Monthly Operating Rept for July 1996 for Comanche Peak Unit 1 & 2
ML20116N665
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/31/1996
From: Samuel M, Woodlan D
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TXX-96436, NUDOCS 9608220230
Download: ML20116N665 (9)


Text

.

l M Log # TXX 96436 llllllll" = "

File # 10010.2 L _ Ref. # 10CFR50.36 r

= __

7UELECTRIC August 15, 1996 C. Lance Terry Group We PresiJens U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50 445 AND 50-446 MONTHLY OPERATING REPORT FOR JULY 1996 Gentlemen:

Attached is the Monthly Operating Report for July 1996, prepared and submitted pursuant to Technical Specification 6.9.1.5 contained in Appendix A to the Comanche Peak Steam Electric Station Units 1 and 2 Operating License Nos. NPF-87 and NPF-89, respectively. Should you have any questions, please contact Jacob M. Kulangara at (214) 812 8818.

Sincerely, C. L. Terry By: Nh D. R. Woodlan Docket Licensing Manager JMK/jmk Attachment cc: Mr. L. J. Callan, Region IV Ms. L. J. Smith, Region IV Mr. T. J. Polich, NRR Resident Inspectors fg2/ '/,

9608220230 960731 PDR R

ADOCK0500g5 Energy Plua 1601 Bryan Street Dalla. Texas 75201-3411

Attachment to TXX. 96436 Page 1. of 8 COMANCHE H AK STEAM ELECTRIC STATION, UNIT 1 NRC MONTHLY OPERATING REPORT

. DOCKET N0; 50445 UNIT: CPSES 1

! DATE: 8/11/96

, COMPLETED BY: MARK SAMUEL TELEPHONE: 897 5793

OPERATING STATUS
1. REPORTING PERIOD: JULY 1996 GROSS HOURSIN REPORTING PER00: 744
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWe Net): 1150
  • DESIGN ELECTRICAlRATING (MWs Net): 1150
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY)(MWe Net): NONE
4. REASON FOR RESTRICTION (IF ANY):

THIS MONTH YR TO DATE CUMULATIVE

5. NUMBER OF HOURS REACTOR WAS CRITICAL 744 4,680 43,431
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 2,604
7. HOURS GENERATOR ON LINE 744 4,644 42,833
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2,530,426 15,438,197 138,863,449
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 840,646 5,247,759 46,313,962
11. NET ELECTRIC AL ENERGY GENERATED (MWH) 805,610 5,017,642 44,184,835
12. REACTOR SERVICE FACTOR 100.0 91.6 83.0
13. REACTOR AVAILABILITY FACTOR 100.0 91.6 88.0
14. UNIT SERVICE FACTOR 100.0 90.9 81.9
15. UNIT AVAILABillh FACTOR 100.0 90.9 81.9
16. UNIT CAPACITY FACTOR (USING MDC) 94.2 85.4 73.4
17. UNIT CAPACITY FACTOR (USING DESIGN MWel 94.2 85.4 73.4 j
18. UNIT FORCED OUTAGE RATE 0.0 9.1 50
19. SHUTDOWNS SCHEDULED DVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

Refueling Outage scheduled to begin October 4,1996 with an estirnated duration of 42 Days.

20. IF SHUTDOWN AT END OF REPORTING PERIDO, ESTIMATED DATE OF STAilTUP:
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED l

COMintRCIAL OPERATION 900813 l l

ESTIMATED l l

Attachment to TXX- 96436 Page 2 of 8 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 50 445 UNIT: CPSES 1 DATE: 8/11/96 COMPLETED BY: MARK SAMUEL l TELEPHONE: 897 5793 MONTH: JULY 1996 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL l OAY (MWe Net) DAY (MWe Net) i i

1 1106 17 1085 2 1069 18 1087 3 1066 19 1087 4 1085 20 1086 l

5 1069 21 1086 6 1027 22 1086 i

7 1084 23 1084 8 1084 24 1085 l 9 1083 25 1085 I 10 1083 26 1085 11 1086 27 1086 12 1085 28 1084 13 1085 29 1084 14 1085 30 1084 15 1086 31 1084 16 1085

Attachment to TXX- 96436 Page 3 of 8

SUMMARY

OF OPERATING EXPERIENCE FOR THE MONTH DOCKET NO.: 50 445 UNIT: CPSES 1 DATE: 8/11/96 COMPLETED BY: MARK SAMUEL.

