Advises That Rev 12 to Facility Number 2 Contingency Plan Dtd 920805 Is Consistent W/Provisions of 10CFR50.54(p) & Acceptable
ML20126J860
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 12/30/1992
From: Pate R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
References
NUDOCS 9301060319
Download: ML20126J860 (2)


Text

. - _ _ _ _ _ _ _ - _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ _

(

DEC 3 9 D32 Docket No. 50-397 G. C. Sorensen, Manager of Regulatory Programs Washington Public Power Supply System P. O. Box 968 3000 George Washington Way Richland, Washington 99352 This acknowledges the receipt of your letter dated August 6,1992 (G02 189), by which you transmitted a complete reissuance of the Washington Nuclear _-

Project, Number 2 Contingency Plan, denoted as Revision 12 and dated August 5, 1992.

We find the page changes, as described in your cover letter, to be consistent with the provisions of 10 CFR Part 50.54(p). Accordingly, Revision 12 is considered acceptable as a replacement for your previously approved plan.

The attachments to your letters are being withheld from public disclosure because they contain Safeguards Information and must be protected in accordance with the provisions of 10 CFR Part 73.21.

Sincerely, Robert J. Pate, Chief Safeguards, Emergency Preparedness, and Non-Power Reactor Branch cc: Service List P. McKee, Chief, RSGB, NRR E. McPeek, PDRS, NRR Document Control Desk,ilQ WNP-2 NRC Resident Inspector NRR Docket File L. R. Norderhaug, RV RV/GMD M L REQUEST $0PY REQUEST C0PY SEND:TO PDR N9tderhaug RJPatA 4;/}// , DES /NO MES/NO YES[N0' I'

if/>f/92 12/s/92 110043 p

, ,p g ,

13 OL() 6319t Q 3 / &>

i ,-

Hr. G. C. Sorensen WPPSS Nuclear Project No. 2 Washington Public Power Supply System (WNP-2) cc:

Mr. J. W. Baker Regional Ad:ninistrator, Region V WNP-2 Plant Manager U.S. Nuclear Regulatory Comission Washington Public Power Supply System 1450 Haria Lane, Suite 210 P.O. Box 968, MD 927H Walnut Creek, California 94596 Richland, Washington 99352

6. E. C. Doupe Esq. Chairman Washingten Public Power Supply System Benton County Board of Comissioners 3000 George Washington Way P. O. Box 190 P. O. Box 968, MD 396 Prosser, Washington 99350-0190 Richland, Washington 99352 6 Mr. R. G. Waldo, Chairman Mr. R. C. Sorensen Energy Facility Site Evaluation Council U. S. Nuclear Regulatory Comission Mail Stop PY-ll P. O. Box 69 Olympia, Washington 98504 Richland, Washington 99352 Mr. Alan G. llosler, licensing Nanager Nicholas S. Reynolds. Esq.

Washington Public Power Supply System Winston & Strawn P. O. Box 968, MD PE21 1400 L Street, N.W.

Richland, Washington 99352 Washington, D.C. 20005-3502 Mr. J. V. Parrish, Assistant Managing Director for Operations Washington Public Power Supply System P. O. Box 968, MD 1023 Richland, Washington 99352 Mr. James C. Gearhart, Director  %[20/95 Quality Assurance Washington Public Power Supply System P. O. Box 968, MD 280 Richland, Washington 99352 i

Lod eat-<amo-ousesn - nace: 1o se co z1 m