
- V V U U' U FDR AD3CK 05000445 R PDR COMANCllE PEAK STEAM ELEC'IRIC STATION P.O. Box 1002 Glen Rose. Texas 7604L1002
Attachment to TXX 98201 Page 1 of 8
,- COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 1 NRC MONTHLY OPERATING REPORT DOCKET NO.: 50-445 :
UNIT: CPSES 1 ;
DATE: 9/ 9/98 COMPLETED BY: Bob Reible TELEPHONE: 254 897-0449 OPERATING STATUS
- 1. REPORTING PERIOD: AUGUST 1998 GROSS HOURS IN REPORTING PERIOD: 744
- 2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWe Net): 1150 *
~ DESIGN ELECTRICAL RATING (MWe Net): 1150
- 3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe Net): NONE
- 4. REASON FOR RESTRICTION (IF ANY):
, THIS MONTH YR TO DATE CUMULATIVE
- 5. NUMBER OF HOURS REACTOR WAS CRITICAL 744 4,945 59,706
- 6. REACTOR RESERVE SHUTDOWN HOURS 0 0 2,632 l
' 7. . HOURS GENERATOR ON LINE 744 4,920 59,030
, 8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
- 9. GROSS THERMAL ENERGY GENERATED (MWH) 2,536,025 16.490,534 193.270,318
- 10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 840,242 5,533,418 64,605,378 l 11. NET ELECTRICAL ENERGY GENERATED (MWH) 805,031 5.294,387 61,696,699
! 12. REACTOR SERVICE FACTOR 100.0 84.8 84.6
- 13. REACTOR AVAILABILITY FACTOR 100.0 84.8 88.3 l
- 14. UNIT SERVICE FACTOR 100.0 84.4 83.6 l
l.15. UNIT AVAILABILITY FACTOR 100.0 84.4 83.6 !
-16. UNIT CAPACITY FACTOR (USING MDC) 94.1 79.0 76.0 ;
- 17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 94.1 79.0 76.0 l ' 18. UNIT FORCED OUTAGE RATE 0.0 0.0 3.9
- 19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH):
- 20. IF SHIRDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
22, . UNITS IN TEST STATUS (PRIOR TO COPNERCIAL OPERATION): ACHIEVED l
. COMMERCIAL OPERATION 900813
Attachment to TXX 98201
'Page 2. of 8 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50 445 UNIT: CPSES 1 DATE: 9/ 9/98 COMPLETED BY: Bob Reible 254 897 0449 TELEPHONE:
MONTH: AUGUST 1998 AVE:MGE DAILY POWER LEVEL- AVERAGE DAILY POWER LEVEL DAY (MWe Net) DAY (MWe Net) 1 1084 17 1082-2 1084 18 1081 3 .1083 19 1081 4 1082 20 1081 5 1082 21 1082 6 1083- 22 1082 7 1084 23 1083 8 1083 '24 1083 9 1083 25 1084 10 1083 26 1084 11 1081 27 1082 12 1080 28 1080 13 1081 29 1081 14 1082 30 1080 15 1082 31 1082 16 1082
l ' Attachment to TXX 98201 !
[ : Page 3 of 8 t
l SlH%RY OF OPERATING EXPERIENCE FOR THE MONTH ,
DOCKET NO.: 50 445 !
