ML18153A267

From kanterella
Jump to navigation Jump to search
Requests Approval for Extended Compliance Schedule for Specific Provisions of Part III (9 Vac 25-91-130,Pollution Prevention Requirements) for Surry Nuclear Power Station
ML18153A267
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/22/1998
From: Hadder A
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Lilliard L
VIRGINIA, COMMONWEALTH OF
References
NUDOCS 9809290270
Download: ML18153A267 (3)


Text

, ..

e Innsbrook Tecbnical Center 5000 Dominioi1 Ho11le1*ard Glen A((en, Virginia 23060 Hand Delivered

.September 22, 1998 Mr. L. Samuel Lilliard VIRGINIA POWER Office of Spill Response and Remediation Virginia Department of Environmental Quality 629 East Main Street Richmond, VA 23240-0009 Re: AST REGULATIONS EXTENDED COMPLIANCE SCHEDULE - SURRY NUCLEAR POWER STATION (ODCP NO. FC-04-3535)

Dear.Mr. Lilliard:

In accordance with section 9VAC 25-91-40.B of the Facility and Aboveground Storage Tank (AST) Regulations, Virginia Power is requesting approval for an extended compliance schedule for specific provisions of Part III (9 VAC 25-91-130, Pollution Prevention Requirements) for Surry Nuclear Power Station. The facility has an aggregate oil storage capacity of less than 1 million gallons. The specific provisions and proposed compliance dates are as follows:

  • . Inventory control and testing for significant variations (9 VAC 25-91-130.B.1) will be completed by September 30, 1999. The major portion of the work required to comply consists of revising procedures and reviewing instrumentation systems.
  • Safe fill and shutdown practices (9 VAC 25-91-130.B.3) will be completed by September 30, 1999. The major portion of the work required to comply includes procedural and ~,*

possible equipment modifications.

  • Visual daily and weekly inspections (9 VAC 25-91-130.B.5) will be completed by February 28, 1999. Most of the provisions of this section are included in existing procedures, however, to include the remaining items will require procedure revisions.
  • Training of individuals (9 V AC 25-91-130.B.6) will be completed by September 30, Go O/

1999. A program is already in place and the personnei performing inspections are currently trained on the existing procedures. Once the procedures are revised to include the AST provisions, the training program will use the revised procedures in subsequent training sessions. The training must also be incorporated into the operator retraining program.

The primary reason in requesting approval of an extended compliance schedule is the method of operation practiced at the station as required by the NRC and necessitated by the safety concerns related to operating a nuclear power station. In order to assure safe operation of the station we operate through an extensive system of written procedures. In fact, the NRC requires compliance with approved station procedures and it is not appropriate for us to operate systems without an approved procedure in place. To comply with the previously specified provisions of the AST regulation we will need to revise an estimated 60 procedures.

( 9809290270 980922~'-=------'~-~-------

I PDR ADOCK 05000280 P PDR

Mr. L. Samuel Lilliard

. .... September 22, 1998 Page2 *

, Following the initial draft incorporating the pollution prevention requirements, each of the procedures must undergo an extensive review and approval process.

Additionally, modification of equipment is anticipated irt order to comply with some of the AST requirements. To perform the physical modifications, additional engineering will be required. The development of a Design Change Package (DCP) will be followed by a lengthy approval cycle. Then the actual modifications will be impleinented and inspected.

Drawings and procedures are then updated to reflect the new conditions. All equipment modifications must be documented and approved per NRC requirements, which requires additional time.

The schedule for implementing these changes (procedural and physical) is also affected by the station undergoing an outage during October and November and again in April and May.

Total dedication to the outage is required not only during the actual offline period, but for four to six weeks prior to the outage to prepare. The amount and scope of the major outage activities (e.g., refueling, equipment maintenance and replacements, system inspections) increases the time required to implement the changes.

Please contact Wes Sprouse at 273-3552 with any questions.

Sincerely, d.w.1~

A. W. Hadder Manager Environmental Policy & Compliance

Mr. L. Samuel Lilliard

. . -*"September 22, 1998 Page 3 cc:

U.S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth Street, SW Suite 23T85 Atlanta, GA. 30303 RE: Surry Units 1 and 2 Docket Nos. 50-280/50-281 License Nos. DPR-32/DPR-37 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 RE: Surry Units 1 and 2 Docket Nos. 50-280/50-281 License Nos. DPR-32/DPR-37

~r.R. A.~usser NRC Senior Resident Inspector Surry Power Station