MONTHYEARML20217G4151999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2 TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Cpses.With ML20210U4081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2 ML20209G0801999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Cpses,Units 1 & 2 ML20195G5141999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Comanche Peak Steam Electric Station,Units 1 & 2.With ML20196L2241999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Cpses,Units 1 & 2 ML20205N3101999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Cpses,Units 1 & 2 ML20205N1481999-02-28028 February 1999 Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2 ML20204H6371999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Comanche Peak Units 1 & 2 ML20199E9961998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Cpses,Units 1 & 2 ML20197K2371998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Cpses,Units 1 & 2 ML20195F3161998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Cpses,Units 1 & 2 ML20154M8841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Cpses,Units 1 & 2 ML20151W0361998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Cpses,Units 1 & 2. with ML20237C6721998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Cpses,Units 1 & 2 ML20236R0711998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Cpses,Units 1 & 2 ML20249B2581998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Cpses,Units 1 & 2 ML20247G3241998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Cpses,Units 1 & 2 ML20216J3061998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Cpses,Units 1 & 2 ML20216J1861998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Comanche Peak Steam Electric Station ML20202H0431998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Cpses,Units 1 & 2 ML20198N7141997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Cpses,Units 1 & 2 ML20197J0941997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for CPSES Units 1 & 2 ML20199D2261997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Cpses,Units 1 & 2 TXX-9721, Monthly Operating Repts for Sept 1997 for Comanche Peak Steam Electric Station1997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Comanche Peak Steam Electric Station ML20212C4851997-08-31031 August 1997 Revised Monthly Operating Rept for Aug 1997 for CPSES Unit 2 ML20210V2101997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for CPSES ML20141J3911997-07-31031 July 1997 Monthly Operating Repts for July 1997 for CPSES ML20149E2991997-06-30030 June 1997 Monthly Operating Repts for June 1997 for CPSES TXX-9713, Monthly Operating Repts for May 1997 for CPSES1997-05-31031 May 1997 Monthly Operating Repts for May 1997 for CPSES TXX-9710, Monthly Operating Repts for Apr 1997 for Comanche Peak Steam Electric Station1997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Comanche Peak Steam Electric Station TXX-9708, Monthly Operating Repts for Mar 1997 for CPSES Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for CPSES Units 1 & 2 ML20137B9781997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for CPSES Units 1 & 2 ML20134Q2521997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20137B9901997-01-31031 January 1997 Revised MOR for Jan 1997 CPSES Unit 2 ML20133M1971996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Comanche Peak Steam Electric Station Units 1 & 2 ML20132C1631996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Comanche Peak Steam Electric Station TXX-9650, Monthly Operating Repts for Oct 1996 for Comanche Peak Steam Electric Station1996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Comanche