Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/97-01, 50-412/97-01,50-334/97-02 & 50-412/97-02 on 970703ML20210R834 |
Person / Time |
---|
Site: |
Beaver Valley |
---|
Issue date: |
08/27/1997 |
---|
From: |
Eselgroth P NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
---|
To: |
Cross J DUQUESNE LIGHT CO. |
---|
References |
---|
50-334-97-01, 50-334-97-02, 50-334-97-1, 50-334-97-2, 50-412-97-01, 50-412-97-02, 50-412-97-1, 50-412-97-2, NUDOCS 9709030424 |
Download: ML20210R834 (2) |
|
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective ML20207G2611999-06-0707 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart IR 05000412/19980091999-05-26026 May 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-412/98-09 ML20195C4461999-05-21021 May 1999 Forwards Insp Repts 50-334/99-02 & 50-412/99-02 on 990321-0501.No Violations Were Identified.Licensee Conduct of Activities at Beaver Valley Power Station Characterized by Safe Conduct of Activities During Refueling Outage ML20206P1241999-05-14014 May 1999 Refers to Proposed Changes Submitted by Dl on 990316 to BVPS QA Program Described in BVPS-2 Ufsar,Chapter 17.2.Forwards RAI Re Proposed QA Program Changes ML20206N3161999-05-0606 May 1999 Responds to Ltr to NRC on Continued Events Re Transfer of Generation Assets Between Dl & Firstenergy.Info Will Be Considered as NRC Monitor Pending License Transfer Application of Bvps,Units 1 & 2 & Pnpp ML20206H7931999-04-30030 April 1999 Ack Receipt of 990426 Request for Enforcement Discretion & 990427 Withdrawal of Request for Enforcement Discretion. Resolution Documented.Enforcement Discretion Not Necessary ML20206B2751999-04-22022 April 1999 Forwards Insp Repts 50-334/99-01 & 50-412/99-01 on 990207- 0320.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206A8381999-04-20020 April 1999 Forwards Reactor Operator Initial Exam Rept 50-412/99-301 on 990322-25.All Three Reactor Operator Applicants Passed. Initial Written Exam Submittal Was Determined Not to Meet NRC Guidelines in Certain Instances ML20205R9071999-04-20020 April 1999 Forwards Second Request for Addl Info Re Response to GL 95-07, Pressure-Locking & Thermal-Binding of Safety-Related Power-Operated Gate Valves, for Beaver Valley Power Station,Units 1 & 2 ML20205Q8311999-04-14014 April 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-11 & 50-412/98-11 Issued on 990225.Actions Will Be Examined During Future Insp of Licensed Program ML20205L0341999-04-0909 April 1999 Forwards SER Accepting Util 971209 & 980729 Submittal of Second 10-year Interval ISI Program Plan & Associated Relief Requests for Beaver Valley Power Station,Unit 2.TER Also Encl ML20205P2431999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Ltr Provided to Minimize Resource Impact on Staff & to Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival ML20205K0901999-04-0505 April 1999 Informs of Individual Exam Result on Initial Retake Exam Conducted on 990322-25 at Licensee Facility.Three Individuals Were Administered Exam & All Three Passed. Forwards Encl Re Exam.Without Encl ML20205R1791999-03-30030 March 1999 Responds to Issue Re Generic Implication of part-length Control Rod Drive Mechanism Housing Leak at Praire Island, Unit 2 & Beaver Valley Power Station,Units 1 & 2 ML20205C0301999-03-26026 March 1999 Informs That Util Responses to GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps Acceptable ML20204D7371999-03-16016 March 1999 Advises That RW Lindsey Authorized to Administer Initial Written Exams to Sh Cencic,Tf Lardin & Ta Pittas on 990322. Region I Operator Licensing Staff Will Administer Operating Tests ML20207E0201999-02-25025 February 1999 Forwards Insp Repts 50-334/98-11 & 50-412/98-11 on 981227- 990206 & Forwards Notice of Violations Re Uncontrolled Reduction of Main Condenser Vacuum ML20203D0691999-02-10010 February 1999 Forwards SE Accepting Approval of