TELEPHONE: 897 5793 MONTH: JULY 1996 DAY TIME REMARKlMODE 07/01 0000 UNIT BEGAN THE MONTH AT 100% POWER.

07/31 2400 UNIT ENDED THE MONTH AT 100% POWER.

l 1

1

,c-- .,

Attachment to TXX- 96436 '

Page 4 of 8 UNIT SHUTDOWNS AND POWER REDUCTIONS .

'I DOCKET NO.: 50-445 UNIT: CPSES 1 DATE: 8/11/96 COMPLETED BY: Mark Samuel TELEPHONE: 817-897-5793 REPORT MONTH: JULY 1996 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONSICOMMENTS NONE

1) REASON 2) METHOD A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION 1: MANUAL B: MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4: OTHER (EXPLAIN) 1

Attachment to TXX- 96436 Page ' 5. of 8 i ,

COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 j NRC MONTHLY OPERATING REPORT I

DOCKET NO.: 50-446

] UNIT: CPSES 2 1 DATE: 8/11/09 COMPLETED BY: MARK SAMUEL

TELEPHONE
897 5793 OPERATING STATUS i ' JULY 1996
1. REPORTING PERIOD: GROSS HOURSIN REPORTING PER00: 744
  • l
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWs Net): 1150 l DESIGN ELECTRICAL RATING (MWe Net)- 1150
3. POWER LEVEL TO WH:CH RESTRICTED IIF ANY)(MWe Net): NONE
4. REASON FOR RESTRICTION OF ANY):

l THIS MONTH YR TO DATE CUMULATIVE l

i 5. NUMBER OF HOURS REACTOR WAS CRITICAL 744 3,346 20,890 i

6. REACTOR RESERVE SHUTDOWN HOURS 0 0 2,229 i 7. HOURS GENERATOR ON LINE 744 3,335 20,657
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2,530,637 10,856,779 66,419,690 J 10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 851,070 3,663,117 22,367,738 l
11. NET ELECTRICAL ENERGY GENERATED (MWH) 817,644 3,508,439 21,366,797 I 12. REACTOR SERVICE FACTOR 100.0 65.5 79.6 i
13. REACTOR AVAILABILITY FACTOR 100.0 65.5 88.1
14. UNIT SERVICE FACTOR 100.0 65.3 78.7
15. UNIT AVAILABillTY FACTOR 100.0 65.3 78.7
16. UNIT CAPACITY FACTOR (USING MDC) 95.6 59.7 70.8
17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 95.6 59.7 70.8
18. tlNIT FORCED OUTAGE RATE 0.0 13.0 8.3
19. SHUT 00WNS SCHEDULED DVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

NONE

20. IF SHUTOOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED COMMERCIAL OPERATION 930803 ESTIMATED

4 .

i i

Attachment to TXX- 96436 j

, Page 6 of 8 l I

AVERAGE DAILY UNIT POWER LEVEL 1

g DOCKET NO.: 50 446 I

! UNIT: CPSES 2

, DATE: 8/Ill96

! COMPLETED BY: MARK SAMUEL l TELEPHONE: 897 5793 MONTH: JULY 1996 i

AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe Net) DAY (MWe Net) 1 1103 17 1101 2 1102 18 1102 3 1101 19 1097 i l

4 1101 20 1033 5 1101 21 1103 6 1100 22 1103 7 1100 23 1102 8 1100 24 1103 9 1099 25 1102 10 1100 26 1102 11 1102 27 1103 12 1102 28 1103 13 1102 29 1102 14 1102 30 1101 15 1102 31 1101 16 1095

i

)

Attachment to TXX- 96436 Page 7 of 8

SUMMARY

OF OPERATING EXPERIENCE FOR THE MONTH DOCKET NO.: 50 446 UNIT: CPSES 2 DATE: 8/11/96 COMPLETED BY: MARK SAMUEL TELEPHONE: 897 5793 l MONTH: JULY 1996 DAY TIME REMARKIMODE 07/01 0000 UNIT BEGAN THE MONTH AT 100% POWER.

07131 2400 UNIT ENDED THE MONTH AT 100% POWER.  !

l l

I l

I i

1 i

-:=___

~

I' Attachment to TXX- 96436 Page 8 of 8 ',

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50446 UNIT: CPSES 2 DATE- 8/11/96 COMPLETED BY: Mark Samuel TELEPHONE: 817-897-5793 REPORT MONTH: JULY 1996 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS NONE