Peak Steam Electric Station ML20129F1601996-09-30030 September 1996 Revised Monthly Operating Repts for Sept 1996 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20129B2401996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Comanche Peak Steam Electric Station ML20117N5201996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Comanche Peak Steam Electric Station ML20116N6651996-07-31031 July 1996 Monthly Operating Rept for July 1996 for Comanche Peak Unit 1 & 2 TXX-9640, Monthly Operating Rept for June 1996 for Comanche Peak Electric Station1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Comanche Peak Electric Station TXX-9638, Monthly Operating Repts for May 1996 for Comanche Peak Steam Electric Station Units 1 & 21996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Comanche Peak Steam Electric Station Units 1 & 2 ML20112A1951996-04-30030 April 1996 Monthly Operating Repts for April 1996 for CPSES TXX-9610, Monthly Operating Repts for March 1996 for CPSES1996-03-31031 March 1996 Monthly Operating Repts for March 1996 for CPSES ML20101D0461996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Comanche Peak Steam Electric Station Units 1 & 2 TXX-9601, Monthly Operating Repts for Jan 1996 for Comanche Peak Steam Electric Station,Units 1 & 21996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Comanche Peak Steam Electric Station,Units 1 & 2 ML20101D0511996-01-31031 January 1996 Revised Monthly Operating Rept for Jan 1996 for Comanche Peak Steam Electric Station Unit 1 ML20096E7381995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Comanche Peak Steam Electric Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217E8021999-10-0707 October 1999 CPSES Unit 1 Cycle 8 Colr ML20217G4151999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Cpses,Units 1 & 2 ML20212F7671999-09-24024 September 1999 SER Granting Relief Request C-4 Pursuant to 10CFR50.55a(g)(6)(i) for Unit 2,during First 10-year ISI Interval & Relief Requests B-15,B-16 & B-17 Pursuant to 10CFR50.55a(g)(6)(i) ML20216J5701999-09-16016 September 1999 Rev 2 to CPSES Unit 2 Cycle 5 Colr TXX-9920, Monthly Operating Repts for Aug 1999 for Cpses.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Cpses.With ML20211M2981999-08-0606 August 1999 Rev 1 to CPSES Fuel Storage Licensing Rept, CPSES Credit for Soluble Boron & Expansion of Spent Fuel Storage Capacity, Consisting of Revised Title Page and 4-1 ML20210U4081999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Cpses,Units 1 & 2 ML20210D8321999-07-23023 July 1999 Safety Evaluation Accepting Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment Insp ML20209H7661999-07-15015 July 1999 Safety Evaluation Accepting GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Comanche Peak Steam Electric Station,Units 1 & 2 ML20209H2721999-07-0909 July 1999 2RF04 Containment ISI Summary Rept First Interval,First Period,First Outage ML20209H2631999-07-0909 July 1999 2RF04 ISI Summary Rept First Interval,Second Period,Second Outage ML20209G7501999-07-0808 July 1999 SER Finding That Licensee Individual Plant Exam of External Events Complete with Regard to Info Requested by Suppl 4 to GL 88-20 & That IPEEE Results Reasonable Given Design, Operation & History of Comanche Peak Steam Electric Station ML20196L0191999-07-0808 July 1999 Safety Evaluation Granting Request Relief B-6 (Rev 2),B-7 (Rev2),B-12,B-13,B-14 & C-9,pursuant to 10CFR50.55a(g)(6)(i).Technical Ltr Rept Also Encl ML20210J9391999-06-30030 June 1999 CPSES Commitment Matl Change Evaluation Rept 0003,for 970802-990630 ML20209G0801999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Cpses,Units 