Proposed Revs to Plant QA Program Description in Chapter 17.2 of Updated Fsar,Per Util 981224 Submittal ML20206U3011999-02-0505 February 1999 Forwards Insp Repts 50-334/98-09 & 50-412/98-09 on 981116-1217 & Nov.Violation Identified Re Inadequate Design Control in Unit 2 Dc Voltage Drop Calculation ML20203A0811999-02-0404 February 1999 Forwards Request for Addl Info Re Review of Beaver Valley Power Station,Unit 1 License Amend to Allow one-time Extension of Steam Generator Insp Interval ML20199E6681999-01-14014 January 1999 Forwards RAI Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Plant,Units 1 & 2 ML20199F1961999-01-13013 January 1999 Forwards Insp Repts 50-334/98-10 & 50-412/98-10 on 981115-1226.No Violations Noted.Informs That Overall Fire Protection Program Functioning Well ML20199F5101998-12-29029 December 1998 Discusses Third 10-year Interval ISI Program Plan & Associated Relief Requests for BVPS-1 Submitted by Dlc on 970917 & 980618.Informs That NRC Has Adopted Ineel Recommendations in TER INEEL-98-00893.Forwards SE & TER ML20198K5911998-12-24024 December 1998 Forwards Emergency Response Data Sys Implementation Documents Which Include Data Point Library Updates for Fermi (Number 268),Peach Bottom (Number 269) & Beaver Valley (Number 270).Without Encls ML20198K8251998-12-21021 December 1998 Forwards SER Granting Licensee 980611,as Suppl 981015 Pump Relief Request PRR-5 for Third 10-year IST Interval for Beaver Valley Power Station,Unit 1 Pursuant 10CFR50.55(a)(f)(6)(i) ML20198B1301998-12-0909 December 1998 Advises of Planned Insp Effort Resulting from Beaver Valley Power Station mid-year Insp Resource Planning Meeting Held on 981110.Historical Listing of Plant Issues & Details of Insp Plan for Next 6 Months Encl ML20198A1301998-12-0909 December 1998 Forwards SE Re USI A-46 Program Implentation for Plant Unit 1.Staff Concludes Program Implementation Met Purpose & Intent of Criteria in Generic Implementation Procedure 2 & Suppl SER 2 for Resolution of USI A-46 ML20196J2761998-12-0404 December 1998 Forwards Corrected Pages 17 & 18 of NRC Integrated Insp Repts 50-334/98-06 & 50-412/98-06 for Exercise of Enforcement Discretion ML20196H3051998-12-0202 December 1998 Forwards Insp Repts 50-334/98-06 & 50-412/98-06 on 981004-1114.No Violations Noted.Conduct of Activities at Beaver Valley Power Station Facilities Characterized by Safe Plant Operations ML20196H2781998-12-0202 December 1998 Forwards Insp Repts 50-334/98-08 & 50-412/98-08 on 981026- 30.No Violations Noted.Plant Operations Witnessed by Team Were Conducted in Safe & Controlled Manner ML20196G9921998-12-0101 December 1998 Forwards Ltrs from Fk Koob, to JW Pack & CF Wynne Re Plant Deficiencies Assessed During 981006 Exercise Against Hancock County,Wv & Beaver County,Pa,Respectively ML20196D4371998-11-25025 November 1998 Discusses Concerns Re Announced Asset Transfer Between Firstenergy Corp & Duquesne Light Co ML20196A7101998-11-24024 November 1998 Forwards Notice of Withdrawal of Amend to License NPF-73. Proposed Change Would Have Extended on one-time Only Basis, Surveillance Interval for TSs 4.8.1.1.1.b & 4.8.1.2 Until First Entry Into Mode 4 Following Seventh Refueling Outage ML20195K3331998-11-18018 November 1998 Informs That Effective 981214,DS Collins Will Become Project Manager for Beaver Valley Power Station,Units 1 & 2 IR 05000334/19980041998-11-13013 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-04 & 50-412/98-04 Issued on 980915.C/As Will Be Examined During Future Insp of Licensed Program ML20195J2941998-11-12012 November 1998 Forwards Safety Evaluation Re First & Second 10-year Interval Inservice Insp Request for Relief ML20155K4041998-11-0505 November 1998 Forwards Insp Repts 50-334/98-07 & 50-412/98-07 on 981006- 07.No Violations Noted.Overall Performance of Emergency Response Organization Was Good 1999-09-08
[Table view] |
Text
.