UNIT: CPSES- 1 i DATE: 9/ 9/98 l COMPLETED BY: Bob Reible i TELEPHONE: 254 897 0449 I I
MONTH: AUGUST 1998 l DAY TIME REMARK / MODE 08/01 0000 Unit began the month at 100% power. ,
08/31 2400 Unit ended the month at 100% power, i l
l
'!4
)
l 1
i i
I 1
j
('
i
! l l'
l
' Attachment to TXX-98201 Page 4 of 8 UNIT SHUTD06t:S AND POWER REDUCTIONS DOCKET NO.: 50-445 UNIT: CPSES 1 DATE: 9/ 9/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 REPORT MONTH: AUGUST 1998 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO .DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS / COW 1ENTS None .None
- 1) REASON 2) METHOD A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION 1: MANUAL B: MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCPAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4: OTHER (EXPLAIN)
i Attachment t@ TXX 98201 i Pa9e 5 of 8' 1 COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 l NRC MONTHLY OPERATING REPORT DOCKET No.: 50-446 UNIT: CPSES 2 DATE: 9/ 9/98 COMPLETED BY: Bob Reible TELEPHONF: 254-897 0449
-OPERATING STATUS
- 1. REPORTING PERIOD: AUGUST 1998 GROSS HOURS IN REPORTING PERIOD: 744 )
i
- 2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWe Net): 1150
- DESIGN ELECTRICAL RATING (MWe Net): 1150
- 3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe Net): NONE
- 4. REASON FOR RESTRICTION (IF ANY):
THIS MONTH YR TO DATE CUMULATIVE
- 5. NUM8ER OF HOURS REACTOR WAS CRITICAL 744 5,816 37,920 ,
- 6. REACTOR RESERVE SHUTDOWN HOUP,5 0 15 2,326 )
~7. HOURS GENERATOR ON LINE 744 5,812 37,601 ;
- 8. UNIT RESERVE SHUTDOWN HOURS 0 0 0 I
- 9. GROSS THERMAL ENERGY GENERATED (MWH) '2,048,722 18,960,372 122.066,258 671,683 6,411,706 41,213,018
- 10. GROSS ELECTRICAL ENERGY GENERATED (MWH)
)i
- 11. NET ELECTRICAL. ENERGY GENERATED (MWH) 638,941 6,155,556 39,446,337
- 12. REACTOR SERVICE FACTOR 100.0 99.7 85.2
- 13. REACTOR AVAILABILITY FACTOR 100.0 100.0 90.4
- 14. UNIT SERVICE FACTOR 100.0 99.7 84.5
- 15. UNIT AVAILABILITY FACTOR 100.0 99.7 84.5
- 16. UNIT CAPACITY FACTOR (USING MDC) 74.7 91.8 77.1 l
- 17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 74.7 91.8 77.1 18; UNIT FORCED OUTAGE RATE 0.0 0.3 5.0
- 19. SH'JTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH):
- 20. SHUTDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
- 21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED COMMERCIAL OPERATION 930803
' Attachment to TXX 98201
'Page 6 of 8 l
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50 446 UNIT: CPSES 2 DATE: 9/ 9/98 COMPLETED BY: Bob Reible !
TELEPHONE: 254 897 0449 -l MONTH: AUGUST 1998 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe Net) . DAY (MWe-Net) l' -
858 17 859 2 858 18 859 l
3 858 19 859 [
4 858 20 859 5 859 21 859- ;
6 859 22 859 i i
7 859 23 859 8 859 24 859 l 4 !
9 859 25 850 10 859 26 860 )
11 859 27 860 12 859 28 856 !
l 13 859 29 858 14 859 30 861 15 859 31 858 16 859
. . . - . _ . _ . . . . . .. - -. - . . . . - .... .. ~ . - . . . . - .- . . . - . - . . . ~ . . . . . - .
. .: l
' Attachment'to TXX 98201 !
,:Page 7 of 8 l SlH%RY OF OPERATING EXPERIENCE FOR THE MONTH DOCKET NO.: 50 446 !
UNIT: CPSES 2 DATE: 9/ 9/98 i COMPLETED BY: Bob Reible l TELEPHONE: 254 897 0449 !
i MONTH: AUGUST 1998 ;
DAY TIME REMARK / MODE:
08/01 0000 Unit began the month at 81% Reactor power to ensure the. <
turbine vibration level does not exceed established limits.
08/31 2400 Unit ended the month at 81% power.
l 1
l l
b l
l ,
e 4
G
,vw w - -
r, , -,
Attachment to TXX-982011 '.*
Page 8 cf 8 - ],
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-446 -
UNIT: CPSES 2-DATE: 9/ 9/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0 4 9 REPORT MONTH. AUGUST 1998 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS /COPt(ENTS 4a 980801 S H 4 On 07/16 at 0000, unit power was reduced to 81%
power to ensure the turbine blade vibrations did not exceed established limits. This planned reduction was a conservative response to expected high summer temperatures. Unit was at 81% power for the entire month.
- 1) REASON 2) METH00 A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION 1: MANUAL B: MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4: OTHER (EXPLAIN)
- _ _ _ - _ - _ _ . _ _ _ _ _ _ _ _ _ _ _ - _ - - _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - - - _ _ - . . - . - - - - - _. - , . . _ _ . - _ - . _ _ .