1 & 2 ML20196J0621999-06-29029 June 1999 Safety Evaluation Supporting Proposed Changes to Emergency Plan Re Licenses NPF-87 & NPF-89 Respectively ML20195G5141999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Comanche Peak Steam Electric Station,Units 1 & 2.With ML20216E0711999-05-21021 May 1999 1999 Graded Exercise - Comanche Peak Steam Electric Station ML20206Q0091999-05-14014 May 1999 Safety Evaluation Accepting GL 92-08, Thermo-Lag 330-1 Fire Barriers, Dtd 921217,for Comanche Peak Electric Station,Unit 1 ML20206H2061999-05-0606 May 1999 SER Accepting Exemption to App K Re Leading Edge Flowmeter for Plant,Units 1 & 2 ML20196L2241999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Cpses,Units 1 & 2 ML20205R5701999-04-14014 April 1999 Rev 6 to ER-ME-067, TU Electric Engineering Rept,Evaluation of Thermo-Lag Fire Barrier Sys ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20205J7831999-04-0101 April 1999 Rev 0 to ERX-99-001, CPSES Unit 2 Cycle 5 Colr ML20205N3101999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Cpses,Units 1 & 2 ML20204H6371999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Comanche Peak Units 1 & 2 ML20205N1481999-02-28028 February 1999 Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2 ML20203A4881999-02-0303 February 1999 Safety Evaluation Granting Requests for Relief B-3 - B-6,C-2 & C-3 for Plant,Unit 2 ML20210J9201999-02-0101 February 1999 CPSES 10CFR50.59 Evaluation Summary Rept 0008,for 970802- 990201 ML20202D0101999-01-27027 January 1999 Safety Evaluation Supporting First 10-yr Interval ISI Program Plan Requests for Relief B-9,B-10 & B-11 for CPSES, Unit 1 ML20199E9961998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Cpses,Units 1 & 2 ML20207D6091998-12-31031 December 1998 1998 Annual Operating Rept for Cpses,Units 1 & 2. with ML20197K2371998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Cpses,Units 1 & 2 ML20195F3161998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Cpses,Units 1 & 2 ML20154M8841998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Cpses,Units 1 & 2 ML20154B5741998-09-30030 September 1998 Safety Evaluation Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety- Related Motor-Operated Valves. Licensee Has Established Acceptable Program ML20151W0361998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Cpses,Units 1 & 2. with ML20151Q1211998-08-14014 August 1998 Rev 0 to Control of Hazard Barriers ML20237C4061998-08-14014 August 1998 Safety Evaluation Supporting Request to Implement Risk Informed IST Program ML20237C6721998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Cpses,Units 1 & 2 ML20236V3121998-07-29029 July 1998 Final Part 21 Rept Re Enterprise DSR-4 & DSRV-4 Edgs.Short Term Instability Was Found During post-installation Testing & Setup as Part of Design mod/post-work Testing Process. Different Methods Were Developed to Correct Problem ML20236R0711998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Cpses,Units 1 & 2 ML20249B2581998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Cpses,Units 1 & 2 ML20248A1671998-05-22022 May 1998 Interim Part 21 Re Enterprise DSR-4 & DSRV-4 Emergency diesel.Post-installation Testing Revealed,High Em/Rfi Levels Affected New Controllers,Whereas Original Controllers Were unaffected.Follow-up Will Be Provided No Later than 980731 ML20247G3241998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Cpses,Units 1 & 2 ML20216B8661998-04-0101 April 1998 Rev 0 to ERX-98-001, CPSES Unit 1 Cycle 7 Colr ML20216J3061998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Cpses,Units 1 & 2 ML20216J1861998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Comanche Peak Steam Electric Station ML20197A6951998-02-24024 February 1998 Inservice Insp Summary Rept,First Interval,Second Period, First Outage ML20199J5391998-02-0202 February 1998 CPSES Commitment Matl Change Evaluation Rept 0002 for 960202-970801 1999-09-30