.
August 27, 1997 Mr. J. President Generation Group Duquesne Light Company Post Office Box 4 Shippingport, Pennsylvania 15077 '
SUBJECT: INSPECTION REPORT NOS, 50 334;412/97 0102 REPLY
Dear Mr. Cross:
This letter refois to your August 1,1997, correspondence, in response to our July 3,1997, letter.
Thank you forinforming us of the corrective and preventive actions documented in your im sr.
These actions will be examined during a future inspection of your licensed program.
Your cooperation with us is appreciated.
Sincerely,
.
.
Peter W. Eselgroth, Chief Project Branch No. 7
.
Division of Reactor Projects Docket Nos. 50 334; 50-412 cc:
Sushil C. Jain, Vice President, Nuclear Services-R. LeGrand, Division Vice President, Nuclear Operations Group & Plant Manager W. Kline, Manager, Nuclear Engineering Department B. Tulte, General Manager,-Nuclear Operations Unit K. L. Ostrowski, Manager, Quality Services Unit J.- Arias, Director, Safety & Licensing Department
-_ M. Clancy, Mayor !
'
(hf
,
Commonwealth of Pennsylvania State of Ohio > l 9709030424 970827 gDR ADOCK050003]4 lllll]lllll
__
- _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ - _ _ _ - _ - _ _ _ _
,
.
! J. Distribution:
l Region l Docket Room (with concurrences)
l PUBLIC
'
Nuclear Safety Information Center (NSIC)
NRC Resident inspector W. Axelson, DRA P. Eselgroth, DRP
' D. Haverkamp, DRP A. Keatley, DRP J. Stofr, PDI 2, NRR-D. Brinkman, PM, PDI 2, NRR W. Dean, OEDO R. Correia, NRR F. Talbot, NRR DOCDESK Inspection Program Branch, NRR (IPAS)
i DOCUMENT NAME: G:\ BRANCH 7\BV\970102.RL-n . , .e w. .u . we.. m m. w. c . copy wiinout .it. cam.nii.ncio.u,. : . co , . in .ti..s nti.ncio.u,, =.N..,
OFFICE Rl/DR1, I Rl/ORP 2 ,) / I I(
NAME KERTE/2.-- ESELGR P DATE 08/27/97 08/ 27/97 08/ /97 08/ /97 08/ /97 0FFICIAL RECORD COPY
. _ _ _ _ _ ._ . _ .
'i- -
-
. . . - .. _ . . . . .
.. .
_, _ ., .
. . .
-__ - _ - - - _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
'*' Be vet Va liy Po*+t $tahon
$Nppmpport. P A 16077 0004 HONALD L LeGRAND Hit) 393 7622 u ** erst o e a d Plant Manage'
Auguet !, 1997 1.-97-001 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 0001 Subject: Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50 334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Reply to Notice of Violation EA 97-255 In response to NRC correspondence dated July 3,1997, and in accordance with 10 CFR 2.201, the attached reply addresses the Notice of Violation transmitted with the letter.
The cited events were discussed in NRC Inspection Report Nos. 50-334/97-01, 50-412/97-01 and 50-334/97-02, 50-412/97-02 and also during a Predecisional Enforcement Conference held on June 13,1997.
Please note that some of the compledon dates for the programmatic enhancements to the Technical Specification surveillance program have been revised from the dates discussed in the Predecisional Enforcement Conference to reflect changes in work scope.
The specific revisions are identified in the body of the response. These changes also supersede the applicable dates provided in Licensee Event Repoits (LER) 50 334/97-011-00 (Corrective Action No. 2), LER 50-334/97-013-00 (Corrective Action No. 6),
LER $0-334/97-014-00 (Corrective Action No. 5), and LER 50-412/97 003-00 (Corrective Action No. 5).
