Requests 60-day Extension for Submittal of Initial Abatement Rept & SCR
ML18153B061
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/30/1994
From: Marshall B
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: James Anderson
VIRGINIA, COMMONWEALTH OF
References
NUDOCS 9409150172
Download: ML18153B061 (1)


Text

BARD DELIVERED

  • Innsbrook Technical Center 5000 Dominion Boule1*ard Gle11 Allen. Virll,i11ia 23060 August 30, 1994 Mr. J. Meade R. Amerson, P.G. VIRGINIA POWER Department of Environmental Quality Piedloont Water Regional Office P.O. Box 6030 Glen Allen, VA 23058 RE: PC# 94-3824 StlRRY PCJ1ER STATIClf 1lNl)mGROONI) OIL RET,EASB SITE

~ Z A T I C l f REl?CRl' EXTDEIClf REQ)mT

Dear Mr. Amerson:

Due to complications with our investigation of the fuel oil release of May 9, 1994, at SUrry Power station, we requested am. received a sixty-day extension far sul:mittal of the Initial Abatement Report. '!he extension also applied to the Site Olara.cterization Report (SCR) , whim was originally due July 8, 1994.

We have made plans to install nDnitoring wells as the initial part of the SCR; however, due to nuclear-related activities in the vicinity of the fuel oil lines, we will not be able to begin drilling until approxilllately August 31, 1994. 'Ihe station recently canpleted a maintenance outage on Unit 2 during which they produced radioactive waste material. '!he station is currently processing the radioactive material am has prcx::essing equipnent installed in the yard area near the fuel oil lines. '!he waste processing equipnent is blocking acx:ess far the drilling rig. 'lhus, we request another 60 day extension far the sul:mittal of the SCR.

We appreciate your cooperation in this matter. Please contact Wes Sprouse at 273-3552 if you have any questions.

sincerely, B. M. Marshall, P.E.

Manager, Water (,)Jality cc: U. s. Nuclear Regulatory Ccmnission Region I I 101 Marietta st., NW suite 2900

  • Atlanta, GA 30323 Re: SUrry Units 1 & 2 Docket Nos. 50-280/50~281 License Nos. DPR-32/DPR-37 Nuclear Regulatory camnission Docunent Control Desk Washington, DC 20555 Re: SUrry Units 1 & 2 Docket Nos. 50-280/50-281 License Nos. DPR-32/DPR-37 Mr. M. W. Branch NRC Senior Resident Inspector.,____ _ _ _ _ _ _ _ _ _ _ _------,

SUrry Power station 9409150172 940830 PDR ADOCK 05000280 090009 p PDR