Text
.
.=.
~-
Attachment to TXX 97057 Page 9 of 9...
COMANCHE PEAK STEAM ELECTRIC STATION UNIT 2 NRC MONTHLY OPERATING REPORT REVISION 1 DOCKET NO.:
50 446 UNIT:
CPSES 2 DATE:
2/10/97 COMPLETED BY:
Bob Reible TELEPHONE:
897 0449 OPERATING STATUS 1.
REPORTING PERIOD:
JANJARY 1997 GROSS HOURS IN REPORTING PERIOD:
744 2.
CURRENTLY AlffHORIZED POWER LEVEL (MWt):
3411 MAX. DEPEND. CAPACITY (MWe Net):
1150 DESIGN ELECTRICAL RATING (MWe Net):
1150 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe Net):
NONE 4.
REASON FOR RESTRICTION (IF ANY):
THIS MONTH YR TO DATE CUMULATIVE 5.
NUMBER OF HOURS REACTOR WAS CRITICAL 662 662 25.143 6.
REACTOR RESERVE SHUTDOWN HOURS 82 82 2.311 7.
HOURS GENERATOR ON LINE 641 641 24.875 8.
UNIT RESERVE SHUTDOWN HOURS 0
0 0
9.
GROSS THERMAL ENERGY GENERAH D (MWH) 2.118,763 2.118.763 80.402.390 9
- 10. GROSS ELECTRICAL ENERGY GENERATED (lWH) 722.129 722.129 27.114.229
- 11. NET ELECTRICAL ENERGY GENERATED (MWH) 690.736 690.736 25.919.467
- 12. REACTOR SERVICE FACTOR 88.9 88.9 82.0
- 13. REACTOR AVAILABILITY FACTOR 100.0 100.0 89.8
- 14. UNIT SERVICE FACTOR 86.2 86.2 81.1
- 15. UNIT AVAILABILITY FACTOR 86.2 86.2 81.1
- 16. UNIT CAPACITY FACTOR (USING IOC) 80.7 80.7 73.5
- 17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 80.7 80.7 73.5
- 18. UNIT FORCED OUTAGE RATE 0.0 0.0 7.3
- 19. SHUTDOWNS SCHEDULED OVER NEXT 6 M0FTHS (TYPE. DATE. AND DURATION OF EACH):
None
- 20. IF SHUTDOWN AT END OF REPORTING PERIOD ESTIMATED DATE OF STARTUP:
- 21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
ACHIEVED COMMERCIAL OPERATION:
930803 ESTIMATED 9703240117 970314 PDR ADOCK 05000445' R