Corrected Monthly Operating Rept for Feb 1999 for CPSES, Units 1 & 2
ML20205N148
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/28/1999
From: Reible B
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20205N130 List:
References
NUDOCS 9904160163
Download: ML20205N148 (1)


Text

Attachment to TXX-99093

-Page '15f 1 (Replacement for page 5 of 8 for TXX-99066)

COMANCHE PEAK STEAM ELECTRIC STATION, UNIT NRC MONTHLY OPERATING REPORT DOCKET NO.: 50-445 ,

UNIT: CPSES 2 DATE: 2/8/99 COMPLETED BY: Bob Reible TELEPHONE: 254-897-0449 OPERATING STATUS

1. REPORTING PERIOD: FEBRUARY 1999 GROSS HOURS IN REPORTING PERIOD: 672
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3411 MAX. DEPEND. CAPACITY (MWe-Net): 1150
  • DESIGN ELECTRICAL RATING (MWe-Net): 1150 1
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY)(MWe-Net): NONE
4. REASON FOR RESTRICTION (IF ANY):

THIS MONTH YR TO DATE CUMULATIVE l

5. NUMBER OF HOURS REACTOR WAS CRITICAL 672 1,376 42,225 l
6. REACTOR RESERVE SHUTDOWN HOURS 0 40 2,366
7. HOURS GENERATOR ON LINE 672 f,364 41,893
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2.285,275 4,597,310 136,464,323
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 778,725 1,564,305 46,099,038
11. NET ELECTRICAL ENERGY GENERATED (MWH) 749,277 1,502,517 44,138,594 l
12. REACTOR SERVICE FACTOR 100.0 97.2 86.4
13. REACTOR AVAILABILITY FACTOR 100.0 100.0 91.3
14. UNIT SERVICE FACTOR 100.0 96.3 85.7 l
15. UNIT AVAILABILITY FACTOR 100.0 96.3 85.7 l
16. UNIT CAPACITY FACTOR (USING MDC) 97.0 92.3 78.6
17. UNIT CAPACITY FACTOR (USING DESIGN MWe) 97.0 92.3 78.6
18. UNIT FORCED OUTAGE RATE 0.0 3.7 4.6
19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
20. IF SHUTDOWN AT END OF REPORTING PERIOD, ESTIMATED DATE OF STARTUP:
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): ACHIEVED COMMERCIAL OPERATION 930803 ESTIMATED 9904160163 990412 PDR ADOCK 05000445 R PDR