If there are any questions concerning this response, please contact Mr. J. Arias, Director, Safety & Licensing at (412) 393 5203.
Sincerely, q/70 g, -
.
kd Ronald L. LeGrand x '
c: ir. D. M. Kem, Sr. Resident inspector D.filyt RING Mr. H. J. Miller, NRC Region I Administrator 0UAiiIY Mr. D, S. Brinkman, Sr. Project Manager EN[RGV
.
, , , . _ . . . _ . _ - - - . -
_ - - - - - _ _ - - _ .- _ . _ _ _
,
.. .
AFFIDAVIT COMMONWEALTH OF PENNSYLVANIA)
) SS:
COUNTY OF BEAVER )
Subject: Beaver Valley Power Station, Unit No. I and No. 2 BV 1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, Lleense No. NPF-73 Reply to Notlee of Violation EA 97-255 ,
Before me, the undersigned notary public, in and for the County and
,
Commonwealth aforesaid, this day personally appeared Ronald L. LeGrand, to me known, who being duly sworn according to law, deposes and says that he is Division Vice President, Nuclear Operations and Plant Manager of the Nuclear Power Disision, Duquesne Light Company, he is duly authorized to execute and file the foregoing submittal on behalf of said Company, and the statements set forth in the submittal are true and correct to the best of his knowledge, infonnation and belief.
,
d' '% (?
-
Ronald L. LeGrand Subscribed and sworn to before me on this/I/ day of R,f/
f /9f/ .
Ide. 701 9dt/n Y
'/ Notary Public E
,yj,"{,syP
g _
g,spggon
, . = , .e,,,,,, . set
- 26.
= - -
. - -
. . .
.. . . . .
.. . . . . . . . .
.
. _ . _ _
_ __ _ _ _ _ _ _ _ _ _ _
., .
'
'
DUQUESNE LIGilT COMPANY l .
Nuclear Power Dh'ision i
Beaver Valley Power Station, Unit Nos. I and 2 Reply to Notice of Violation Letter dated July 3.1997 VIOLATION (Severity Level lilt Supplement I)
EA 97-255 Unit I and Unit 2 Technical Specification (TS) 4.0.2 require that, each surveillance requirement shall be performed within the specified time interval.
1. Unit 1 TS 4.8.1.1.2.b.5 requires that each diesel generator shall be demonstrated OPERABLE at least once per 18 months during shutdown by verifying the diesel generator operates for greater than or equal to 60 minutes while loaded to greater than or equal to 2750 KW.
Contrary to the above, on April 11,1996, and April 20, 1996, during emergency diesel generator (ECO) surveillance tests, the load test values used were inadequate to ensure that the EDGs achieved 2750 KW due to inaccuracies in the kilowatt meter instrument loop. Specifically, the EDGs had to be tested to at least 2875 KW to account for meter inaccuracies; however, EDO 11 was tested at 2850 KW on April 20,1996, and EDO l 2 was tested at 2800 KW on April 11,1996. These were the only EDG surveillance tests perfonned to meet TS 4.8.1.1.2.b.5 during the 18-month period. (01013)
2. Unit I and Unit 2 TS 4.4.6.3.1 require, in part, that leakage testing of reactor coolant system (RCS) pressure isolation valves (PlVs) listed in Table 4.4. 3 shall be accomplished prior to entering Mode 2 after every time the plant is placed in the COLD SHUTDOWN condition for refueling. Unit 1 TS Table 4.4-3 includes, in part, residual heat removal (RHR) system inlet isolation valves MOV RH-700 and MOV-RH-701. Unit 2 TS Table 4.4-3 includes, in part, RHR system inlet isolation valves 2RHS MOV701 A,2RHS-MOV702A,2RHS-MOV701B, and 2RHS-MOV702B, Contrary to the above, Unit I reactor coolant system (RCS) pressure isolation valves MOV RH-700 and 701 were not leak tested prior to entering Mode 2, after placing the unit in cold shu'Jown on March 23, 1996. Additionally, Unit 2 RCS pres:ure isolation valves 2RHS MOV701 A(B) and 2RHS MOV702A(B) were not leak tested prior to entering Mode 2, after placing the unit in cold shutdown on September 1, 1996.(01023)
_ _ _ i
_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
. . .