[Table view] |
Text
' Attachment to TXX-98224-Page 1 of 8 I COMANCHE' PEAK STEAM ELECTRIC STATION, UNIT 1
-NRC HONTHLY OPERATING REPORT
, . i y DOCKET N0.. 50 445 L UNIT: CPSES 1 l .DATE: 10/ 8/98 COMPLETED BY: Bob Reible- l J
I-- TELEPHONE: 254-897-0449 l 1 l OPERAIINGSTATUS- I l ', REPORTING PERIOD: SEPTEMBER 1998 GROSS HOURS IN REPORTING PERIOD: 720
- 2.- CURRENTLY AUTHOR'IZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWe-Net): 1150
- i l ' DESIGN ELECTRICAL RATING (MWe-Net): 1150
' 3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): NONE
'4. REASON FOR RESTRICTION (IF ANY):
, THIS MONTH YR TO DATE CUMULATIVE
- 5. NUMBER OF HOURS REACTOR WAS CRITICAL 720 5,665 60,426
- 6. ' REACTOR RESERVE SHUTDOWN HOURS 0 0 2,632
~ 7. HOURS GENERATOR ON LINE 720 5.640 59,750
- .8 . UNIT RESERVE SHUTDOWN HOURS 0 0 0
' 9. GROSS THERMAL ENERGY GENEPATED (MWH) 2,451,499 18.942.034 195,721,818
': 10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 813.403 6,346,821 65,418.781
- 11. NET ELECTRICAL ENERGY-GENERATED (MWH) 779,551 6.073,938 62.476,250
- 12. REACTOR SERVICE FACTOR 100.0 86,5 84.8
.13. REACTOR AVAILABILITY FACTOR- 100.0 86.5 88.4
-14 c JUNIT SERVICE FACTOR: 100.0 86.1 83.8
- 15. 1 UNIT AVAILABILITY FACTOR. 100.0 86.1 83.8 g :16. , UNIT CAPACITY FACTOR (USING MDC)- 94.1 80.6 76.2
- 17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 94.1 80.6 76.2 i18.' UNIT FORCED OUTAGE RATE 0.0 0.0 3.8 119. -SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS-(TYPE, DATE, AND DURATION OF EACH):
~
L 20. -IF SHUTDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
L
, 21. UNITS IN TEST-STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED L
COMMERCIAL OPERATION 900813
- ESTIMATED-9910210070 981012 PDR ADOCK 05000445 is R
PDR y
.s. . -. -. . --
Attachment to TXX-98224
[ Page 2 of 8
~
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-445 UNIT: CPSES 1 DATE: 10/ 8/98 COMPLETED BY: Bob Reible TELEPHONE: 254 897-0449 MONTH: SEPTEMBER 1998 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL
-DAY (MWe-Net) DAY (MWe-Net) 1 1081 17 1088 2 1080 18 1089 3 1080 19 1088 4 1080 20 1087 5 1080 21 1787 6 1080 22 1086 7 1080 23 1086 l
8 1080 24 1087 9 1079 25 1087 l
10 1079 26 1087 11 1072 27 1086 12 1052 28 1085 13 1088 29 1083 14 1088 30 1083 15 ' 1087 31
. 1089 l
l i
i i
! Attachment to TXX-98224 i - Page 3 of 8 L.
SUMMARY
OF OPERATING EXPERIENCE FOR THE MONTH
, . DOCKET NO.: 50-445 UNIT: CPSES 1 DATE: 10/ 8/98 i '
COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 MONTH: SEPTEMBER 1998 DAY TIME REMARK / MODE
- l. 09/01 0000 Unit began the month at 100% power.
09/30 2400 Unit ended the month at 100% power.
l i
i I
4 I
l l
4
Attachment-to TXX-98224 .
. Page .4 of 8 -
UNIT SHUTDOWNS ANO POWER REDUCTIONS DOCKET NO.: 50-445 .
UNIT: CPSES 1 DATE: 10/ 8/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 REPORT MONTH: SEPTEMBER 1998 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS None None
- 1) REASON 2) METHOD A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION 1: MANUAL B: MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: 0THER (EXPLAIN) 4: OTHER (EXPLAIN) 4
+
l Attachment to TXX-98224 Page 5 of 8 l
- COMANCHE PEAK STEAM ELECTRIC STATION, UNIT 2 NRC MONTHLY OPERATING REPORT
[
? ,
DOCKET NO.. 50-446 UNIT: CPSES 2 DATE: 10/ 8/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 l