' * ,-
l Reply to Nstice cf Vi:lati:n Page 2 l
3. Unit I and Unit 2 TS 4.6.4.2.b.4 require that each hydrogen recombiner system shall be demonstrated OPERABLE at least once per 18 months by verifying the integrity of all heater electrical circuits by performing a continuity and resistance to ground test immediately following the functional test required by TS 4.6.4. 2.b.3.
Contrary to the above, on March 24, 1996, the integrity of Unit I hydrogen recombiner IA and IB heater circuitry was not verified immediately following the functional tests of the recombiners. On September 1,1996, the integrity of Unit 2 hydrogen recombiner 21A and 21B heater circuitry was not verified immediately following the functional tests of the recombiners. (01033)
4. Unit I and Unit 2 TS 4.3.1.1.1 require that each reactor trip system instrumentation channel shall be demonstrated OPERABLE by the performance of the CHANNEL CHECK, CHANNEL CAllBRATION, and CHANNEL FUNCTIONAL TEST operations during the modes and at the frequencies shown in Table 4.3 1.
Unit I and Unit 2 TS 4.3.2.1.1 require that each engineered safety feature actuation system (ESFAS) instrumentation channel shall be demonstrated OPERABLE by the performance of the CHANNEL CHECK, CHANNEL CALIBRATION, and CHANNEL FUNCTIONAL TEST operations during the modes and. at the frequencies shown in Table 4.3-2.
Unit I and Unit 2 TS 4.3.2.1.2 require that the logic for the interlocks shall be demonstrated OPERABLE during the at power CHANNEL FUNCTIONAL TEST of channels affected by interlock operation.
Contrary to the above, prior to March 24,1997, and March 27,1997, respectively, the Unit I and Unit 2 reactor coolant system loop stop valve position block signals were not tested during bimonthly channel functional testing for ESFAS instrumentation, and channel functional testing for reactor trip system instrumentation, in addition, an ESFAS P-4 interlock logic diode in the Unit I and Unit 2 solid state protection system logic circuits was not tested during channel functional testing. These testing omissions resulted in failure to demonstrate the interlock logic and the interlock function operable. (01043)
5. Unit I and Unit 2 TS 4.0.5.a.2 require that inservice testing of ASME Code Class 1, 2, and 3 pumps and valves shall be performed in accordance with Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda as required by 10 CFR 50.55a(f).
Unit 1 TS 4.7.7.2.b.1 requires that the bottled air pressurization system shall be demonstrated OPERABLE at least once per 18 months by verifying that a
_
'
chlorine / control room high radiation / containment phase B isolation test signal-from
__ _ _ ____ _ - _ _____
'
.. .
-
- , Reply to N:tice cf Vi:lati:n Page 3 cither Unit will initiate system operation. Unit 2 TS 4.7.7.1.e.6 requires that the Control Room Emergency Air Cleanup and Pressurization System shall be demonstrated OPERABLE at least once per 18 months by verifying that a chlorine / control room high radiation / containment phase B isolation signal will initiate
- operation of the bottled air pressurization system.
Operating Surveillance Test 1/20ST-44A.ll, " Chlorine Actuation of Control Room-Isolation /CREBAPS Systems," implements the surveillance requirements and requires that the stroke times for the discharge trip valves do not exceed a prescribed ASME limiting stroke time. The test also requires that, if the discharge trip test valves exceed their previously recorded stroke times by greater than 50%, the test frequency will be increased to monthly.
Contrary to the above, CREBAPS discharge trip valves TV VS-101 B, D, and E were not stroke time tested between January 29 and March 22, 1997, following a 50%
stroke time increase measured during performance of I /20ST-44 A.11 on January 28,
-1997.(01053)
6. Unit 1 TS 4.1.2.2.b and Unit 2 TS 4.1.2.1.b require that at least oac of the required boron injection flow paths shall be demonstrated OPERABLE at leist once per 31 days by verifying that each valve (manual, power operated or automatic) in the flow path that is not locked, scaled or otherwise secured in position, is in its correct position.