OPERATING STATUS 1
- 1. REPORTING PERIOD: SEPTEMBER 1998 GROSS HOURS IN REPORTING PERIOD: 720 1
- 2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 1150
- MAX. DEPEND. CAPACITY (MWe-Net):
DESIGN ELECTRICAL RATING (MWe-Net): 1150
- 3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): NONE
- 4. REASON FOR RESTRICTION (IF ANY):
THIS MONTH YR TO DATE CUMULATIVE
- 5. NUMBER OF HOURS REACTOR WAS CRITICAL 720 6.536 38.640
- 6. REACTOR RESERVE SHUTDOWN HOURS 0 15 2,326 l
- 7. HOURS GENERATOR ON LINE 720 6.532 38,321
- 8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
- 9. GROSS THERMAL ENERGY GENERATED (MWH) 2.281,630 21.242,002 124,347.887
- 10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 760,736 7,172,442 41,973.754
- 11. NET ELECTRICAL ENERGY GENERATED (MWH) 728,788 6,884.344 40,175,125
- 12. REACTOR SERVICE FACTOR 100.0 99.8 85.4
- 13. REACTOR AVAILABILITY FACTOR 100.0 100.0 90.6
- 14. UNIT SERVICE FACTOR 100.0 99.7 84.7
- 15. UNIT AVAILABILITY FACTOR 100.0 99.7 84.7
- 16. UNIT CAPACITY FACTOR (USING MDC) 88.0 91.4 77.2 17; 'UNITCAPACITYFACTOR(OSINGDESIGNMWe) 88.0 91.4 77.2
-18. UNIT FORCED OUTAGE RATE 0.0 0.3 4.9
- 19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE DATE. AND DURATION OF EACH):
l
- 20. IF SHUTDOWN AT END OF REPORTING PERIOD. ESTIMATED DATE OF STARTUP:
- 21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED COMMERCIAL OPERATION 930803 ESTIMATED
, - Attachment to TXX-98224 Page 6 of 8 AVERAGE DAILY UNIT POWER LEVEL
, DOCKET NO.: 50-446 UNIT: CPSES 2 DATE: 10/ 8/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 MONTH: SEPTEMBER 1998 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-Net) DAY (MWe-Net) l
.1 857 17 -1104 2- 858 18 1104 3 858 19 1101 L
4 858 20 1104 5 858 21 1100 l 6 857 22 1102 7 856 23 1102 8 859 24 1102 9 859 25 1102 10 858 26 1102 11 863 27 1101 12 1084 28 1102 13 1105 29 1099 14 1104 30 1099 15 1103 31 16 1104 L
I
. . .. . .-- . .. .... -.=. - -.. - - - . - . .- . _ . - . . - . . . .
Attachment to TXX-98224 l I
Page ,7 of 8
SUMMARY
OF OPERATING EXPERIENCE FOR THE MONTH DOCKET NO.. 50 446 I UNIT: CPSES 2 l DATE: 10/ 8/98 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 i
-MONTH: SEPTEMBER 1998 DAY TIME REMARK / MODE 09/01 0000 Unit began the month at 81% Reactor power as a planned derate to ensure the turbine vibration level did not exceed established limits.
09/11 2100 Unit at 81% power. Commenced ramp to 100% power after planned derate i to ensure the turbine vibration level did not exceed established l limits. )
09/12 0515 Unit completed ramp to 100% power.
09/30 2400 Unit ended the month at 100% power.
1 h
i
Attachment to TXX-98224
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-446 UNIT: CPSES 2 DATE: 10/ 8/98 -
COMPLETED BY: Bob Reible
. TELEPHONE: 254-897-0449 REPORT MONTH: SEPTEMBER 1998 METHOD OF TYPE SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO DATE S: SCHEDULED (HOURS) REASON REDUCING POWER CORRECTIVE ACTIONS / COMMENTS 4b 980901 S H 4 On 07/16 at 0000, unit power was reduced to 81%
power to ensure the turbine blade vibration; did not exceed established limits. This planr.ed ,
reduction was a conservative response to expected '
high summer temperatures. Ur.it began to ramp to 100% power on 09/11 at 2100. The Unit was returned to 100% power on 09/12 at 0515.
- 1) REASON 2) METHOD A: EQUIPMENT FAILURE (EXPLAIN) E: OPERATOR TRAINING AND LICENSE EXAMINATION 1: MANUAL B: MAINT OR TEST F: ADMINISTRATIVE 2: MANUAL SCRAM C: REFUELING G: OPERATIONAL ERROR (EXPLAIN) 3: AUTOMATIC SCRAM D: REGULATORY RESTRICTION H: OTHER (EXPLAIN) 4: OTHER (EXPLAIN) l