Contrary to the above, prior to March 25,1997, the monthly boron injection flowpath operability verifications were not satisfactorily completed. Specifically, position verifications for boron injection flowpath valves MOV-lCH-289 and 310 and ICH-83 and 86 on Unit I and 2CHS MOV289 and 310 on Unit 2 (valves which were not locked or secured in position) were not performed. (01063)
These violations are classified in the aggregate as a Severity Level III problem (Supplement I),
Reason for the Violations The root cause of the violations was inadequate management oversight and control of the TS surveillance program. Contributing factors were weaknesses in the procedures, scheduling, coordination and communication processes used for surveillance testing.
.- _
_ _ _ _ - _ _ _
'
.. :.
,i -- Reply to N:tice of Violation -
Page 4 Corrective Actions Taken and Results Achieved ~
li The specific details regarding this violation including corrective actions were provided by Licensee Event Report (LER) 50-334/97-002-00 dated March 19,1997, 2. The specific details regarding this- violation including corrective actions were provided by LER 50-334/97-003-00 dated March 24,1997,
- 3, The - specific- details regarding this violation including corrective actions were
_
provided by LER 50-334/97-004-00 dated March 28,1997,
,
4 The specific details regarding this violation including corrective actions were provided by LER 50-334/97-006-00 dated April 21,1997,
' 5. The specific details regarding this violation including corrective actions were provided by LER 50-334/97-007-00 dated April 21,1997, 6. The specific details regarding this violation including corrective actions were provided by LER 50-334/97-008-00 dated April 22,1997, An assessment of the TS surveillance requirements for Units 1 and 2 was performed by -
the- Quality Services Unit by April 10,1997, .This assessinent reviewed- each TS surveillance requirement to determine if the wording implied that the surveillance was to be performed in a specific scheduling sequence or if it was mandated following a specific plant event. This essessment was reviewed by Opersions, and-procedure changes ~were initiated to incorporate clarifications when necessary.
- Actions Taken to Prevent Recurrence The following programmatic enhancements to the TS surveillance program are being made:
+ v evaluation of the adequacy of surveillance procedures that implement TS will be coCucted to ensure that the procedures implement the required testing. This evaluation and-appropriate procedure revisions will be completed for Units 1 and 2 by Januaiy 30,1998.
- The current processes for revising / preparing TS surveillance procedures will be revised to include a technical review led by the System and Performance Engineering -
Department (SPED) for intent changes. These processes will be revised by August 29,1997, This date has been revised from the July 31,1997 date discussed at
_ .
-
--
- _ - _ _ _ _ - _ _ - _ _ _ _ _ _ _
.',
_ ._
.;, Reply to Notice of Violation Page 5 the Predecisional Enforcement Conference on June 13,1997, due to changes in work scope, e The coordination and scheduling process for TS surveillances will be centralized under the responsibility of the Work Management Manager. Additional resources will be allocated to incorporate the surveillance schedule into the on-line scheduling system. These improvements will be completed by November 30,1997. This date has been revised from the July 31, 1997 date discussed at the Predecisional Enforcement Conference, due to changes in work scope.
A self-assessment of the TS surveillance program will be conducted during the second quarter of 1998. Any significant deficiencies resulting from this self-assessment will be addressed through the Condition Report program.
Date When Full Comoliance Will Be Achieved Full compliance was achieved for each of the six violations discussed above with the completion of the immediate corrective actions for the LERs referenced above.
The procedure revisions that are being made as a result of the Operations review of the QSU assessm:nt will be completed by October 1,1997.
The programmatic enhancements to the TS surveillance program will be completed as follows: >
e The evaluation of the adequacy-of TS surveillance procedures and . appropriate procedure revision will be completed for Units 1 and 2 by January 30,1998.
. The processes for revising / preparing TS surveillance procedures will be revised to include a technical review led by SPED for intent changes by August 29,1997.
. The coordination and scheduling process for TS surveillances will be improved by November 30,1997.
The self assessment of the TS surveillance program will be completed by June 30,1998.
..
.
. . _ _ - - - _ - _ _ - . - . _ . . _ _ _ - - - - .